Bid tab 130059

Let Jan 17, 2013 · Division 8 · Rogers Sign up free

‹ Jan 2013 results

BRIDGE AND APPROACHES SH -66: OVER PRYOR CREEK , 0.9 MILES NORTHEAST OF SH -28. PROJECT LENGTH = 0.537 MILES

Let date
Thursday, January 17, 2013
Contract
130059
J/P numbers
21920(04)
District
Division 8
County
Rogers
Highway
Limits
BRIDGE AND APPROACHES SH -66: OVER PRYOR CREEK , 0.9 MILES NORTHEAST OF SH -28. PROJECT LENGTH = 0.537 MILES
Project number
STPY-166C(155)

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$3,714,242
1 B & B BRIDGE COMPANY, LLC Low bidder $3,356,596 -9.6%
2 BECCO CONTRACTORS, INC. $3,531,322 -4.9% +5.2%
3 APAC-CENTRAL, INC. $3,648,056 -1.8% +8.7%

Bid tab: unit prices 131 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 B & B BRIDGE CO…#2 BECCO CONTRACTO…#3 APAC-CENTRAL, I…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $13,000.00 $15,000.00 $25,000.00 $21,250.58
2202(A) 0183 UNCLASSIFIED EXCAVATION8,935CY $6.00 $4.25 $7.00 $7.38
3202(D) 0184 UNCLASSIFIED BORROW20,356CY $9.00 $7.50 $7.00 $11.35
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $15,000.00 $15,000.00 $30,000.00 $19,786.85
5221(C) 2801 TEMPORARY SILT FENCE4,503LF $1.70 $1.99 $2.00 $1.93
6221(D) 2803 TEMPORARY SEDIMENT FILTER3EA $232.10 $125.00 $50.00 $152.01
7221(F) 0100 TEMPORARY SILT DIKE210LF $7.50 $9.95 $10.00 $9.21
8230(A) 2806 SOLID SLAB SODDING28,216SY $1.30 $1.29 $1.50 $1.35
9233(A) 2817 VEGETATIVE MULCHING20AC $386.80 $449.00 $450.00 $470.08
10241 2832 MOWING12AC $71.60 $59.00 $65.00 $61.77
11303(A) 2100 AGGREGATE BASE TYPE A4,055CY $32.00 $34.59 $40.00 $34.20
12307(A) 4200 FLY ASH1,091TON $56.00 $64.38 $50.00 $63.65
13307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE20,080SY $2.40 $2.94 $1.00 $2.91
14325 5271 SEPARATOR FABRIC20,764SY $1.20 $1.06 $1.00 $1.05
15402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,649TON $23.10 $18.00 $15.00 $17.88
16408 5774 PRIME COAT11,586GAL $4.90 $7.32 $3.00 $7.24
17411(B) 5940 SUPERPAVE, TYPE S3(PG 70-28 OK)2,032TON $78.00 $66.06 $65.00 $65.31
18411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)4,368TON $70.00 $57.79 $55.00 $57.14
19411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)2,110TON $82.00 $81.30 $75.00 $80.39
20411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,121TON $75.00 $76.34 $70.00 $75.48
21412 5267 COLD MILLING PAVEMENT8,205SY $3.10 $1.68 $2.00 $1.66
22413(B) 4863 RUMBLE STRIP-METHOD HMA-CYC7,428LF $0.4000 $0.1100 $0.5500 $0.8000
23501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED53CY $20.80 $45.00 $25.00 $26.17
24509(A) 0319 CLASS AA CONCRETE100.92CY $444.90 $480.00 $600.00 $415.83
25511(A) 0332 REINFORCING STEEL13,715LB $1.00 $1.30 $1.00 $0.6800
26601(A) 0297 TYPE I PLAIN RIPRAP38TON $50.00 $35.00 $50.00 $43.98
27609(B) 1513 1'-8" COMB. CURB & GUTTER (6" BARRIER)447LF $18.10 $20.00 $25.00 $16.71
28611(G) 5327 INLET GPI TYPE 1 (DES. 1)1EA $2,500.00 $2,500.00 $3,200.00 $4,033.25
29611(G) 5338 INLET GPI TYPE 2 (DES. 12)2EA $2,600.00 $3,200.00 $3,900.00 $6,133.56
30611(H) 5374 ADD'L DEPTH IN INLET GPI TYPE 10.66VF $250.00 $250.00 $250.00 $665.55
31611(H) 5375 ADD'L DEPTH IN INLET GPI TYPE 23.8VF $260.00 $300.00 $300.00 $380.12
32613(A) 0492 24" R.C.PIPE CLASS III78LF $62.80 $42.00 $65.00 $61.12
33613(B) 0689 18" CORR. GALV. STEEL PIPE348LF $25.40 $25.00 $40.00 $62.12
34613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND1EA $726.30 $950.00 $800.00 $721.14
35613(T) 1187 STANDARD BEDDING MATERIAL, CLASS C137CY $34.20 $40.00 $40.00 $62.26
36613(V) 1180 TRENCH EXCAVATION247CY $9.90 $5.00 $15.00 $14.61
37619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $8,000.00 $25,000.00 $2,315.41
38619(B) 0291 REMOVAL OF HEADWALL2EA $1,239.30 $1,500.00 $500.00 $1,598.17
39619(B) 4726 REMOVAL OF CURB AND GUTTER447LF $7.00 $5.00 $3.00 $3.81
40619(B) 4728 REMOVAL OF ASPHALT PAVEMENT12,947SY $2.60 $3.50 $2.00 $5.47
41619(B) 4763 REMOVAL OF CONCRETE PAVEMENT W/ASPHALT OVERLAY4,428SY $6.70 $6.85 $4.00 $8.13
42619(B) 4780 REMOVAL OF GUARDRAIL300LF $3.00 $4.00 $4.00 $4.19
43619(C) 0924 SAWING PAVEMENT2,881LF $3.20 $4.00 $3.00 $3.38
44623 0100 (PL)GUARDRAIL CURBING5EA $1,000.00 $1,000.00 $1,000.00 $890.95
45623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE956.25LF $16.30 $16.75 $17.00 $17.54
46623(F) 8300 GUARDRAIL TRAIL END TURNDOWN (31")1EA $3,000.00 $500.00 $500.00 $523.47
47623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,700.00 $2,200.00 $2,300.00 $2,303.27
48623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")5EA $1,500.00 $1,650.00 $1,750.00 $1,727.45
49624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)487LF $5.40 $7.00 $9.00 $8.38
50629(A) 4958 MAILBOX INSTALLATION-SINGLE1EA $87.40 $100.00 $125.00 $130.87
51629(C) 4960 MAILBOX1EA $40.00 $25.00 $30.00 $57.58
52629(D) 4961 REMOVAL OF MAILBOX INSTALLATION1EA $14.20 $5.00 $6.00 $209.38
53853 9066 GUARDRAIL DELINEATORS(TYPE 1, CODE 1)25EA $10.30 $10.00 $13.00 $11.52
54501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON90CY $12.80 $25.00 $25.00 $26.17
55501(G) 6309 CLSM BACKFILL164.6CY $108.60 $95.00 $80.00 $99.46
56503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)856LF $170.10 $200.00 $175.00 $209.39
57504(A) 1304 APPROACH SLAB218.8SY $151.70 $175.00 $180.00 $181.09
58504(B) 1305 SAW-CUT GROOVING1,112.8SY $3.90 $4.05 $4.00 $4.24
59504(E) 6190 42" F-SHAPED PARAPET527LF $79.50 $98.00 $100.00 $102.60
60506(A) 1322 STRUCTURAL STEEL1,040LB $2.90 $2.75 $1.00 $2.88
61507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY8EA $733.60 $470.00 $500.00 $492.06
62507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY16EA $2,824.40 $1,950.00 $1,800.00 $2,041.53
63507(C) 6282 ELASTOMERIC BEARING PADS16EA $488.00 $500.00 $250.00 $523.47
64509(A) 1326 CLASS AA CONCRETE268.8CY $419.80 $485.00 $400.00 $507.77
65509(B) 1328 CLASS A CONCRETE112.8CY $438.10 $485.00 $600.00 $507.77
66509(D) 1331 CLASS C CONCRETE12CY $404.90 $600.00 $400.00 $628.16
67511(B) 6010 EPOXY COATED REINFORCING STEEL100,110LB $1.00 $1.00 $1.50 $1.05
68514(A) 6010 PILES, FURNISHED (HP 10X42)344LF $28.60 $29.00 $30.00 $30.36
69514(B) 6292 PILES, DRIVEN (HP 10X42)344LF $11.70 $22.00 $25.00 $23.03
70515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)944SY $3.60 $3.65 $4.00 $3.82
71516(A) 6094 DRILLED SHAFTS 48" DIAMETER112LF $494.30 $595.00 $700.00 $622.93
72523(A) 6550 SEALER CRACK PREPARATION152LF $4.00 $4.00 $4.00 $4.19
73523(B) 6560 SEALER RESIN1.7GAL $139.00 $100.00 $110.00 $104.69
74601(B) 1353 TYPE I-A PLAIN RIPRAP960TON $34.30 $30.00 $35.00 $31.41
75601(C) 1355 TYPE I-A FILTER BLANKET230TON $28.30 $32.00 $25.00 $33.50
76613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND82LF $20.60 $25.00 $40.00 $26.17
77613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.40LF $19.80 $25.00 $40.00 $26.17
78619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $30,000.00 $30,000.00 $60,000.00 $31,408.16
79501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON90CY $12.80 $25.00 $25.00 $26.17
80501(G) 6309 CLSM BACKFILL164.6CY $108.60 $95.00 $80.00 $99.46
81503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)856LF $170.10 $200.00 $175.00 $209.39
82504(A) 1304 APPROACH SLAB218.8SY $151.70 $175.00 $180.00 $180.04
83504(B) 1305 SAW-CUT GROOVING1,112.8SY $3.90 $4.05 $4.00 $4.24
84504(E) 6190 42" F-SHAPED PARAPET527LF $79.50 $98.00 $100.00 $102.60
85506(A) 1322 STRUCTURAL STEEL1,040LB $2.90 $2.75 $1.00 $2.88
86507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY8EA $733.60 $470.00 $500.00 $492.06
87507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY16EA $2,824.40 $1,950.00 $1,800.00 $2,041.53
88507(C) 6282 ELASTOMERIC BEARING PADS16EA $488.00 $500.00 $250.00 $523.47
89509(A) 1326 CLASS AA CONCRETE268.8CY $419.80 $485.00 $400.00 $507.77
90509(B) 1328 CLASS A CONCRETE112.8CY $438.10 $485.00 $600.00 $507.77
91509(D) 1331 CLASS C CONCRETE12CY $404.90 $600.00 $400.00 $628.16
92511(B) 6010 EPOXY COATED REINFORCING STEEL100,110LB $1.00 $1.00 $1.50 $1.05
93514(A) 6010 PILES, FURNISHED (HP 10X42)352LF $28.60 $29.00 $30.00 $30.36
94514(B) 6292 PILES, DRIVEN (HP 10X42)352LF $11.70 $22.00 $25.00 $23.03
95515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)944SY $3.60 $3.65 $4.00 $3.82
96516(A) 6094 DRILLED SHAFTS 48" DIAMETER114LF $494.30 $595.00 $700.00 $622.93
97523(A) 6550 SEALER CRACK PREPARATION152LF $4.00 $4.00 $4.00 $4.19
98523(B) 6560 SEALER RESIN1.7GAL $139.00 $100.00 $110.00 $104.69
99601(B) 1353 TYPE I-A PLAIN RIPRAP960TON $34.30 $30.00 $35.00 $31.41
100601(C) 1355 TYPE I-A FILTER BLANKET230TON $28.30 $32.00 $25.00 $33.50
101613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND82LF $20.60 $25.00 $40.00 $26.17
102613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.40LF $19.80 $25.00 $40.00 $26.17
103619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $30,000.00 $25,000.00 $60,000.00 $26,173.47
104857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)11,000LF $0.2000 $0.2500 $0.3200 $0.3700
105857(C) 8851 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)22,000LF $0.6000 $0.2500 $0.3200 $0.8900
106857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)1,000LF $0.6000 $0.5000 $0.6500 $0.8900
107877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER700LF $22.20 $26.51 $25.00 $41.68
108877(C) 8486 RELOCATION OF PORTABLE LONGITUDINAL BARRIER700LF $4.40 $3.17 $8.00 $10.70
109880(A) 8812 ARROW DISPLAY(TYPE C)600SD $3.40 $5.00 $6.00 $26.17
110880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF19,000SD $0.1000 $0.0500 $0.0600 $0.0500
111880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF23,000SD $0.2000 $0.0500 $0.0600 $0.0200
112880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF17,000SD $0.4000 $0.0500 $0.0600 $0.0500
113880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)7,000SD $0.2000 $1.00 $1.25 $0.3700
114880(C) 8848 WING BARRICADES1,200SD $0.7000 $5.00 $6.50 $1.05
115880(E) 8860 WARNING LIGHTS(TYPE A)24,000SD $0.1000 $0.1000 $0.1300 $0.1000
116880(E) 8872 WARNING LIGHTS(TYPE C)31,000SD $0.1000 $0.0200 $0.0300 $0.0200
117880(F) 8878 DRUMS31,000SD $0.1000 $0.1000 $0.1300 $0.3700
118880(G) 8884 TUBE CHANNELIZERS12,000SD $0.3000 $0.2500 $0.3200 $0.3700
119880(G) 8890 CHANNELIZER CONES3,000SD $0.3000 $0.1000 $0.1300 $0.3700
120882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN600SD $11.10 $10.00 $13.00 $15.70
121805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS34EA $45.00 $25.00 $32.00 $20.94
122805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS2EA $202.40 $100.00 $125.00 $209.39
123850(A) 8110 SHEET ALUMINUM SIGNS250.63SF $15.60 $12.00 $15.00 $15.70
124851(C) 8324 2" SQUARE TUBE POST29.36LF $11.90 $6.00 $8.00 $12.56
125851(C) 8330 2 1/2" SQUARE TUBE POST408.67LF $11.90 $6.00 $8.00 $10.47
126855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)15,200LF $0.6000 $0.5000 $0.6500 $1.05
127855(A) 8825 TRAFFIC STRIPE(PLASTIC)(24" WIDE)100LF $6.70 $10.00 $13.00 $6.28
128642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $17,000.00 $14,000.00 $25,000.00 $37,794.49
129220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,330.00 $5,500.00 $3,500.00 $3,422.49
130640(A) 1398 FIELD OFFICE1EA $7,763.20 $7,300.00 $6,000.00 $10,718.82
131641 1399 MOBILIZATION1LSUM $59,627.90 $100,000.00 $200,000.00 $85,772.59