RESURFACE (ASPHALT ) SH-74: FROM THE US -77 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 1.09 MILES
- Let date
- Thursday, February 17, 2011
- Contract
- 110095
- J/P numbers
- 28211(04)
- District
- Division 3
- County
- Mcclain
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-74: FROM THE US -77 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 1.09 MILES
- Project number
- STPY-144B(159)3P
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $336,492 | ||
| 1 | HASKELL LEMON CONSTRUCTION CO. Low bidder | $289,725 | -13.9% | |
| 2 | MARKWELL PAVING COMPANY, INC. | $295,510 | -12.2% | +2.0% |
| 3 | THE CUMMINS CONSTRUCTION CO., INC. | $343,145 | +2.0% | +18.4% |
| 4 | Silver Star Construction Company, Inc. | $343,879 | +2.2% | +18.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 HASKELL LEMON C… | #2 MARKWELL PAVING… | #3 THE CUMMINS CON… | #4 Silver Star Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 407(B) 0250 | TACK COAT | 1,887 | GAL | $3.25 | $2.10 | $1.00 | $2.75 | $3.00 |
| 2 | 411(C) 5955 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 3,505 | TON | $70.00 | $66.00 | $64.00 | $68.40 | $74.50 |
| 3 | 412 5267 | COLD MILLING PAVEMENT | 37,734 | SY | $1.50 | $0.6000 | $1.00 | $1.80 | $0.7000 |
| 4 | 855(A) 8812 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 40,286 | LF | $0.4500 | $0.5300 | $0.5200 | $0.5000 | $0.5400 |
| 5 | 855(B) 8818 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 2 | EA | $75.00 | $110.00 | $105.00 | $100.00 | $106.00 |
| 6 | 855(B) 8821 | TRAFFIC STRIPE(PLASTIC)(WORDS) | 1 | EA | $130.00 | $220.00 | $210.00 | $200.00 | $215.00 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $10,000.00 | $10,000.00 | $10,200.00 | $9,750.00 | $28,500.00 |