ODOT Bid Results

Feb 2011 · 57 let jobs Sign up free
57Let jobs
$151,940,557Total low bids
$74,017,161Total estimates
+105.3%Low bids vs estimates

Feb 2011 results

Bid tabs (Excel) ExcelCSV
Let dateContractCounty / DistrictProject EstimateLow bidLow bidder% vs est.Bidders
Feb 17, 2011 110205IM-TIGR(497)SS Tulsa
Division 8
BRIDGE AND APPROACHES I -244: OVER THE ARKANSAS RIVER , IN THE CITY OF TULSA. PROJECT LENGTH = 0.968 MILES · — $63,637,568 MANHATTAN ROAD & BRIDGE COMPANY, LLC 3
Feb 17, 2011 110015STP-157A(143)IG Osage, Tulsa
GRADE, DRAIN, AND SURFACE GILCREASE WEST EXPRESSWAY : FROM 41ST AVE , EXTEND EAST IN THE CITY OF TULSA. PROJECT LENGTH = 2.1774 MILES · $8,062,658 $7,781,954 BECCO CONTRACTORS, INC. -3.5% 4
Feb 17, 2011 110022BRFY-110B(170) Stpy-110b(232)
26499(04) SSP-110B(218)SS 24806(04) CIRB-110C(204)RB CARTER GRADE, DRAIN, SURFACE , AND BRIDGE US-70: FROM MERIDAN RD IN LONE GROVE, EXTEND EAST. CITY STREET (MERIDIAN RD): FROM US-70, EXT N IN LONE GROVE . PROJECT LENGTH = 1.694 MILES · $6,199,364 $6,498,226 Silver Star Construction Company, Inc. +4.8% 5
Feb 17, 2011 110097STPY-125C(202)3P Stpy-125c(203)3p
28212(06) STPY-125C(204)3P GARVIN RESURFACE (ASPHALT ) US-77: FROM THE MURRAY COUNTY LINE EXTEND NORTH . PROJECT LENGTH = 19.57 MILES · $4,060,262 $3,660,027 HASKELL LEMON CONSTRUCTION CO. -9.9% 6
Feb 17, 2011 110050STPY-119B(207)3P Stpy-119b(208)3p
CREEK RESURFACE (ASPHALT ) SH-33: FROM 3.0 MILES WEST OF THE SH -48 JUNCTION, EXTEND EAST. PROJECT LENGTH = 13.14 MILES · $3,516,340 $3,293,426 THE QUAPAW COMPANY -6.3% 7
Feb 17, 2011 110213NHY-021N(053)3P Nhy-011n(091)3p
STEPHENS RESURFACE (ASPHALT ) SH-7: FROM THE COMANCHE COUNTY LINE , EXTEND EAST. US-81: FROM THE SH-7W JUNCTION, EXTEND NORTH . PROJECT LENGTH = 6.9 MILES · — $3,199,135 T & G CONSTRUCTION, INC. 4
Feb 17, 2011 110051SSP-102C(112)SS Alfalfa
Division 6
GRADE, DRAIN, SURFACE , AND BRIDGE US-64: FROM 5.0 MILES EAST OF THE WOODS COUNTY LINE, EXTEND EAST. PROJECT LENGTH = 1.188 MILES · — $3,184,455 Venture Corporation dba VCO Paving 4
Feb 17, 2011 110124STPY-158B(188)3P Stpy-158a(189)3p
OTTAWA RESURFACE (ASPHALT ) US-69A: FROM THE US -69 JUNCTION, EXTEND EAST. US-69: FROM THE SH-10E JUNCTION, EXTEND NORTH . PROJECT LENGTH = 14.40 MILES · $3,490,633 $3,074,815 GLOVER & ASSOCIATES, INC. -11.9% 3
Feb 17, 2011 110171NHY-013N(149)3P Nhy-013n(151)3p
MUSKOGEE RESURFACE (ASPHALT ) US-69: FROM THE MCINTOSH COUNTY LINE , EXTEND NORTH . AND FROM 0.5 MILES NORTH OF THE US -64, EXTEND NORTH . PROJECT LENGTH = 16.45 MILES · $3,112,686 $3,036,841 GLOVER & ASSOCIATES, INC. -2.4% 2
Feb 17, 2011 110031NHY-017N(234)3P Beaver, Texas
RESURFACE (ASPHALT ) SH-3: FROM 6.0 MILES WEST OF THE TEXAS /BEAVER COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 8.0 MILES · $3,404,540 $2,953,226 J & R SAND COMPANY, INC. -13.3% 4
Feb 17, 2011 110174IMY-0040-6(372)303 Sequoyah
Division 1
RESURFACE (ASPHALT ) I-40: FROM DWIGHT MISSION ROAD , EXTEND EAST IN THE CITY OF SALLISAW . PROJECT LENGTH = 7.67 MILES · $2,722,501 $2,562,620 JOB CONSTRUCTION CO., INC. -5.9% 4
Feb 17, 2011 110088STPY-138C(184)3P Stpy-138c(185)3p
KIOWA RESURFACE (ASPHALT ) SH-54: BEGIN AT THE SH -9 JCT EXTEND SOUTH . PROJECT LENGTH = 16.0 MILES · — $2,501,668 CORNELL CONSTRUCTION COMPANY, INC. 3
Feb 17, 2011 110148NHY-008N(082)3P Texas
Division 6
RESURFACE (ASPHALT ) US-54: FROM 0.75 MILES NORTHEAST OF THE TEXAS STATE LINE , EXTEND NORTHEAST . PROJECT LENGTH = 8.0 MILES · — $2,177,162 HIGHWAY CONTRACTORS, INC. 3
Feb 17, 2011 110125STPY-131C(109) Stpy-131b(110)3p
28291(05) STPY-131B(111)3P HASKELL PAVEMENT REHABILITATION AND RESURFACE (ASPHALT ) SH-31: AT THE SH-2 JUNCTION IN THE CITY OF KINTA . SH-2: FROM JUST NORTH OF SH -31 IN THE CITY OF KINITA EXTEND NORTH. PROJECT LENGTH = 10.08 MILES · $2,216,654 $2,145,997 GLOVER & ASSOCIATES, INC. -3.2% 4
Feb 17, 2011 110122NHY-018N(060)3P Osage
Division 8
RESURFACE (ASPHALT ) US-60: FROM THE SH -18 JUNCTION, EXTEND EAST. PROJECT LENGTH = 6.63 MILES · $2,039,687 $1,880,569 APAC-CENTRAL, INC. -7.8% 3
Feb 17, 2011 110098STPY-126C(188)3P Nhy-011n(090)3p
28089(04) STPY-126C(185) GRADY RESURFACE (ASPHALT ) SH-17: FROM 1.02 MILES WEST OF US -81, EXTEND EAST. US-81: FROM SH-17, EXTEND SOUTH. PROJECT LENGTH = 6.6 MILES · $1,993,978 $1,834,143 T & G CONSTRUCTION, INC. -8.0% 6
Feb 17, 2011 110083STPY-137B(100)3P Stpy-137b(104)3p
KINGFISHER RESURFACE (ASPHALT ) SH-33: FROM 1.0 MILE EAST OF THE US -81 JUNCTION, EXTEND EAST. PROJECT LENGTH = 13.37 MILES · $1,767,000 $1,816,546 HASKELL LEMON CONSTRUCTION CO. +2.8% 2
Feb 17, 2011 110038IMY-0240-1(356)0003P Stpy-142c(210)3p
28239(04) STPY-109C(175)3P CANADIAN, LOGAN, OKLAHOMA RESURFACE (UTBWC) SH-152: FROM 5.25 MI EAST OF US -81, EXTEND EAST. SH-74: FROM SH-74C, EXTEND NORTH . I-240: FROM I-44, EXTEND EAST. PROJECT LENGTH = 15.96 MILES · $2,040,393 $1,755,503 HASKELL LEMON CONSTRUCTION CO. -14.0% 2
Feb 17, 2011 110096STPY-144C(160)3P Stpy-144c(161)3p
28214(06) STPY-144C(162)3P MCCLAIN RESURFACE (ASPHALT ) US-77: FROM THE GARVIN COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 10.41 MILES · — $1,667,635 HASKELL LEMON CONSTRUCTION CO. 4
Feb 17, 2011 110054STPY-119B(211)3P Stpy-119c(212)3p
CREEK RESURFACE (ASPHALT ) SH-51: FROM THE SH -99 JUNCTION, EXTEND EAST. SH-99: FROM THE SH-33 JUNCTION, EXTEND EAST. PROJECT LENGTH = 10.26 MILES · $1,753,401 $1,636,271 THE QUAPAW COMPANY -6.7% 6
Feb 17, 2011 110121STPY-127B(181)3P Stpy-127b(183)3p
GRANT RESURFACE (ASPHALT ) US-81: FROM SH-11 EXTEND NORTH TO THE KANSAS STATE LINE. PROJECT LENGTH = 14.34 MILES · $1,298,000 $1,543,125 THE CUMMINS CONSTRUCTION CO., INC. +18.9% 4
Feb 17, 2011 110123STPY-158C(187)3P Ottawa
Division 8
RESURFACE (ASPHALT ) SH-125: FROM 1.75 MILES NORTH OF THE US -60 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 6.45 MILES · — $1,490,758 GLOVER & ASSOCIATES, INC. 3
Feb 17, 2011 110172STP-124B(079)UR Garfield
Division 4
GRADE, DRAIN, SURFACE , AND TRAFFIC SIGNAL CITY STREET (OAKWOOD ROAD): AT THE INTERSECTION OF WILLOW ROAD IN THE CITY OF ENID . PROJECT LENGTH = 0.338 MILES · $1,376,194 $1,458,679 TOM HUDSON PAVING, INC. +6.0% 3
Feb 17, 2011 110101NHY-013N(150)3P Mcintosh
Division 1
RESURFACE (ASPHALT ) US-69: FROM JUST NORTH OF I -40, EXTEND NORTH . PROJECT LENGTH : 4.04 MILES · $1,551,571 $1,453,998 GLOVER & ASSOCIATES, INC. -6.3% 3
Feb 17, 2011 110210SBR-162A(217)SB Sbr-162b(218)sb
PONTOTOC BRIDGE REHABILITATION SH -1: OVER SH-3, 1.0 MILE SOUTH OF ADA . SH-3W: OVER SH-19, 1.5 MILES EAST OF THE SH -1 JUNCTION. · $1,863,034 $1,437,855 OBC, INC. -22.8% 7
Feb 17, 2011 110078STPY-132B(150)3P Hughes
Division 3
RESURFACE (ASPHALT ) US-270: FROM THE US -270B JUNCTION, EXTEND EAST. PROJECT LENGTH = 6.79 MILES · $1,398,246 $1,373,859 HASKELL LEMON CONSTRUCTION CO. -1.7% 3
Feb 17, 2011 110047NHY-020N(039)3P Comanche
Division 7
RESURFACE (ASPHALT ) US-62: FROM 0.17 MILES NORTH OF THE US -277 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 4.83 MILES · $1,432,162 $1,352,562 T & G CONSTRUCTION, INC. -5.6% 3
Feb 17, 2011 110160NHY-017N(236)3P Woodward
Division 6
RESURFACE (UTBWC) US-183: BEGIN 0.75 MILE NORTH OF US -412 IN WOODWARD EXTEND NORTH . PROJECT LENGTH = 7.50 MILES · $1,391,520 $1,295,929 J & R SAND COMPANY, INC. -6.9% 2
Feb 17, 2011 110113NHY-018N(059)3P Nowata
Division 8
RESURFACE (ASPHALT ) US-60: FROM 2.90 MILES EAST OF THE US -169 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.0 MILES · $1,227,032 $1,282,061 APAC-CENTRAL, INC. +4.5% 3
Feb 17, 2011 110035STPY-104C(074)3P Beaver
Division 6
RESURFACE (ASPHALT ) US-270: FROM 7.2 MI. SOUTH OF US-64 JUNCTION, EXTEND SOUTH. PROJECT LENGTH = 7.00 MILES · $1,081,349 $1,248,423 J & R SAND COMPANY, INC. +15.5% 3
Feb 17, 2011 110065STPY-125C(205)3P Garvin
Division 3
RESURFACE (ASPHALT ) SH-74: FROM THE SH -29 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 8.0 MILES · $1,440,269 $1,212,615 Silver Star Construction Company, Inc. -15.8% 4
Feb 17, 2011 110156STPY-175C(129)3P Custer, Washita
RESURFACE (ASPHALT ) SH-54: FROM 8.0 MILES NORTH OF THE SH -152 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 7.85 MILES · $1,225,128 $1,207,488 CASWELL CONSTRUCTION, INC. -1.4% 4
Feb 17, 2011 110063NHY-021N(055)3P Garvin
Division 3
RESURFACE (ASPHALT ) SH-7: FROM THE MURRAY COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 4.02 MILES · $1,371,018 $1,165,525 Silver Star Construction Company, Inc. -15.0% 4
Feb 17, 2011 110120STPY-157B(179)3P Stpy-157b(180)3p
OSAGE RESURFACE (ASPHALT ) SH-11: FROM THE SH -99 JUNCTION, EXTEND EAST. PROJECT LENGTH = 10.72 MILES · $1,182,962 $1,129,277 APAC-CENTRAL, INC. -4.5% 4
Feb 17, 2011 110126STPY-159C(107)3P Pawnee
Division 8
RESURFACE (ASPHALT ) US-64: FROM THE NOBLE COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 7.29 MILES · — $1,104,551 APAC-CENTRAL, INC. 2
Feb 17, 2011 110084STPY-137C(101)3P Kingfisher
Division 4
RESURFACE (ASPHALT ) SH-51: FROM THE BLAINE COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 7.65 MILES · $930,486 $1,071,109 HASKELL LEMON CONSTRUCTION CO. +15.1% 3
Feb 17, 2011 110087STPY-138A(183)3P Kiowa
Division 5
RESURFACE (ASPHALT ) US-183: FROM 4.9 MILES SOUTH OF THE SH -9W JUNCTION, EXTEND NORTH . PROJECT LENGTH = 4.70 MILES · $1,094,348 $1,037,471 APAC-CENTRAL, INC. -5.2% 3
Feb 17, 2011 110045STPY-115C(106)3P Coal
Division 3
RESURFACE (ASPHALT ) SH-48: FROM JOHNSTON COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 6.45 MILES · — $961,292 R. K. Hall, LLC 2
Feb 17, 2011 110175SBR-169N(159)SB Stephens
Division 7
BRIDGE REHABILITATION SH -7: OVER LITTLE BEAVER CREEK , 5.45 MILES EAST OF THE COMANCHE COUNTY LINE . · $850,836 $870,509 K & R BUILDERS, INC. +2.3% 5
Feb 17, 2011 110137STPY-163C(354)3P Pottawatomie
Division 3
RESURFACE (ASPHALT ) SH-270: FROM THE SH -102 JUNCTION, EXTEND EAST. PROJECT LENGTH = 6.55 MILES · — $863,141 HASKELL LEMON CONSTRUCTION CO. 1
Feb 17, 2011 110117SSR-156N(143)SR Okmulgee
Division 1
RESURFACE (ASPHALT ) I-40: FROM MILE MARKER 237 EXTEND EAST TO MILE MARKER 239.3. PROJECT LENGTH = 2.33 MILES · $698,968 $719,137 HASKELL LEMON CONSTRUCTION CO. +2.9% 3
Feb 17, 2011 110118NHY-014N(091)3P Okmulgee
Division 1
RESURFACE (UTBWC) US-75: FROM SH-16 EXTEND NORTH. PROJECT LENGTH = 8.0 MILES · — $657,002 APAC-CENTRAL, INC. 4
Feb 17, 2011 110037STPY-105B(200)3P Beckham
Division 5
RESURFACE (ASPHALT ) US-283: FROM 8.0 MILES NORTH OF THE GREER COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 4.34 MILES · $648,351 $633,983 CASWELL CONSTRUCTION, INC. -2.2% 3
Feb 17, 2011 110141STPY-167C(186)3P Seminole
Division 3
RESURFACE (ASPHALT ) US-270B: FROM THE US -270 JUNCTION, EXTEND EAST. PROJECT LENGTH = 3.16 MILES · $711,839 $633,431 HASKELL LEMON CONSTRUCTION CO. -11.0% 2
Feb 17, 2011 110036SBR-105C(190)SB Beckham
Division 5
BRIDGE REHABILITATION SH -152: OVER MIDDLE BUFFALO CREEK , 2.7 MILES EAST OF THE SH -30 JUNCTION. · $780,555 $532,309 PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) -31.8% 5
Feb 17, 2011 110154NHY-014N(092)3P Washington
Division 8
RESURFACE (ASPHALT ) US-75: FROM 2.19 MILES SOUTH OF THE KANSAS /OKLAHOMA STATE LINE , EXTEND NORTH . PROJECT LENGTH = 2.19 MILES · $489,852 $526,582 APAC-CENTRAL, INC. +7.5% 1
Feb 17, 2011 110074STPY-127C(182)3P Grant
Division 4
RESURFACE (ASPHALT ) US-64: FROM THE ALFALFA COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 4.08 MILES · $432,000 $514,800 THE CUMMINS CONSTRUCTION CO., INC. +19.2% 3
Feb 17, 2011 110149SBR-172A(390)SB Tulsa
Division 8
BRIDGE REHABILITATION SH -11: OVER EDISON ROAD AT THE I -244 JUNCTION IN THE CITY OF TULSA. · $463,441 $423,422 Keystone Services, Inc. -8.6% 6
Feb 17, 2011 110043STPY-109C(179)3P Canadian
Division 4
RESURFACE (ASPHALT ) SH-152: FROM 2.05 MILES EAST OF THE US -81 JUNCTION, EXTEND EAST. PROJECT LENGTH = 3.20 MILES · $445,714 $419,288 HASKELL LEMON CONSTRUCTION CO. -5.9% 4
Feb 17, 2011 110061BRF-121C(133)CO Delaware
Division 8
BRIDGE AND APPROACHES COUNTY ROAD (NS-471): OVER CHEROKEE CREEK, 0.9 MILES NORTH OF THE SH -116 EAST JUNCTION. PROJECT LENGTH = 0.081 MILES · $649,421 $402,784 BEACHNER CONSTRUCTION CO., INC. -38.0% 5
Feb 17, 2011 110055BRO-105D(179)CI Beckham
Division 5
BRIDGE AND APPROACHES COUNTY ROAD (EW-118): OVER SHORT CREEK , 2.3 MILES WEST OF THE I-40 JUNCTION. PROJECT LENGTH = 0.123 MILES · $387,887 $345,335 Munoz Construction, Inc. -11.0% 10
Feb 17, 2011 110157SBR-176C(174)SB Woods
Division 6
BRIDGE REHABILITATION SH -50: OVER THE CIMARRON RIVER , AT THE WOODWARD COUNTY LINE. · $435,706 $327,802 LOGOS CONSTRUCTION CO., LLC -24.8% 5
Feb 17, 2011 110095STPY-144B(159)3P Mcclain
Division 3
RESURFACE (ASPHALT ) SH-74: FROM THE US -77 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 1.09 MILES · $336,492 $289,725 HASKELL LEMON CONSTRUCTION CO. -13.9% 4
Feb 17, 2011 110040NHY-011N(092)3P Canadian
Division 4
RESURFACE (ASPHALT ) US-81: FROM 0.50 MILES NORTH OF THE GRADY COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 1.37 MILES · $310,660 $270,610 MARKWELL PAVING COMPANY, INC. -12.9% 4
Feb 17, 2011 110029STPG-155C(595)AG Oklahoma
Division 4
STRIPING AND PAVEMENT MARKING CITY STREETS : AT VARIOUS LOCATIONS IN MIDWEST CITY. PROJECT LENGTH = 9.5 MILES · $132,024 $192,052 ACTION SAFETY SUPPLY CO., LLC +45.5% 1
Feb 17, 2011 110155STPY-174B(080)3P Washington
Division 8
RESURFACE (ASPHALT ) SH-11: FROM THE OSAGE COUNTY LINE , EXTEND SOUTH. PROJECT LENGTH = 1.25 MILES · — $153,075 APAC-CENTRAL, INC. 2
Feb 17, 2011 110086STPY-114C(293)RW Cleveland
Division 3
RIGHT-OF-WAY CLEARANCE US-77: FROM 6.05 MILES NORTH OF THE SH -39 JUNCTION, EXTEND NORTH . · — $41,210 MIDWEST WRECKING, INC. 4
1–57 of 57

Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.