| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$19,750.00 |
$20,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$63,500.00 |
$81,955.00 |
$72,000.00 |
| 3 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,000 | LF |
$2.50 |
$1.65 |
$1.80 |
| 4 | 221(F) 0100 |
TEMPORARY SILT DIKE | 300 | LF |
$6.00 |
$8.00 |
$9.00 |
| 5 | 230(A) 2806 |
SOLID SLAB SODDING | 10,400 | SY |
$2.50 |
$1.60 |
$1.90 |
| 6 | 233(A) 2817 |
VEGETATIVE MULCHING | 4.3 | AC |
$500.00 |
$350.00 |
$800.00 |
| 7 | 307(K) 4300 |
STABILIZED SUBGRADE | 3,200 | SY |
$7.07 |
$8.25 |
$11.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 16 | TON |
$30.00 |
$43.26 |
$100.00 |
| 9 | 408 5774 |
PRIME COAT | 1,120 | GAL |
$4.50 |
$4.00 |
$8.00 |
| 10 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$300.00 |
$282.50 |
$350.00 |
| 11 | 613(B) 4527 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 34 | LF |
$50.00 |
$29.00 |
$80.00 |
| 12 | 613(L) 4504 |
21" X 15" PREFAB. CULVERT END SECTION, ARCH | 2 | EA |
$300.00 |
$300.00 |
$1,000.00 |
| 13 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 230 | CY |
$15.00 |
$8.75 |
$25.00 |
| 14 | 501(F) 6352 |
GRANULAR BACKFILL | 138 | CY |
$50.00 |
$65.00 |
$80.00 |
| 15 | 503(A) 6290 |
PRESTRESSED CONCRETE BEAMS (TYPE J BT) | 374 | LF |
$300.00 |
$365.00 |
$250.00 |
| 16 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 344.5 | LF |
$60.00 |
$78.00 |
$80.00 |
| 17 | 506(A) 1322 |
STRUCTURAL STEEL | 1,100 | LB |
$3.00 |
$3.00 |
$3.00 |
| 18 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 3 | EA |
$750.00 |
$1,042.00 |
$1,000.00 |
| 19 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 3 | EA |
$800.00 |
$1,042.00 |
$1,000.00 |
| 20 | 509(A) 1326 |
CLASS AA CONCRETE | 112.8 | CY |
$550.00 |
$607.50 |
$590.00 |
| 21 | 509(B) 1328 |
CLASS A CONCRETE | 93.6 | CY |
$500.00 |
$642.50 |
$650.00 |
| 22 | 511(A) 1332 |
REINFORCING STEEL | 40,930 | LB |
$1.00 |
$0.9300 |
$1.50 |
| 23 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 88 | LF |
$30.00 |
$37.10 |
$25.00 |
| 24 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 224 | LF |
$35.00 |
$44.80 |
$32.00 |
| 25 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 88 | LF |
$12.00 |
$15.90 |
$35.00 |
| 26 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 224 | LF |
$14.00 |
$19.20 |
$35.00 |
| 27 | 514(K) 6260 |
(PL)PILOT HOLES | 156 | LF |
$100.00 |
$150.00 |
$140.00 |
| 28 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 3,111 | TON |
$35.00 |
$33.74 |
$40.00 |
| 29 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 791 | TON |
$30.00 |
$27.95 |
$35.00 |
| 30 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 60 | LF |
$20.00 |
$35.00 |
$25.00 |
| 31 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 50 | LF |
$20.00 |
$35.00 |
$25.00 |
| 32 | 623(A) 1418 |
BEAM GUARDRAIL W-BEAM SINGLE | 200 | LF |
$15.00 |
$18.98 |
$23.00 |
| 33 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,500.00 |
$1,538.52 |
$1,800.00 |
| 34 | 623(F) 6030 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 4 | EA |
$1,000.00 |
$1,164.00 |
$1,400.00 |
| 35 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$3,000.00 |
$3,500.00 |
| 36 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$11,500.00 |
$8,750.00 |
$15,000.00 |
| 37 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$4,000.00 |
$3,500.00 |
| 38 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$52,000.00 |
$56,400.00 |
$30,000.00 |