Bid tab 110113

Let Feb 17, 2011 · Division 8 · Nowata Sign up free

‹ Feb 2011 results

RESURFACE (ASPHALT ) US-60: FROM 2.90 MILES EAST OF THE US -169 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.0 MILES

Let date
Thursday, February 17, 2011
Contract
110113
J/P numbers
28266(04)
District
Division 8
County
Nowata
Highway
Limits
RESURFACE (ASPHALT ) US-60: FROM 2.90 MILES EAST OF THE US -169 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.0 MILES
Project number
NHY-018N(059)3P

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,227,032
1 APAC-CENTRAL, INC. Low bidder $1,282,061 +4.5%
2 BECCO CONTRACTORS, INC. $1,295,999 +5.6% +1.1%
3 KOSS CONSTRUCTION COMPANY & SUBSIDIARY $1,463,121 +19.2% +14.1%

Bid tab: unit prices 7 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 APAC-CENTRAL, I…#2 BECCO CONTRACTO…#3 KOSS CONSTRUCTI…
1402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E986TON $25.00 $18.75 $20.00 $28.00
2411(C) 5950 SUPERPAVE, TYPE S4(PG 76-28 OK)15,474TON $68.00 $74.00 $75.00 $85.00
3412 5267 COLD MILLING PAVEMENT7,462SY $1.75 $1.65 $2.50 $3.29
4413(A) 4861 RUMBLE STRIP-METHOD HMA-CON86,170LF $0.2000 $0.0800 $0.0800 $0.0600
5855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)174,451LF $0.3500 $0.3800 $0.4000 $0.3600
6880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $30,000.00 $15,000.00 $12,000.00 $12,100.00
7880(L) 8911 TRAFFIC SURVEILLANCE, POLICE240HOUR $120.00 $75.00 $35.00 $65.00