| 1 | 201 6215 |
(PL)REMOVE DRIFT AND SILT | 1 | LSUM |
$2,000.00 |
$8,000.00 |
$5,900.00 |
| 2 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$20,000.00 |
$25,000.00 |
$14,500.00 |
| 3 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 5,907 | CY |
$5.00 |
$10.50 |
$6.05 |
| 4 | 202(D) 0184 |
UNCLASSIFIED BORROW | 1,518 | CY |
$8.00 |
$12.00 |
$7.05 |
| 5 | 202(E) 0186 |
SELECT BORROW | 100 | CY |
$12.00 |
$30.00 |
$12.00 |
| 6 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$12,735.00 |
$20,000.00 |
$6,900.00 |
| 7 | 221(C) 2801 |
TEMPORARY SILT FENCE | 8,100 | LF |
$1.75 |
$1.40 |
$2.00 |
| 8 | 221(F) 0100 |
TEMPORARY SILT DIKE | 918 | LF |
$7.00 |
$6.25 |
$9.00 |
| 9 | 230(A) 2806 |
SOLID SLAB SODDING | 17,620 | SY |
$1.25 |
$1.45 |
$1.50 |
| 10 | 233(A) 2817 |
VEGETATIVE MULCHING | 7.6 | AC |
$375.00 |
$625.00 |
$871.50 |
| 11 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 5,050 | CY |
$40.00 |
$50.00 |
$49.60 |
| 12 | 307(K) 4300 |
STABILIZED SUBGRADE | 23,782 | SY |
$5.25 |
$5.25 |
$7.00 |
| 13 | 311(B) 0152 |
PROCESSING EXISTING BASE & SURFACE, METHOD B | 6,486 | LF |
$2.00 |
$2.35 |
$3.90 |
| 14 | 325 5271 |
SEPARATOR FABRIC | 33,492 | SY |
$1.50 |
$1.05 |
$1.70 |
| 15 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 2,077 | TON |
$20.00 |
$23.50 |
$26.80 |
| 16 | 407(B) 0250 |
TACK COAT | 1,750 | GAL |
$3.00 |
$3.00 |
$4.80 |
| 17 | 408 5774 |
PRIME COAT | 13,001 | GAL |
$5.00 |
$6.00 |
$8.50 |
| 18 | 409(A) 4242 |
FABRIC REINFORCEMENT | 6,043 | SY |
$1.75 |
$1.00 |
$2.50 |
| 19 | 409(B) 4268 |
BITUMINOUS BINDER | 1,209 | GAL |
$4.50 |
$3.00 |
$4.35 |
| 20 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 3,107 | TON |
$65.00 |
$78.75 |
$88.35 |
| 21 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 4,921 | TON |
$75.00 |
$99.00 |
$93.85 |
| 22 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 619 | TON |
$70.00 |
$96.00 |
$158.55 |
| 23 | 411(H) 6210 |
SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) | 34 | TON |
$100.00 |
$125.00 |
$210.60 |
| 24 | 501(A) 0313 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 68.8 | CY |
$15.00 |
$5.25 |
$10.00 |
| 25 | 509(A) 0319 |
CLASS AA CONCRETE | 39.5 | CY |
$450.00 |
$625.00 |
$700.00 |
| 26 | 509(B) 0321 |
CLASS A CONCRETE | 20.9 | CY |
$450.00 |
$575.00 |
$700.00 |
| 27 | 509(D) 0325 |
CLASS C CONCRETE | 137.7 | CY |
$250.00 |
$400.00 |
$300.00 |
| 28 | 511(A) 0332 |
REINFORCING STEEL | 8,460 | LB |
$1.00 |
$0.9200 |
$1.50 |
| 29 | 610(B) 0604 |
6" CONCRETE DRIVEWAY | 64 | SY |
$50.00 |
$58.00 |
$100.00 |
| 30 | 611(G) 6004 |
INLET (SMD-TYPE 2A) | 6 | EA |
$2,700.00 |
$2,900.00 |
$2,500.00 |
| 31 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 180 | LF |
$55.00 |
$52.00 |
$70.00 |
| 32 | 613(B) 0696 |
60" CORR. GALV. STEEL PIPE | 34 | LF |
$120.00 |
$104.00 |
$100.00 |
| 33 | 613(B) 4527 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 372 | LF |
$35.00 |
$37.00 |
$25.00 |
| 34 | 613(B) 4528 |
28" X 20" CORR. GALV. STEEL PIPE ARCH | 832 | LF |
$30.00 |
$40.00 |
$35.00 |
| 35 | 613(E) 4788 |
30" CORRUGATED POLYETHYLENE PIPE TYPE "S" | 1,450 | LF |
$55.00 |
$48.00 |
$15.00 |
| 36 | 613(L) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 1 | EA |
$650.00 |
$940.00 |
$816.50 |
| 37 | 613(M) 7192 |
TYPE BB4 CULVERT END TREATMENT | 2 | EA |
$1,200.00 |
$1,600.00 |
$3,000.00 |
| 38 | 613(P) 0767 |
60" GALV. STEEL CULVERT END SECTION ROUND | 2 | EA |
$800.00 |
$2,100.00 |
$3,000.00 |
| 39 | 613(P) 4571 |
28" X 20" GALV. STEEL CULVERT END SECTION ARCH | 44 | EA |
$300.00 |
$500.00 |
$300.00 |
| 40 | 613(P) 7025 |
21" X 15" GALV. STEEL CULVERT END SECTION ARCH | 9 | EA |
$275.00 |
$400.00 |
$300.00 |
| 41 | 613(S) 1186 |
STANDARD BEDDING MATERIAL, CLASS B | 689 | CY |
$35.00 |
$36.00 |
$40.00 |
| 42 | 613(V) 1180 |
TRENCH EXCAVATION | 1,046 | CY |
$8.50 |
$10.00 |
$5.00 |
| 43 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$9,300.00 |
$24,000.00 |
$28,400.00 |
| 44 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 1,575 | SY |
$3.20 |
$5.00 |
$9.60 |
| 45 | 619(C) 0924 |
SAWING PAVEMENT | 8,872 | LF |
$3.50 |
$2.50 |
$4.50 |
| 46 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 2 | EA |
$1,500.00 |
$1,550.00 |
$1,500.00 |
| 47 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 2 | EA |
$4,000.00 |
$1,925.00 |
$1,875.00 |
| 48 | 629(A) 4958 |
MAILBOX INSTALLATION-SINGLE | 3 | EA |
$75.00 |
$72.00 |
$70.00 |
| 49 | 629(B) 4959 |
MAILBOX INSTALLATION-MULTIPLE | 1 | EA |
$150.00 |
$175.00 |
$170.00 |
| 50 | 629(C) 4960 |
MAILBOX | 7 | EA |
$30.00 |
$25.00 |
$25.00 |
| 51 | 629(D) 4961 |
REMOVAL OF MAILBOX INSTALLATION | 4 | EA |
$15.00 |
$12.00 |
$12.00 |
| 52 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 481 | CY |
$8.00 |
$12.00 |
$8.05 |
| 53 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 20 | CY |
$20.00 |
$5.25 |
$20.00 |
| 54 | 509(A) 1326 |
CLASS AA CONCRETE | 191 | CY |
$450.00 |
$292.00 |
$350.00 |
| 55 | 511(A) 1332 |
REINFORCING STEEL | 26,810 | LB |
$1.00 |
$0.9200 |
$1.00 |
| 56 | 601(D) 1357 |
TYPE II SPECIAL PLAIN RIPRAP | 74 | TON |
$35.00 |
$55.00 |
$45.00 |
| 57 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$1,500.00 |
$3,000.00 |
$23,000.00 |
| 58 | 805(A) 8722 |
(PL)REMOVAL OF EXISTING SIGNS | 1 | LSUM |
$250.00 |
$51.00 |
$1,125.00 |
| 59 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 13 | EA |
$150.00 |
$67.00 |
$65.00 |
| 60 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 75.19 | SF |
$17.00 |
$12.25 |
$12.00 |
| 61 | 851(D) 8597 |
FLANGE CHANNEL POSTS(4 LB/FT) | 227 | LF |
$11.00 |
$9.25 |
$9.00 |
| 62 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 42,744 | LF |
$0.5500 |
$0.3500 |
$0.3500 |
| 63 | 855(A) 8825 |
TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 136 | LF |
$0.5500 |
$2.40 |
$2.40 |
| 64 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$30,000.00 |
$20,000.00 |
$8,250.00 |
| 65 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$15,000.00 |
$46,980.00 |
| 66 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$2,500.00 |
$3,150.00 |
| 67 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$62,000.00 |
$78,500.00 |
$99,000.00 |
| 68 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 1,034 | LF |
$4.00 |
$8.00 |
$3.40 |