$5.31Avg low bid / LF
$7.02Avg of all bids
$6.78Avg engineer's estimate
8Jobs · 127,733.82 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 450 | $8.00 | $9.51 |
| 2020 | 3 | 87,371.99 | $4.18 | $6.11 |
| 2019 | 3 | 37,136.83 | $7.98 | $9.54 |
| 2018 | 1 | 2,775 | $4.70 | $6.38 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 17, 2021 | 210172 | DeweyDivision 5 | 450 LF | $8.00 | Wyatt Contracting |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 41,945.99 LF | $5.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200251 | HarmonDivision 5 | 36,914 LF | $1.91 | Frontier Bridge, Inc. |
| Jan 16, 2020 | 200043 | HaskellDivision 1 | 8,512 LF | $10.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Aug 22, 2019 | 190244 | CusterDivision 5 | 746.83 LF | $7.00 | SEWELL BROS., INC. |
| Feb 14, 2019 | 190101 | Pontotoc | 31,570 LF | $8.45 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190001 | AtokaDivision 2 | 4,820 LF | $5.09 | THE CUMMINS CONSTRUCTION CO., INC. |
| Sep 20, 2018 | 180314 | BryanDivision 2 | 2,775 LF | $4.70 | OVERLAND CORPORATION |