| 1 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 600 | LF |
$6.00 |
$6.00 |
$2.00 |
$2.00 |
$5.00 |
$2.10 |
| 2 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 350 | LF |
$20.00 |
$20.00 |
$15.95 |
$16.00 |
$18.00 |
$20.00 |
| 3 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,200.00 |
$3,300.00 |
$2,050.00 |
$2,100.00 |
$2,300.00 |
$2,600.00 |
| 4 | 623(I) 8675 |
GUARDRAIL BRIDGE CONNECTION-TYPE A | 4 | EA |
$2,000.00 |
$2,500.00 |
$1,300.00 |
$1,300.00 |
$2,200.00 |
$1,500.00 |
| 5 | 509(A) 1326 |
CLASS AA CONCRETE | 4 | CY |
$800.00 |
$2,500.00 |
$1,250.00 |
$2,000.00 |
$4,500.00 |
$6,000.00 |
| 6 | 511(A) 1332 |
REINFORCING STEEL | 720 | LB |
$4.00 |
$3.50 |
$4.30 |
$1.50 |
$1.00 |
$2.00 |
| 7 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$40,000.00 |
$49,500.00 |
$17,000.00 |
$50,000.00 |
$50,000.00 |
$76,000.00 |
| 8 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$6,000.00 |
$4,500.00 |
$21,500.00 |
$800.00 |
$1,000.00 |
$10,000.00 |
| 9 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 120 | SY |
$550.00 |
$200.00 |
$300.00 |
$300.00 |
$250.00 |
$400.00 |
| 10 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 25 | SY |
$700.00 |
$300.00 |
$500.00 |
$650.00 |
$500.00 |
$700.00 |
| 11 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 12 | SY |
$10.00 |
$20.00 |
$21.00 |
$30.00 |
$20.00 |
$90.41 |
| 12 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 380 | LF |
$50.00 |
$20.00 |
$39.00 |
$40.00 |
$61.00 |
$100.00 |
| 13 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 38 | GAL |
$100.00 |
$10.00 |
$86.00 |
$70.00 |
$10.00 |
$60.00 |
| 14 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 130 | SY |
$500.00 |
$400.00 |
$1,000.00 |
$725.00 |
$850.00 |
$650.00 |
| 15 | 524(A) 6610 |
(SP)CARBON FIBER-REINFORCED POLYMER | 420 | SF |
$75.00 |
$120.00 |
$140.00 |
$125.00 |
$89.00 |
$110.00 |
| 16 | 535 6130 |
(SP)CORROSION INHIBITOR(SURFACE APPLIED) | 80 | SY |
$60.00 |
$39.00 |
$45.00 |
$15.00 |
$30.00 |
$15.00 |
| 17 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$10,000.00 |
$10,286.00 |
$2,100.00 |
$20,000.00 |
$5,600.00 |
$9,000.00 |
| 18 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 3,898 | LF |
$2.00 |
$5.00 |
$1.60 |
$2.00 |
$1.65 |
$1.70 |
| 19 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$20,000.00 |
$19,166.00 |
$3,035.00 |
$13,000.00 |
$17,000.00 |
$3,500.00 |
| 20 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$8,000.00 |
$800.00 |
$2,050.00 |
$3,500.00 |
$500.00 |
$3,200.00 |
| 21 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$35,000.00 |
$32,500.00 |
$28,000.00 |
$38,525.00 |
$53,000.00 |
$44,000.00 |