| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$8,000.00 |
$17,250.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 423 | CY |
$12.00 |
$15.00 |
$28.75 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 145 | CY |
$15.00 |
$15.00 |
$28.75 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$6,000.00 |
$35,000.00 |
$11,500.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,595 | LF |
$5.00 |
$1.90 |
$1.55 |
| 6 | 221(F) 0100 |
TEMPORARY SILT DIKE | 100 | LF |
$10.00 |
$10.00 |
$8.05 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 3,075 | SY |
$2.00 |
$2.25 |
$1.84 |
| 8 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 10 | CY |
$60.00 |
$77.00 |
$177.09 |
| 9 | 307(K) 4300 |
STABILIZED SUBGRADE | 7,264 | SY |
$9.00 |
$8.00 |
$8.34 |
| 10 | 317 4270 |
CEMENT TREATED BASE | 5,216 | SY |
$15.00 |
$30.00 |
$18.11 |
| 11 | 408 5774 |
PRIME COAT | 1,411 | GAL |
$8.00 |
$12.70 |
$10.35 |
| 12 | 409(A) 4242 |
FABRIC REINFORCEMENT | 5,732 | SY |
$2.50 |
$4.23 |
$3.45 |
| 13 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 109 | TON |
$200.00 |
$375.00 |
$345.00 |
| 14 | 412 5267 |
COLD MILLING PAVEMENT | 64 | SY |
$12.00 |
$14.00 |
$34.50 |
| 15 | 414(A) 0210 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 3,594 | SY |
$15.00 |
$22.00 |
$29.90 |
| 16 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 2,533 | SY |
$21.00 |
$24.00 |
$41.40 |
| 17 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 1,533 | CY |
$135.00 |
$150.00 |
$189.41 |
| 18 | 414(J) 5263 |
TERMINAL JOINT SLEEPER SLAB | 26 | SY |
$110.00 |
$110.00 |
$71.90 |
| 19 | 504(E) 1381 |
CONCRETE PARAPET | 312 | LF |
$225.00 |
$150.00 |
$111.04 |
| 20 | 509(B) 0321 |
CLASS A CONCRETE | 29 | CY |
$700.00 |
$320.00 |
$533.97 |
| 21 | 511(A) 0332 |
REINFORCING STEEL | 3,880 | LB |
$1.00 |
$1.60 |
$1.28 |
| 22 | 609(A) 0288 |
CONCRETE CURB (6" MNTBLE-INTEGRAL) | 409 | LF |
$15.00 |
$8.00 |
$14.38 |
| 23 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$4,000.00 |
$1,000.00 |
$11,500.00 |
| 24 | 619(B) 4727 |
REMOVAL OF CONCRETE PAVEMENT | 3,232 | SY |
$10.00 |
$12.00 |
$17.25 |
| 25 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 1,618 | SY |
$7.00 |
$9.16 |
$9.20 |
| 26 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 1,032 | LF |
$5.00 |
$4.15 |
$3.52 |
| 27 | 619(B) 4791 |
REMOVAL OF CURB | 409 | LF |
$8.00 |
$13.57 |
$17.25 |
| 28 | 619(H) 0200 |
CLEAN STORM DRAIN, 12" TO 30" DIAMETER | 188 | LF |
$20.00 |
$14.09 |
$57.50 |
| 29 | 623 0100 |
(PL)GUARDRAIL CURBING | 7 | EA |
$1,500.00 |
$729.50 |
$2,875.00 |
| 30 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 758 | LF |
$20.00 |
$20.41 |
$16.10 |
| 31 | 623(F) 8300 |
GUARDRAIL TRAIL END TURNDOWN (31") | 3 | EA |
$2,500.00 |
$1,277.67 |
$1,043.05 |
| 32 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 2 | EA |
$3,000.00 |
$3,068.10 |
$2,495.50 |
| 33 | 623(I) 8690 |
GUARDRAIL BRIDGE CONN-TRAIL END (31") | 3 | EA |
$2,000.00 |
$2,255.29 |
$1,828.50 |
| 34 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,500.00 |
$2,814.53 |
$2,297.70 |
| 35 | 871(A) 8330 |
(PL) IMPACT ATTENUATOR | 2 | EA |
$22,000.00 |
$28,807.38 |
$24,610.00 |
| 36 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 100 | CY |
$12.00 |
$15.32 |
$28.75 |
| 37 | 202(D) 0184 |
UNCLASSIFIED BORROW | 73 | CY |
$15.00 |
$32.07 |
$57.50 |
| 38 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,808 | LF |
$5.00 |
$1.90 |
$1.55 |
| 39 | 221(F) 0100 |
TEMPORARY SILT DIKE | 110 | LF |
$10.00 |
$9.86 |
$8.05 |
| 40 | 230(A) 2806 |
SOLID SLAB SODDING | 1,861 | SY |
$2.50 |
$2.25 |
$1.84 |
| 41 | 307(K) 4300 |
STABILIZED SUBGRADE | 1,139 | SY |
$9.00 |
$8.04 |
$8.34 |
| 42 | 317 4270 |
CEMENT TREATED BASE | 994 | SY |
$18.00 |
$30.00 |
$18.11 |
| 43 | 408 5774 |
PRIME COAT | 280 | GAL |
$8.00 |
$12.68 |
$10.35 |
| 44 | 409(A) 4242 |
FABRIC REINFORCEMENT | 1,139 | SY |
$1.75 |
$4.23 |
$3.45 |
| 45 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 245 | TON |
$200.00 |
$422.60 |
$345.00 |
| 46 | 414(A) 0210 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 372 | SY |
$19.00 |
$22.00 |
$34.50 |
| 47 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 407 | SY |
$24.00 |
$24.00 |
$46.00 |
| 48 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 195 | CY |
$135.00 |
$150.00 |
$172.50 |
| 49 | 504(E) 1381 |
CONCRETE PARAPET | 235 | LF |
$225.00 |
$150.00 |
$111.04 |
| 50 | 509(B) 0321 |
CLASS A CONCRETE | 22 | CY |
$700.00 |
$320.00 |
$533.97 |
| 51 | 511(A) 0332 |
REINFORCING STEEL | 2,940 | LB |
$1.00 |
$1.64 |
$1.28 |
| 52 | 609(A) 0288 |
CONCRETE CURB (6" MNTBLE-INTEGRAL) | 251 | LF |
$15.00 |
$8.14 |
$17.25 |
| 53 | 613(B) 0689 |
18" CORR. GALV. STEEL PIPE | 72 | LF |
$40.00 |
$53.86 |
$29.58 |
| 54 | 613(L) 5726 |
18" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$400.00 |
$346.72 |
$406.45 |
| 55 | 619(B) 4727 |
REMOVAL OF CONCRETE PAVEMENT | 407 | SY |
$10.00 |
$12.00 |
$17.25 |
| 56 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 629 | SY |
$7.00 |
$9.16 |
$9.20 |
| 57 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 1,180 | LF |
$5.00 |
$4.15 |
$3.52 |
| 58 | 619(B) 4791 |
REMOVAL OF CURB | 1,031 | LF |
$8.00 |
$13.57 |
$17.25 |
| 59 | 619(B) 5918 |
REMOVAL OF EXISTING PIPE | 72 | LF |
$15.00 |
$5.13 |
$23.00 |
| 60 | 623 0100 |
(PL)GUARDRAIL CURBING | 4 | EA |
$1,500.00 |
$2,213.29 |
$2,875.00 |
| 61 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 700 | LF |
$20.00 |
$20.41 |
$16.10 |
| 62 | 623(F) 8300 |
GUARDRAIL TRAIL END TURNDOWN (31") | 1 | EA |
$2,500.00 |
$1,277.67 |
$1,043.05 |
| 63 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$3,000.00 |
$3,068.09 |
$2,495.50 |
| 64 | 623(I) 8690 |
GUARDRAIL BRIDGE CONN-TRAIL END (31") | 1 | EA |
$2,000.00 |
$2,255.29 |
$1,828.50 |
| 65 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,500.00 |
$2,814.53 |
$2,297.70 |
| 66 | 871(A) 8330 |
(PL) IMPACT ATTENUATOR | 2 | EA |
$22,000.00 |
$28,807.38 |
$24,610.00 |
| 67 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 205 | CY |
$20.00 |
$17.95 |
$17.25 |
| 68 | 501(G) 6309 |
CLSM BACKFILL | 182 | CY |
$170.00 |
$149.08 |
$151.41 |
| 69 | 504(A) 1304 |
APPROACH SLAB | 238.8 | SY |
$250.00 |
$209.69 |
$216.81 |
| 70 | 504(B) 1305 |
SAW-CUT GROOVING | 742.2 | SY |
$5.00 |
$5.07 |
$4.37 |
| 71 | 504(C) 6250 |
SEALED EXPANSION JOINT | 71.8 | LF |
$350.00 |
$299.84 |
$315.34 |
| 72 | 504(E) 6190 |
42" F-SHAPED PARAPET | 602.4 | LF |
$200.00 |
$157.79 |
$117.43 |
| 73 | 506(A) 1322 |
STRUCTURAL STEEL | 142,990 | LB |
$2.50 |
$2.10 |
$2.80 |
| 74 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$2,800.00 |
$3,538.57 |
$2,865.40 |
| 75 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 9 | EA |
$2,800.00 |
$3,152.66 |
$3,835.80 |
| 76 | 509(A) 1326 |
CLASS AA CONCRETE | 137.7 | CY |
$750.00 |
$995.00 |
$597.73 |
| 77 | 509(B) 1328 |
CLASS A CONCRETE | 157.4 | CY |
$700.00 |
$739.27 |
$562.72 |
| 78 | 509(D) 1331 |
CLASS C CONCRETE | 9.1 | CY |
$500.00 |
$1,043.86 |
$537.73 |
| 79 | 510(C) 6138 |
SLOPE WALL (5") | 829 | SY |
$120.00 |
$123.94 |
$109.83 |
| 80 | 511(A) 1332 |
REINFORCING STEEL | 620 | LB |
$1.00 |
$1.25 |
$1.17 |
| 81 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 68,530 | LB |
$1.20 |
$1.33 |
$1.29 |
| 82 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 1,007 | LF |
$36.00 |
$39.20 |
$43.94 |
| 83 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 1,007 | LF |
$18.00 |
$32.25 |
$23.00 |
| 84 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 579 | SY |
$4.00 |
$4.93 |
$3.39 |
| 85 | 516(A) 6094 |
DRILLED SHAFTS 48" DIAMETER | 180 | LF |
$500.00 |
$488.12 |
$1,227.84 |
| 86 | 523(A) 6550 |
SEALER CRACK PREPARATION | 140.5 | LF |
$4.00 |
$5.63 |
$4.83 |
| 87 | 523(B) 6560 |
SEALER RESIN | 2 | GAL |
$90.00 |
$140.87 |
$230.00 |
| 88 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 252 | LF |
$25.00 |
$21.69 |
$19.00 |
| 89 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 102 | LF |
$25.00 |
$27.52 |
$19.00 |
| 90 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$50,000.00 |
$75,000.00 |
$411,700.00 |
| 91 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 125 | CY |
$20.00 |
$17.95 |
$17.25 |
| 92 | 501(G) 6309 |
CLSM BACKFILL | 169 | CY |
$170.00 |
$149.46 |
$151.41 |
| 93 | 502(A) 6173 |
ENGINEERED FALSEWORK | 1 | LSUM |
$90,000.00 |
$125,000.00 |
$176,074.20 |
| 94 | 504(A) 1304 |
APPROACH SLAB | 228 | SY |
$250.00 |
$220.24 |
$218.38 |
| 95 | 504(B) 1305 |
SAW-CUT GROOVING | 655.9 | SY |
$5.00 |
$5.07 |
$4.37 |
| 96 | 504(C) 6250 |
SEALED EXPANSION JOINT | 76.3 | LF |
$350.00 |
$299.85 |
$315.34 |
| 97 | 504(E) 6190 |
42" F-SHAPED PARAPET | 369.8 | LF |
$225.00 |
$208.51 |
$116.30 |
| 98 | 506(A) 1322 |
STRUCTURAL STEEL | 2,130 | LB |
$4.00 |
$4.11 |
$5.38 |
| 99 | 507(C) 6282 |
ELASTOMERIC BEARING PADS | 38 | EA |
$300.00 |
$507.08 |
$997.92 |
| 100 | 509 6153 |
SPECIAL CONCRETE FINISH | 1 | LSUM |
$30,000.00 |
$11,315.17 |
$40,250.00 |
| 101 | 509(A) 1326 |
CLASS AA CONCRETE | 318.9 | CY |
$1,100.00 |
$975.00 |
$827.73 |
| 102 | 509(B) 1328 |
CLASS A CONCRETE | 67.9 | CY |
$700.00 |
$775.00 |
$763.97 |
| 103 | 510(C) 6137 |
SLOPE WALL (4") | 16 | SY |
$120.00 |
$107.14 |
$109.27 |
| 104 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 96,720 | LB |
$1.20 |
$1.33 |
$1.29 |
| 105 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 382 | SY |
$4.00 |
$4.93 |
$3.39 |
| 106 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 65 | LF |
$30.00 |
$50.71 |
$42.55 |
| 107 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 7 | GAL |
$80.00 |
$28.17 |
$23.00 |
| 108 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 5 | SY |
$800.00 |
$1,246.68 |
$1,035.00 |
| 109 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 63 | LF |
$25.00 |
$21.69 |
$19.00 |
| 110 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 34 | LF |
$25.00 |
$27.54 |
$19.00 |
| 111 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$70,000.00 |
$75,000.00 |
$385,250.00 |
| 112 | 202(D) 1302 |
UNCLASSIFIED BORROW | 120 | CY |
$20.00 |
$15.60 |
$97.75 |
| 113 | 501(G) 6309 |
CLSM BACKFILL | 122 | CY |
$170.00 |
$148.96 |
$266.41 |
| 114 | 504(A) 1304 |
APPROACH SLAB | 180.4 | SY |
$250.00 |
$212.73 |
$216.75 |
| 115 | 504(B) 1305 |
SAW-CUT GROOVING | 495.5 | SY |
$5.00 |
$5.07 |
$4.37 |
| 116 | 504(C) 6250 |
SEALED EXPANSION JOINT | 62.4 | LF |
$350.00 |
$299.85 |
$378.59 |
| 117 | 504(E) 6190 |
42" F-SHAPED PARAPET | 404.8 | LF |
$225.00 |
$209.31 |
$116.86 |
| 118 | 509 6153 |
SPECIAL CONCRETE FINISH | 1 | LSUM |
$20,000.00 |
$10,955.75 |
$40,250.00 |
| 119 | 509(A) 1326 |
CLASS AA CONCRETE | 89.6 | CY |
$900.00 |
$975.00 |
$1,287.73 |
| 120 | 509(D) 1331 |
CLASS C CONCRETE | 5.2 | CY |
$500.00 |
$1,050.21 |
$872.71 |
| 121 | 510(C) 6138 |
SLOPE WALL (5") | 230 | SY |
$120.00 |
$124.21 |
$109.83 |
| 122 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 28,530 | LB |
$1.20 |
$1.33 |
$1.52 |
| 123 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$40,000.00 |
$44,647.93 |
$37,950.00 |
| 124 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$10,000.00 |
$2,746.91 |
$2,507.00 |
| 125 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 385 | SY |
$4.00 |
$4.93 |
$3.39 |
| 126 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 58.9 | LF |
$30.00 |
$50.71 |
$42.55 |
| 127 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 6 | GAL |
$80.00 |
$28.17 |
$23.00 |
| 128 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 20.7 | SY |
$800.00 |
$1,112.85 |
$920.00 |
| 129 | 545 4805 |
(PL)REPLACE BRIDGE ITEMS | 6 | EA |
$900.00 |
$2,408.83 |
$1,725.00 |
| 130 | 619(B) 2510 |
REMOVAL OF BRIDGE ITEM (TYPE A) | 1 | LSUM |
$50,000.00 |
$55,000.00 |
$69,000.00 |
| 131 | 619(B) 2525 |
REMOVAL OF BRIDGE ITEM (TYPE B) | 8 | EA |
$700.00 |
$952.26 |
$1,725.00 |
| 132 | 501(G) 6309 |
CLSM BACKFILL | 20 | CY |
$300.00 |
$537.74 |
$323.91 |
| 133 | 504(B) 1305 |
SAW-CUT GROOVING | 919 | SY |
$5.00 |
$5.07 |
$4.37 |
| 134 | 504(E) 6190 |
42" F-SHAPED PARAPET | 565.8 | LF |
$225.00 |
$250.14 |
$148.43 |
| 135 | 504(G) 6390 |
RAPID CURE JOINT SEALANT | 76.1 | LF |
$30.00 |
$27.12 |
$40.25 |
| 136 | 505(A) 6065 |
BRIDGE DECK CONCRETE OVERLAY | 971.4 | SY |
$120.00 |
$152.17 |
$180.55 |
| 137 | 505(E) 1000 |
HYDRODEMOLITION | 1,008.4 | SY |
$100.00 |
$205.19 |
$143.75 |
| 138 | 509 6153 |
SPECIAL CONCRETE FINISH | 1 | LSUM |
$70,000.00 |
$65,000.00 |
$75,900.00 |
| 139 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$7,000.00 |
$7,000.00 |
$4,830.00 |
| 140 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$5,000.00 |
$4,500.00 |
$977.50 |
| 141 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,560 | SY |
$4.00 |
$4.93 |
$3.39 |
| 142 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 108.5 | LF |
$50.00 |
$50.71 |
$42.55 |
| 143 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 12 | GAL |
$120.00 |
$28.17 |
$23.00 |
| 144 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 43.4 | SY |
$800.00 |
$1,001.57 |
$862.50 |
| 145 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$40,000.00 |
$45,000.00 |
$66,125.00 |
| 146 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 10,000 | LF |
$0.2000 |
$0.3200 |
$0.2700 |
| 147 | 857(C) 8851 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 43,938 | LF |
$0.7000 |
$1.10 |
$0.9000 |
| 148 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 3,002 | EA |
$0.6000 |
$0.6500 |
$0.5300 |
| 149 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 34,500 | LF |
$0.3000 |
$0.1100 |
$0.1400 |
| 150 | 876(A) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 140 | SD |
$16.47 |
$14.09 |
$11.50 |
| 151 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 7,525 | LF |
$22.00 |
$21.00 |
$17.25 |
| 152 | 878(B) 8487 |
MODULAR GLARE SCREEN (TEMPORARY) | 792,000 | SD |
$0.1500 |
$0.0300 |
$0.0200 |
| 153 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 1,270 | SD |
$2.79 |
$4.23 |
$3.45 |
| 154 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 164,175 | SD |
$0.5000 |
$0.0700 |
$0.0600 |
| 155 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 28,935 | SD |
$1.00 |
$0.0700 |
$0.0600 |
| 156 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 28,195 | SD |
$1.50 |
$0.1400 |
$0.1200 |
| 157 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 38,695 | SD |
$0.5000 |
$0.0700 |
$0.0600 |
| 158 | 880(C) 8848 |
WING BARRICADES | 4,050 | SD |
$0.3300 |
$0.0700 |
$0.0600 |
| 159 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 34,750 | SD |
$0.1000 |
$0.8500 |
$0.6900 |
| 160 | 880(F) 8878 |
DRUMS | 142,305 | SD |
$0.2500 |
$0.0300 |
$0.0200 |
| 161 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 3,060 | SD |
$20.00 |
$7.04 |
$0.7800 |
| 162 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 46,421 | LF |
$0.6200 |
$0.9600 |
$0.7800 |
| 163 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 3,200 | LF |
$1.25 |
$1.92 |
$1.56 |
| 164 | 619(B) 5190 |
REMOVAL OF CABLE BARRIER | 1,232 | LF |
$5.00 |
$10.00 |
$97.75 |
| 165 | 628(B) 5125 |
HIGH-TENSION CABLE BARRIER(TL-4) | 1,232 | LF |
$12.00 |
$15.00 |
$1.73 |
| 166 | 628(C) 5110 |
END ANCHORS | 4 | EA |
$2,000.00 |
$7,747.71 |
$6,325.00 |
| 167 | 628(E) 5175 |
CABLE BARRIER TENSION METER | 1 | EA |
$2,000.00 |
$5,071.23 |
$4,140.00 |
| 168 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$35,000.00 |
$40,499.37 |
$33,062.50 |
| 169 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$7,000.00 |
$6,067.99 |
$11,500.00 |
| 170 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$295,000.00 |
$280,000.00 |
$300,183.40 |