Bid tab 150160

Let May 21, 2015 · Division 8 · Craig Sign up free

‹ May 2015 results

BRIDGE AND APPROACHES - DIVISION VIII US-59: OVER UNION PACIFIC RAILROAD , 1.1 MILES NORTH OF SH -10 NEAR WELCH. PROJECT LENGTH = 0.871 MILE

Let date
Thursday, May 21, 2015
Contract
150160
J/P numbers
24115(04)
District
Division 8
County
Craig
Highway
Limits
BRIDGE AND APPROACHES - DIVISION VIII US-59: OVER UNION PACIFIC RAILROAD , 1.1 MILES NORTH OF SH -10 NEAR WELCH. PROJECT LENGTH = 0.871 MILE
Project number
STP-118B(080)SS

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 GLOVER & ASSOCIATES, INC. Low bidder $5,040,026
2 B & B BRIDGE COMPANY, LLC $5,244,698 +4.1%
3 SHERWOOD CONSTRUCTION CO., INC. $5,269,909 +4.6%
4 MANHATTAN ROAD & BRIDGE COMPANY, LLC $5,649,109 +12.1%
5 Crossland Construction Company, Inc. $5,661,461 +12.3%

Bid tab: unit prices 93 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 GLOVER & ASSOCI…#2 B & B BRIDGE CO…#3 SHERWOOD CONSTR…#4 MANHATTAN ROAD …#5 Crossland Const…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $20,000.00 $15,000.00 $33,964.00 $9,970.57 $230,000.00 $129,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION43,526CY $10.00 $7.75 $4.01 $5.23 $6.50 $4.10
3202(D) 0184 UNCLASSIFIED BORROW87,664CY $10.00 $6.99 $7.75 $5.23 $8.00 $6.33
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $40,000.00 $28,995.25 $28,484.73 $48,309.09 $25,000.00 $83,000.00
5221(C) 2801 TEMPORARY SILT FENCE8,781LF $2.00 $1.95 $1.29 $1.96 $1.30 $1.29
6221(D) 2803 TEMPORARY SEDIMENT FILTER6EA $225.00 $1,000.00 $149.00 $217.66 $150.00 $215.00
7221(F) 0100 TEMPORARY SILT DIKE770LF $6.00 $8.00 $6.95 $9.79 $7.10 $6.68
8230(A) 2806 SOLID SLAB SODDING54,375SY $3.00 $1.35 $1.10 $1.43 $1.15 $1.13
9232(A) 2813 SEEDING METHOD A10AC $1,000.00 $225.00 $199.00 $257.92 $205.00 $533.00
10233(A) 2817 VEGETATIVE MULCHING10AC $350.00 $225.00 $199.00 $257.92 $205.00 $315.00
11241 2832 MOWING41AC $50.00 $11.00 $49.00 $63.51 $50.00 $44.00
12303(A) 2100 AGGREGATE BASE TYPE A4,976CY $35.00 $44.00 $44.50 $47.33 $53.00 $39.60
13307(K) 4300 STABILIZED SUBGRADE34,409SY $6.00 $6.00 $6.57 $7.21 $6.00 $7.37
14325 5271 SEPARATOR FABRIC28,055SY $1.50 $0.9800 $1.12 $1.28 $1.10 $0.9000
15402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E2,433TON $27.00 $21.95 $18.68 $22.69 $27.00 $21.00
16407(B) 0250 TACK COAT3,689GAL $3.00 $2.00 $2.70 $6.00 $2.75 $2.95
17408 5774 PRIME COAT18,627GAL $4.00 $2.00 $6.16 $6.75 $6.20 $6.73
18411(B) 5940 SUPERPAVE, TYPE S3(PG 70-28 OK)3,762TON $80.00 $65.13 $72.00 $92.90 $75.00 $83.91
19411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)4,965TON $75.00 $64.92 $63.30 $76.34 $65.00 $69.18
20411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)2,566TON $90.00 $80.00 $82.30 $106.36 $85.00 $89.94
21411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)805TON $80.00 $79.82 $68.10 $87.04 $71.00 $74.40
22509(D) 0325 CLASS C CONCRETE747CY $350.00 $225.00 $350.00 $264.80 $200.00 $380.00
23613(A) 0491 18" R.C.PIPE CLASS III48LF $65.00 $60.00 $31.41 $48.35 $40.00 $71.70
24613(A) 0492 24" R.C.PIPE CLASS III126LF $75.00 $55.00 $43.74 $55.78 $45.00 $82.40
25613(B) 0690 24" CORR. GALV. STEEL PIPE74LF $35.00 $29.97 $29.80 $48.07 $36.00 $69.40
26613(L) 5726 18" PREFAB. CULVERT END SECTION, ROUND2EA $650.00 $1,523.97 $779.12 $586.58 $600.00 $383.00
27613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND4EA $1,000.00 $1,500.00 $890.04 $699.56 $775.00 $492.00
28613(P) 0761 24" GALV. STEEL CULVERT END SECTION ROUND4EA $350.00 $300.00 $291.06 $186.34 $235.00 $464.00
29613(T) 1187 STANDARD BEDDING MATERIAL, CLASS C57CY $35.00 $39.98 $42.61 $67.50 $57.00 $41.20
30613(V) 1180 TRENCH EXCAVATION238CY $12.00 $20.00 $9.36 $7.78 $15.00 $6.90
31613(W) 4498 18" JACKED CONDUIT54LF $300.00 $400.00 $153.24 $605.34 $485.00 $545.00
32619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $33,226.42 $1,419.46 $12,617.02 $10,000.00 $11,000.00
33619(B) 4725 REMOVAL OF FENCE8,515LF $3.00 $1.00 $1.50 $1.62 $1.00 $1.28
34619(B) 4728 REMOVAL OF ASPHALT PAVEMENT19,078SY $5.00 $1.70 $2.97 $2.67 $4.50 $1.15
35619(B) 4780 REMOVAL OF GUARDRAIL2,377LF $3.00 $4.00 $1.00 $4.09 $2.75 $3.00
36619(C) 0924 SAWING PAVEMENT2,640LF $3.50 $1.00 $3.00 $3.43 $3.50 $5.80
37623 0100 (PL)GUARDRAIL CURBING4EA $850.00 $400.00 $2,000.00 $2,426.81 $1,325.00 $1,100.00
38623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE400LF $20.00 $20.00 $17.00 $22.03 $17.50 $16.45
39623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $4,000.00 $2,400.00 $2,050.00 $2,656.97 $2,300.00 $2,600.00
40623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,000.00 $2,200.00 $1,695.00 $2,196.86 $3,100.00 $1,885.00
41624(C) 4458 FENCE-STYLE SWF (4 BARBED WIRE)1,874LF $5.00 $5.00 $3.20 $4.99 $3.35 $3.50
42624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)6,762LF $5.00 $5.00 $3.45 $5.83 $3.60 $3.77
43104 0955 (SP) RAILROAD FLAGGING(NON-BIDDABLE)80DAY $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
44501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON270CY $20.00 $16.36 $30.00 $16.42 $60.00 $63.55
45501(G) 6309 CLSM BACKFILL316CY $350.00 $135.35 $150.00 $133.30 $150.00 $133.20
46504(A) 1304 APPROACH SLAB427.8SY $180.00 $155.24 $200.00 $170.80 $155.00 $142.00
47504(B) 1305 SAW-CUT GROOVING1,344.9SY $4.25 $4.00 $4.00 $5.18 $4.15 $3.80
48504(C) 6250 SEALED EXPANSION JOINT53.2LF $300.00 $295.87 $275.00 $337.28 $335.00 $190.00
49504(D) 6245 CONCRETE RAIL (TR4)690.3LF $80.00 $68.99 $85.00 $78.86 $65.00 $109.00
50506(A) 1322 STRUCTURAL STEEL314,890LB $1.95 $1.90 $2.10 $1.84 $2.10 $1.90
51507(A) 6170 STAINLESS STEEL FIXED BEARING ASSEMBLY10EA $3,000.00 $2,011.97 $1,300.00 $1,559.77 $2,000.00 $1,320.00
52507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY20EA $2,500.00 $2,011.97 $1,300.00 $1,635.69 $2,000.00 $1,380.00
53509(A) 1326 CLASS AA CONCRETE279CY $450.00 $694.01 $816.57 $711.15 $500.00 $768.00
54509(B) 1328 CLASS A CONCRETE270.6CY $500.00 $482.07 $816.57 $611.64 $650.00 $840.00
55510(C) 6138 SLOPE WALL (5")1,400SY $70.00 $97.34 $115.00 $101.57 $95.00 $82.70
56511(A) 1332 REINFORCING STEEL1,350LB $1.00 $1.01 $1.00 $1.45 $1.20 $0.9100
57511(B) 6010 EPOXY COATED REINFORCING STEEL126,000LB $1.00 $0.9600 $0.9000 $1.06 $1.30 $0.8900
58514(A) 6010 PILES, FURNISHED (HP 10X42)191LF $30.00 $40.20 $34.00 $32.55 $28.00 $23.20
59514(A) 6011 PILES, FURNISHED (HP 12X53)407LF $40.00 $46.05 $44.00 $27.85 $35.00 $29.30
60514(B) 6292 PILES, DRIVEN (HP 10X42)191LF $15.00 $6.15 $24.00 $81.98 $15.00 $117.00
61514(B) 6294 PILES, DRIVEN (HP 12X53)407LF $15.00 $6.15 $34.00 $55.33 $16.00 $132.00
62514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
63515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)869SY $4.50 $3.65 $3.65 $4.73 $3.75 $3.83
64516(A) 6098 DRILLED SHAFTS 72" DIAMETER96LF $700.00 $1,682.45 $1,000.00 $1,305.60 $2,750.00 $998.00
65516(C) 6200 CROSSHOLE SONIC LOGGING4EA $1,500.00 $1,250.00 $1,000.00 $3,856.54 $2,000.00 $1,100.00
66523(A) 6550 SEALER CRACK PREPARATION52.2LF $5.50 $5.00 $5.00 $6.48 $5.20 $5.46
67523(B) 6560 SEALER RESIN1GAL $100.00 $150.00 $150.00 $194.41 $156.00 $219.00
68613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND332LF $20.00 $20.41 $35.00 $25.40 $18.00 $16.46
69613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.80LF $25.00 $19.82 $35.00 $12.48 $18.00 $16.40
70619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $18,000.00 $68,101.86 $130,000.00 $52,171.99 $50,000.00 $315,000.00
71624(E) 4294 FENCE-STYLE CLF (8'HIGH, CLASS A)192LF $120.00 $134.21 $122.50 $194.41 $58.00 $134.00
72805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS19EA $50.00 $26.00 $25.00 $32.40 $26.00 $27.61
73805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS5EA $150.00 $212.00 $100.00 $129.61 $104.00 $110.00
74850(A) 8110 SHEET ALUMINUM SIGNS107.25SF $15.00 $16.00 $14.00 $18.15 $14.50 $15.46
75851(B) 3217 2 1/2"@5.79 GALV.STEEL PIPE POST136LF $15.00 $16.00 $20.00 $25.92 $20.50 $22.07
76856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)22,016LF $0.5000 $0.7500 $0.4500 $0.5800 $0.4700 $0.5000
77856(A) 8555 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE)26LF $15.00 $11.00 $20.00 $25.92 $20.75 $22.07
78857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)2,650LF $0.2000 $0.6500 $0.2500 $0.3200 $0.2600 $0.2800
79857(C) 8851 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)566LF $0.7500 $1.11 $1.00 $1.30 $1.05 $1.10
80857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)916LF $0.2000 $0.5000 $1.00 $1.30 $1.05 $1.10
81870(A) 8485 SAND FILLED IMPACT ATTENUATION MODULE285SD $1.50 $3.30 $7.00 $9.72 $7.75 $8.28
82877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER3,500LF $25.00 $15.00 $16.00 $19.11 $20.00 $25.11
83877(C) 8486 RELOCATION OF PORTABLE LONGITUDINAL BARRIER2,550LF $4.00 $7.75 $3.50 $3.81 $2.00 $3.86
84880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF8,900SD $0.4000 $0.1500 $0.1000 $0.1300 $0.1100 $0.1100
85880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,855SD $1.10 $3.00 $3.00 $3.89 $3.10 $3.31
86880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF3,440SD $1.10 $3.00 $1.00 $1.30 $1.05 $1.10
87880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)385SD $0.7500 $2.00 $4.00 $5.18 $4.50 $4.41
88880(C) 8848 WING BARRICADES980SD $1.50 $1.55 $1.00 $1.30 $1.05 $1.10
89880(E) 8860 WARNING LIGHTS(TYPE A)2,730SD $0.2000 $0.5500 $1.00 $1.30 $1.05 $1.10
90880(F) 8878 DRUMS13,415SD $0.1500 $0.5500 $0.1000 $0.1300 $0.1200 $0.1100
91642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $20,000.00 $35,000.00 $12,000.00 $44,692.33 $24,000.00 $49,484.00
92220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $1,500.00 $3,000.00 $3,240.20 $2,096.00 $16,400.00
93641 1399 MOBILIZATION1LSUM $295,350.00 $252,348.00 $207,100.00 $210,746.17 $290,000.00 $245,000.00