| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$25,000.00 |
$12,240.00 |
$120,960.00 |
$150,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 34,579 | CY |
$7.50 |
$5.35 |
$5.67 |
$14.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 17,270 | CY |
$9.00 |
$9.20 |
$9.72 |
$0.3000 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$50,000.00 |
$18,360.00 |
$19,440.00 |
$175,000.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,303 | LF |
$1.50 |
$1.15 |
$1.44 |
$1.20 |
| 6 | 221(F) 0100 |
TEMPORARY SILT DIKE | 273 | LF |
$10.00 |
$6.15 |
$9.85 |
$6.40 |
| 7 | 221(G) 0150 |
TEMPORARY ROCK FILTER DAM TYPE 1 | 4 | CY |
$100.00 |
$129.00 |
$270.00 |
$214.00 |
| 8 | 221(K) 0600 |
TEMPORARY FIBER LOG | 250 | LF |
$5.00 |
$4.25 |
$6.18 |
$4.40 |
| 9 | 230(A) 2806 |
SOLID SLAB SODDING | 30,870 | SY |
$1.50 |
$1.15 |
$1.44 |
$1.25 |
| 10 | 230(F) 2812 |
WATERING | 1,235 | KGAL |
$8.00 |
$4.60 |
$2.16 |
$4.50 |
| 11 | 233(A) 2817 |
VEGETATIVE MULCHING | 6.39 | AC |
$500.00 |
$255.00 |
$527.04 |
$270.00 |
| 12 | 241 2832 |
MOWING | 6.39 | AC |
$100.00 |
$45.90 |
$124.20 |
$48.00 |
| 13 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 6,167 | CY |
$50.00 |
$58.40 |
$42.60 |
$70.20 |
| 14 | 307(K) 4300 |
STABILIZED SUBGRADE | 31,644 | SY |
$7.00 |
$9.95 |
$4.59 |
$5.00 |
| 15 | 325 5271 |
SEPARATOR FABRIC | 29,102 | SY |
$1.50 |
$4.80 |
$4.32 |
$4.30 |
| 16 | 402(A) 0217 |
TRAFFIC BOUND SURFACE COURSE TYPE A | 198 | TON |
$35.00 |
$26.10 |
$27.57 |
$35.00 |
| 17 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 468 | TON |
$40.00 |
$28.50 |
$29.73 |
$40.00 |
| 18 | 407(B) 0250 |
TACK COAT | 4,233 | GAL |
$4.00 |
$3.60 |
$2.03 |
$2.50 |
| 19 | 408 5774 |
PRIME COAT | 18,080 | GAL |
$5.00 |
$3.70 |
$3.40 |
$3.00 |
| 20 | 411(B) 5940 |
SUPERPAVE, TYPE S3(PG 70-28 OK) | 3,207 | TON |
$76.00 |
$63.20 |
$71.37 |
$72.30 |
| 21 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 7,668 | TON |
$70.00 |
$56.10 |
$63.03 |
$65.20 |
| 22 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 2,124 | TON |
$85.00 |
$68.70 |
$84.67 |
$73.85 |
| 23 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 1,056 | TON |
$80.00 |
$74.10 |
$73.88 |
$81.90 |
| 24 | 412 5267 |
COLD MILLING PAVEMENT | 6,597 | SY |
$3.50 |
$2.75 |
$1.96 |
$2.00 |
| 25 | 413(A) 4870 |
RUMBLE STRIP-CENTERLINE HMA-CON | 6,748 | LF |
$0.2500 |
$0.1500 |
$0.3800 |
$0.1500 |
| 26 | 413(B) 4863 |
RUMBLE STRIP-METHOD HMA-CYC | 6,206 | LF |
$1.00 |
$0.1500 |
$0.3800 |
$0.1500 |
| 27 | 509(D) 0325 |
CLASS C CONCRETE | 50 | CY |
$400.00 |
$469.00 |
$420.31 |
$400.00 |
| 28 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 33 | TON |
$60.00 |
$65.60 |
$68.83 |
$112.00 |
| 29 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 214 | LF |
$70.00 |
$46.90 |
$48.60 |
$80.50 |
| 30 | 613(A) 0494 |
36" R.C.PIPE CLASS III | 80 | LF |
$100.00 |
$91.80 |
$102.60 |
$145.00 |
| 31 | 613(EE) 5640 |
(SP) 36" CORRUGATED POLYPROPYLENE PIPE | 351 | LF |
$150.00 |
$96.90 |
$102.60 |
$68.20 |
| 32 | 613(H) 0500 |
8" PERFORATED PIPE UNDERDRAIN ROUND | 192 | LF |
$20.00 |
$15.50 |
$30.58 |
$30.00 |
| 33 | 613(I) 1097 |
8" NON-PERF.PIPE UNDERDRAIN RND. | 64 | LF |
$25.00 |
$15.50 |
$30.58 |
$30.00 |
| 34 | 613(M) 7189 |
TYPE D4 CULVERT END TREATMENT | 2 | EA |
$2,500.00 |
$1,538.00 |
$2,333.96 |
$1,970.00 |
| 35 | 613(M) 7197 |
TYPE B6 CULVERT END TREATMENT | 4 | EA |
$1,750.00 |
$1,484.00 |
$2,289.47 |
$1,970.00 |
| 36 | 613(M) 7199 |
TYPE D6 CULVERT END TREATMENT | 2 | EA |
$2,250.00 |
$2,113.00 |
$4,190.33 |
$2,505.00 |
| 37 | 613(Q) 5946 |
OUTLET LATERAL HEADWALL | 1 | EA |
$1,000.00 |
$932.50 |
$1,350.00 |
$1,172.00 |
| 38 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$15,000.00 |
$16,320.00 |
$17,280.00 |
$30,000.00 |
| 39 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 15,233 | SY |
$4.50 |
$6.10 |
$5.44 |
$3.10 |
| 40 | 619(B) 4767 |
REMOVAL OF ASPHALT DRIVEWAY | 519 | SY |
$5.00 |
$13.20 |
$4.32 |
$12.00 |
| 41 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 849 | LF |
$5.00 |
$2.55 |
$6.48 |
$3.00 |
| 42 | 619(C) 0924 |
SAWING PAVEMENT | 2,472 | LF |
$5.00 |
$2.60 |
$8.64 |
$2.00 |
| 43 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 550 | LF |
$18.00 |
$21.20 |
$22.41 |
$19.10 |
| 44 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$2,500.00 |
$2,550.00 |
$2,700.00 |
$2,350.00 |
| 45 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,000.00 |
$2,040.00 |
$2,160.00 |
$1,650.00 |
| 46 | 853 9033 |
DELINEATORS(TYPE 2, CODE 1) | 18 | EA |
$20.00 |
$10.20 |
$10.80 |
$16.00 |
| 47 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 320 | CY |
$40.00 |
$19.80 |
$27.50 |
$10.00 |
| 48 | 501(G) 6309 |
CLSM BACKFILL | 525 | CY |
$170.00 |
$127.50 |
$142.33 |
$147.00 |
| 49 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 2,076 | LF |
$235.00 |
$238.00 |
$281.52 |
$258.00 |
| 50 | 504(A) 1304 |
APPROACH SLAB | 928.6 | SY |
$180.00 |
$182.00 |
$228.65 |
$198.00 |
| 51 | 504(B) 1305 |
SAW-CUT GROOVING | 3,090 | SY |
$5.00 |
$3.65 |
$3.96 |
$3.85 |
| 52 | 504(C) 6250 |
SEALED EXPANSION JOINT | 95 | LF |
$300.00 |
$222.50 |
$275.07 |
$293.00 |
| 53 | 504(E) 6190 |
42" F-SHAPED PARAPET | 662.2 | LF |
$125.00 |
$94.40 |
$100.63 |
$115.50 |
| 54 | 506(A) 1322 |
STRUCTURAL STEEL | 3,460 | LB |
$5.00 |
$2.90 |
$5.72 |
$2.15 |
| 55 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 27 | EA |
$2,000.00 |
$1,103.00 |
$868.38 |
$927.00 |
| 56 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 27 | EA |
$2,000.00 |
$1,103.00 |
$952.12 |
$927.00 |
| 57 | 509(A) 1326 |
CLASS AA CONCRETE | 571.6 | CY |
$550.00 |
$542.50 |
$669.63 |
$613.00 |
| 58 | 509(B) 1328 |
CLASS A CONCRETE | 386.9 | CY |
$600.00 |
$578.50 |
$724.63 |
$671.00 |
| 59 | 511(A) 1332 |
REINFORCING STEEL | 1,600 | LB |
$0.9500 |
$2.90 |
$1.13 |
$1.65 |
| 60 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 198,010 | LB |
$1.05 |
$1.10 |
$1.15 |
$1.14 |
| 61 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 276 | LF |
$35.00 |
$34.60 |
$36.29 |
$29.85 |
| 62 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 1,951 | LF |
$40.00 |
$38.40 |
$42.23 |
$33.60 |
| 63 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 276 | LF |
$20.00 |
$30.80 |
$22.00 |
$12.80 |
| 64 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 1,951 | LF |
$20.00 |
$21.80 |
$11.00 |
$14.40 |
| 65 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 66 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,622 | SY |
$4.00 |
$3.70 |
$4.02 |
$3.90 |
| 67 | 516(A) 6095 |
DRILLED SHAFTS 54" DIAMETER | 615 | LF |
$550.00 |
$711.00 |
$731.86 |
$918.40 |
| 68 | 516(C) 6200 |
CROSSHOLE SONIC LOGGING | 10 | EA |
$2,750.00 |
$2,727.00 |
$2,475.00 |
$2,280.00 |
| 69 | 523(A) 6550 |
SEALER CRACK PREPARATION | 315.2 | LF |
$5.00 |
$4.10 |
$4.40 |
$4.30 |
| 70 | 523(B) 6560 |
SEALER RESIN | 6.3 | GAL |
$125.00 |
$153.00 |
$165.00 |
$160.00 |
| 71 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 2,110 | TON |
$50.00 |
$45.20 |
$48.11 |
$51.20 |
| 72 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 660 | TON |
$40.00 |
$35.50 |
$36.93 |
$39.95 |
| 73 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 194 | LF |
$30.00 |
$34.90 |
$40.29 |
$31.95 |
| 74 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 24 | LF |
$30.00 |
$33.30 |
$45.79 |
$74.60 |
| 75 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$500,000.00 |
$85,590.00 |
$225,500.00 |
$165,145.00 |
| 76 | 804(A) 2915 |
STRUCTURAL CONCRETE | 1 | CY |
$750.00 |
$357.00 |
$378.00 |
$373.00 |
| 77 | 804(B) 2916 |
REINFORCING STEEL | 76 | LB |
$2.00 |
$2.05 |
$2.16 |
$2.10 |
| 78 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 10 | EA |
$200.00 |
$102.00 |
$108.00 |
$106.00 |
| 79 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 55 | SF |
$25.00 |
$16.30 |
$17.28 |
$17.00 |
| 80 | 851(B) 3219 |
3 1/2"@9.11 GALV.STEEL PIPE POST | 33 | LF |
$20.00 |
$25.50 |
$27.00 |
$26.60 |
| 81 | 851(C) 8330 |
2 1/2" SQUARE TUBE POST | 279 | LF |
$10.50 |
$10.20 |
$10.80 |
$10.60 |
| 82 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 23,785 | LF |
$0.8000 |
$0.5200 |
$0.5500 |
$0.5500 |
| 83 | 855(A) 8818 |
TRAFFIC STRIPE(PLASTIC)(12" WIDE) | 897 | LF |
$1.75 |
$1.00 |
$1.08 |
$1.05 |
| 84 | 855(A) 8825 |
TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 16 | LF |
$12.50 |
$20.40 |
$21.60 |
$21.30 |
| 85 | 855(B) 8818 |
TRAFFIC STRIPE(PLASTIC)(ARROWS) | 13 | EA |
$150.00 |
$76.50 |
$81.00 |
$79.90 |
| 86 | 855(B) 8821 |
TRAFFIC STRIPE(PLASTIC)(WORDS) | 1 | EA |
$200.00 |
$153.00 |
$162.00 |
$160.00 |
| 87 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 30,540 | LF |
$0.2000 |
$0.1000 |
$0.1100 |
$0.1100 |
| 88 | 857(C) 8851 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 1,000 | LF |
$2.00 |
$1.00 |
$1.08 |
$1.05 |
| 89 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 600 | EA |
$1.00 |
$1.00 |
$1.08 |
$1.05 |
| 90 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 12,468 | LF |
$0.5000 |
$0.1200 |
$0.1300 |
$0.1000 |
| 91 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 1,080 | SD |
$12.50 |
$3.05 |
$3.24 |
$3.20 |
| 92 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 3,450 | LF |
$30.00 |
$18.90 |
$43.20 |
$14.70 |
| 93 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 3,290 | LF |
$4.00 |
$1.00 |
$4.32 |
$3.10 |
| 94 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 8,460 | SD |
$0.6000 |
$0.1000 |
$0.1100 |
$0.1100 |
| 95 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,080 | SD |
$1.00 |
$1.55 |
$1.62 |
$1.60 |
| 96 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 3,240 | SD |
$1.75 |
$0.1000 |
$0.1100 |
$0.1100 |
| 97 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 540 | SD |
$1.00 |
$3.05 |
$3.24 |
$3.20 |
| 98 | 880(C) 8848 |
WING BARRICADES | 720 | SD |
$1.00 |
$0.5100 |
$0.5400 |
$0.5000 |
| 99 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 2,160 | SD |
$0.8000 |
$3.05 |
$3.24 |
$3.20 |
| 100 | 880(F) 8878 |
DRUMS | 12,780 | SD |
$0.4000 |
$0.0500 |
$0.0500 |
$0.0500 |
| 101 | 880(G) 8890 |
CHANNELIZER CONES | 8,640 | SD |
$0.3500 |
$0.1000 |
$0.1100 |
$0.1100 |
| 102 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 240 | SD |
$20.00 |
$15.30 |
$16.20 |
$16.00 |
| 103 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$15,000.00 |
$26,620.00 |
$35,100.00 |
$45,000.00 |
| 104 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,373.00 |
$5,400.00 |
$20,000.00 |
| 105 | 640(A) 1426 |
FIELD OFFICE | 1 | EA |
$15,000.00 |
$4,892.00 |
$15,120.00 |
$26,000.00 |
| 106 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$290,000.00 |
$234,600.00 |
$301,752.22 |
$308,522.32 |