| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$4,240.00 |
$15,000.00 |
$60,000.00 |
$4,440.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 9,738 | CY |
$6.50 |
$4.24 |
$5.25 |
$5.85 |
$4.44 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 17,327 | CY |
$5.25 |
$5.83 |
$6.25 |
$7.75 |
$6.11 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$45,000.00 |
$10,600.00 |
$10,000.00 |
$19,500.00 |
$11,100.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,325 | LF |
$1.50 |
$1.59 |
$2.00 |
$1.73 |
$2.99 |
| 6 | 221(E) 2804 |
TEMPORARY SEDIMENT BASIN | 1 | EA |
$5,000.00 |
$1,060.00 |
$750.00 |
$172.50 |
$999.99 |
| 7 | 221(F) 0100 |
TEMPORARY SILT DIKE | 126 | LF |
$7.00 |
$7.42 |
$7.50 |
$8.05 |
$9.99 |
| 8 | 230(A) 2806 |
SOLID SLAB SODDING | 47,349 | SY |
$1.25 |
$1.17 |
$1.30 |
$1.27 |
$1.37 |
| 9 | 233(A) 2817 |
VEGETATIVE MULCHING | 9.41 | AC |
$260.00 |
$318.00 |
$650.00 |
$345.00 |
$702.63 |
| 10 | 234(A) 2824 |
FERTILIZING (10-20-10) | 4.55 | TON |
$500.00 |
$848.00 |
$925.00 |
$920.00 |
$980.83 |
| 11 | 241 2832 |
MOWING | 9.41 | AC |
$51.00 |
$106.00 |
$100.00 |
$115.00 |
$107.95 |
| 12 | 307(A) 4200 |
FLY ASH | 877 | TON |
$65.00 |
$61.48 |
$60.00 |
$66.70 |
$64.38 |
| 13 | 307(D) 4230 |
LIME | 82 | TON |
$130.00 |
$148.40 |
$145.00 |
$161.00 |
$155.40 |
| 14 | 307(E) 4240 |
CEMENTITIOUS STABILIZED SUBGRADE | 16,224 | SY |
$2.50 |
$2.11 |
$2.15 |
$2.47 |
$2.21 |
| 15 | 307(G) 4260 |
LIME PRETREATMENT | 5,679 | SY |
$2.00 |
$1.06 |
$1.10 |
$1.15 |
$1.11 |
| 16 | 402(A) 0217 |
TRAFFIC BOUND SURFACE COURSE TYPE A | 218 | TON |
$22.00 |
$27.61 |
$31.25 |
$33.00 |
$29.47 |
| 17 | 407(B) 0250 |
TACK COAT | 5,469 | GAL |
$2.50 |
$3.18 |
$2.40 |
$2.59 |
$2.51 |
| 18 | 408 5774 |
PRIME COAT | 4,138 | GAL |
$4.00 |
$6.78 |
$6.55 |
$7.16 |
$6.90 |
| 19 | 411(B) 5940 |
SUPERPAVE, TYPE S3(PG 70-28 OK) | 1,457 | TON |
$68.00 |
$80.83 |
$80.00 |
$87.40 |
$84.36 |
| 20 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 7,854 | TON |
$62.00 |
$64.66 |
$69.00 |
$75.33 |
$72.70 |
| 21 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 971 | TON |
$75.00 |
$95.51 |
$89.00 |
$96.60 |
$93.24 |
| 22 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 2,411 | TON |
$70.00 |
$76.85 |
$74.00 |
$80.50 |
$77.70 |
| 23 | 501(A) 0313 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 99 | CY |
$15.00 |
$10.60 |
$75.00 |
$12.00 |
$19.99 |
| 24 | 504(E) 6190 |
42" F-SHAPED PARAPET | 222 | LF |
$75.00 |
$116.60 |
$77.50 |
$88.00 |
$79.99 |
| 25 | 509(A) 0319 |
CLASS AA CONCRETE | 321.46 | CY |
$400.00 |
$337.08 |
$375.00 |
$405.00 |
$374.99 |
| 26 | 509(D) 0325 |
CLASS C CONCRETE | 25 | CY |
$250.00 |
$424.00 |
$275.00 |
$425.00 |
$219.99 |
| 27 | 511(A) 0332 |
REINFORCING STEEL | 40,544 | LB |
$0.8500 |
$0.9000 |
$0.9000 |
$0.9200 |
$0.9800 |
| 28 | 511(B) 4269 |
EPOXY COATED REINFORCING STEEL | 7,080 | LB |
$1.00 |
$0.9500 |
$1.15 |
$1.05 |
$1.08 |
| 29 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 124 | LF |
$45.00 |
$41.94 |
$40.00 |
$45.00 |
$59.99 |
| 30 | 613(B) 0689 |
18" CORR. GALV. STEEL PIPE | 258 | LF |
$35.00 |
$24.70 |
$27.25 |
$21.00 |
$22.99 |
| 31 | 613(H) 0500 |
8" PERFORATED PIPE UNDERDRAIN ROUND | 235 | LF |
$9.00 |
$21.78 |
$7.50 |
$18.00 |
$19.99 |
| 32 | 613(I) 1097 |
8" NON-PERF.PIPE UNDERDRAIN RND. | 79 | LF |
$9.00 |
$21.78 |
$7.50 |
$18.00 |
$19.99 |
| 33 | 613(L) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$500.00 |
$529.51 |
$600.00 |
$800.00 |
$1,236.98 |
| 34 | 613(M) 7196 |
TYPE A6 CULVERT END TREATMENT | 4 | EA |
$750.00 |
$954.00 |
$775.00 |
$1,215.00 |
$1,050.00 |
| 35 | 613(Q) 5946 |
OUTLET LATERAL HEADWALL | 1 | EA |
$500.00 |
$669.79 |
$345.00 |
$1,000.00 |
$525.25 |
| 36 | 613(S) 1186 |
STANDARD BEDDING MATERIAL, CLASS B | 48 | CY |
$20.00 |
$65.94 |
$30.00 |
$60.00 |
$84.00 |
| 37 | 613(U) 1100 |
PIPE UNDERDRAIN COVER MAT'L. | 71 | CY |
$15.00 |
$59.82 |
$60.00 |
$60.00 |
$84.00 |
| 38 | 613(V) 1180 |
TRENCH EXCAVATION | 218 | CY |
$12.00 |
$10.60 |
$5.00 |
$7.00 |
$15.99 |
| 39 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$15,000.00 |
$1,060.00 |
$10,000.00 |
$15,000.00 |
$1,250.00 |
| 40 | 619(B) 0291 |
REMOVAL OF HEADWALL | 3 | EA |
$1,000.00 |
$2,067.00 |
$4,000.00 |
$1,100.00 |
$1,249.99 |
| 41 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 8,669 | SY |
$3.25 |
$3.18 |
$1.75 |
$2.15 |
$1.67 |
| 42 | 619(C) 0924 |
SAWING PAVEMENT | 64 | LF |
$5.50 |
$10.60 |
$4.25 |
$11.00 |
$11.11 |
| 43 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 1,537.5 | LF |
$16.00 |
$15.85 |
$16.75 |
$17.19 |
$16.59 |
| 44 | 623(F) 4447 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 1 | EA |
$580.00 |
$530.00 |
$1,300.00 |
$575.00 |
$555.99 |
| 45 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 9 | EA |
$2,000.00 |
$2,210.10 |
$2,000.00 |
$2,400.00 |
$2,314.35 |
| 46 | 623(I) 8675 |
GUARDRAIL BRIDGE CONNECTION-TYPE A | 15 | EA |
$1,800.00 |
$1,388.60 |
$1,650.00 |
$1,506.50 |
$1,454.10 |
| 47 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 2,079 | LF |
$3.50 |
$3.68 |
$4.00 |
$4.00 |
$5.99 |
| 48 | 625(D) 1254 |
REMOVE AND RECONSTRUCT GUARDRAIL | 75 | LF |
$12.00 |
$15.85 |
$10.00 |
$17.19 |
$16.59 |
| 49 | 853 9069 |
GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 55 | EA |
$1.50 |
$10.60 |
$40.00 |
$28.75 |
$10.00 |
| 50 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 80 | CY |
$12.00 |
$20.90 |
$75.00 |
$8.00 |
$14.99 |
| 51 | 501(G) 6309 |
CLSM BACKFILL | 164 | CY |
$120.00 |
$123.15 |
$110.00 |
$130.00 |
$128.99 |
| 52 | 503(A) 1312 |
PRESTRESSED CONCRETE BEAMS (TYPE III) | 777 | LF |
$180.00 |
$178.19 |
$195.00 |
$172.50 |
$197.50 |
| 53 | 504(A) 1304 |
APPROACH SLAB | 224.8 | SY |
$150.00 |
$174.36 |
$165.00 |
$165.00 |
$200.00 |
| 54 | 504(B) 1305 |
SAW-CUT GROOVING | 1,091.1 | SY |
$4.00 |
$3.47 |
$4.00 |
$3.65 |
$4.99 |
| 55 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 487 | LF |
$65.00 |
$74.32 |
$60.00 |
$70.00 |
$64.99 |
| 56 | 506(A) 1322 |
STRUCTURAL STEEL | 1,050 | LB |
$2.50 |
$3.65 |
$3.00 |
$3.00 |
$2.99 |
| 57 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 8 | EA |
$500.00 |
$729.88 |
$1,000.00 |
$800.00 |
$399.99 |
| 58 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 16 | EA |
$3,000.00 |
$2,925.54 |
$2,500.00 |
$2,600.00 |
$1,999.99 |
| 59 | 507(C) 6282 |
ELASTOMERIC BEARING PADS | 16 | EA |
$350.00 |
$424.25 |
$200.00 |
$600.00 |
$400.00 |
| 60 | 509(A) 1326 |
CLASS AA CONCRETE | 258.4 | CY |
$450.00 |
$454.98 |
$450.00 |
$480.00 |
$575.99 |
| 61 | 509(B) 1328 |
CLASS A CONCRETE | 122.6 | CY |
$400.00 |
$425.16 |
$600.00 |
$510.00 |
$475.99 |
| 62 | 509(D) 1331 |
CLASS C CONCRETE | 25 | CY |
$300.00 |
$463.46 |
$500.00 |
$500.00 |
$255.55 |
| 63 | 511(A) 1332 |
REINFORCING STEEL | 560 | LB |
$0.9000 |
$1.74 |
$1.25 |
$1.25 |
$1.99 |
| 64 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 76,520 | LB |
$1.00 |
$1.13 |
$1.00 |
$1.05 |
$1.25 |
| 65 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 1,048 | LF |
$30.00 |
$25.91 |
$32.50 |
$23.80 |
$34.99 |
| 66 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 1,048 | LF |
$15.00 |
$11.00 |
$10.00 |
$10.20 |
$9.99 |
| 67 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 868 | SY |
$4.00 |
$3.85 |
$4.00 |
$4.03 |
$4.99 |
| 68 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 282 | LF |
$600.00 |
$727.36 |
$600.00 |
$575.00 |
$777.00 |
| 69 | 523(A) 6550 |
SEALER CRACK PREPARATION | 163 | LF |
$5.00 |
$4.40 |
$5.00 |
$4.60 |
$4.99 |
| 70 | 523(B) 6560 |
SEALER RESIN | 1.8 | GAL |
$200.00 |
$165.00 |
$200.00 |
$172.50 |
$166.99 |
| 71 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 810 | TON |
$30.00 |
$38.84 |
$37.50 |
$36.31 |
$37.99 |
| 72 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 175 | TON |
$30.00 |
$30.86 |
$30.00 |
$29.05 |
$32.99 |
| 73 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 84 | LF |
$25.00 |
$35.47 |
$22.00 |
$28.00 |
$100.00 |
| 74 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 80 | LF |
$25.00 |
$23.96 |
$15.00 |
$28.00 |
$100.00 |
| 75 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$25,000.00 |
$27,500.00 |
$25,000.00 |
$22,000.00 |
$75,000.00 |
| 76 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 260 | CY |
$12.00 |
$11.00 |
$50.00 |
$8.00 |
$14.99 |
| 77 | 501(G) 6309 |
CLSM BACKFILL | 186.8 | CY |
$120.00 |
$101.15 |
$110.00 |
$130.00 |
$128.99 |
| 78 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 1,196 | LF |
$190.00 |
$205.12 |
$220.00 |
$203.00 |
$225.00 |
| 79 | 504(A) 1304 |
APPROACH SLAB | 262.4 | SY |
$150.00 |
$174.36 |
$165.00 |
$165.00 |
$200.00 |
| 80 | 504(B) 1305 |
SAW-CUT GROOVING | 1,598.6 | SY |
$4.00 |
$3.47 |
$4.00 |
$3.65 |
$4.99 |
| 81 | 504(C) 6250 |
SEALED EXPANSION JOINT | 51.05 | LF |
$250.00 |
$330.50 |
$275.00 |
$280.00 |
$229.99 |
| 82 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 719.1 | LF |
$65.00 |
$74.32 |
$60.00 |
$70.00 |
$64.99 |
| 83 | 506(A) 1322 |
STRUCTURAL STEEL | 1,660 | LB |
$2.50 |
$3.65 |
$3.00 |
$3.00 |
$2.99 |
| 84 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 8 | EA |
$3,000.00 |
$2,831.54 |
$2,750.00 |
$2,800.00 |
$1,999.99 |
| 85 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 16 | EA |
$3,000.00 |
$2,831.54 |
$2,750.00 |
$2,800.00 |
$1,999.99 |
| 86 | 509(A) 1326 |
CLASS AA CONCRETE | 355.7 | CY |
$450.00 |
$427.48 |
$450.00 |
$480.00 |
$574.99 |
| 87 | 509(B) 1328 |
CLASS A CONCRETE | 226.5 | CY |
$400.00 |
$425.16 |
$500.00 |
$510.00 |
$474.99 |
| 88 | 509(D) 1331 |
CLASS C CONCRETE | 25 | CY |
$300.00 |
$463.46 |
$500.00 |
$500.00 |
$225.99 |
| 89 | 511(A) 1332 |
REINFORCING STEEL | 980 | LB |
$0.9000 |
$1.74 |
$1.25 |
$1.25 |
$1.99 |
| 90 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 122,570 | LB |
$1.00 |
$1.13 |
$1.00 |
$1.05 |
$1.25 |
| 91 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 316 | LF |
$30.00 |
$25.62 |
$32.50 |
$23.80 |
$35.00 |
| 92 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 1,342 | LF |
$35.00 |
$31.44 |
$37.50 |
$28.00 |
$40.00 |
| 93 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 316 | LF |
$15.00 |
$11.00 |
$10.00 |
$10.20 |
$10.00 |
| 94 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 1,342 | LF |
$15.00 |
$11.00 |
$10.00 |
$12.00 |
$10.00 |
| 95 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,421 | SY |
$4.00 |
$3.85 |
$4.00 |
$4.03 |
$15.00 |
| 96 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 288 | LF |
$600.00 |
$760.32 |
$600.00 |
$605.00 |
$777.00 |
| 97 | 523(A) 6550 |
SEALER CRACK PREPARATION | 49.7 | LF |
$5.00 |
$4.40 |
$5.00 |
$4.60 |
$12.50 |
| 98 | 523(B) 6560 |
SEALER RESIN | 0.6 | GAL |
$200.00 |
$165.00 |
$200.00 |
$172.50 |
$200.00 |
| 99 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 580 | TON |
$30.00 |
$38.84 |
$37.50 |
$37.31 |
$39.99 |
| 100 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 120 | TON |
$30.00 |
$30.86 |
$30.00 |
$30.00 |
$34.99 |
| 101 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 100 | LF |
$25.00 |
$35.17 |
$22.00 |
$28.00 |
$100.00 |
| 102 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 36 | LF |
$25.00 |
$26.35 |
$15.00 |
$28.00 |
$100.00 |
| 103 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$60,000.00 |
$38,500.00 |
$30,000.00 |
$32,500.00 |
$75,000.00 |
| 104 | 509(A) 1326 |
CLASS AA CONCRETE | 8.9 | CY |
$450.00 |
$977.48 |
$1,250.00 |
$1,100.00 |
$999.99 |
| 105 | 511(A) 1332 |
REINFORCING STEEL | 270 | LB |
$0.9000 |
$1.66 |
$5.00 |
$2.00 |
$4.99 |
| 106 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 950 | LB |
$1.00 |
$1.79 |
$5.00 |
$1.50 |
$1.99 |
| 107 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$1,000.00 |
$1,100.00 |
$5,000.00 |
$5,000.00 |
$1,499.99 |
| 108 | 805(A) 8724 |
(PL)REMOVAL OF EXISTING SIGNS | 3 | EA |
$20.00 |
$53.00 |
$55.00 |
$57.50 |
$22.50 |
| 109 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 20 | EA |
$102.50 |
$106.00 |
$105.00 |
$115.00 |
$100.00 |
| 110 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 210 | SD |
$98.44 |
$127.20 |
$100.00 |
$138.00 |
$225.00 |
| 111 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 12.5 | SF |
$16.00 |
$14.84 |
$15.00 |
$16.10 |
$18.87 |
| 112 | 851(C) 8324 |
2" SQUARE TUBE POST | 28 | LF |
$13.00 |
$8.48 |
$8.50 |
$9.20 |
$9.99 |
| 113 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 15,500 | LF |
$0.5000 |
$0.6600 |
$0.6500 |
$0.7200 |
$0.5600 |
| 114 | 855(B) 8824 |
TRAFFIC STRIPE(PLASTIC)(SYMBOLS) | 2 | EA |
$125.00 |
$530.00 |
$525.00 |
$575.00 |
$499.50 |
| 115 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 21,000 | SD |
$0.5000 |
$0.2700 |
$0.2600 |
$0.2900 |
$0.0300 |
| 116 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,260 | SD |
$0.7000 |
$2.12 |
$2.10 |
$2.30 |
$0.5500 |
| 117 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 4,620 | SD |
$1.15 |
$0.8000 |
$0.8000 |
$0.8700 |
$0.5500 |
| 118 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 2,100 | SD |
$0.7500 |
$1.06 |
$1.05 |
$1.15 |
$1.11 |
| 119 | 880(C) 8848 |
WING BARRICADES | 840 | SD |
$2.76 |
$1.06 |
$1.05 |
$1.15 |
$2.22 |
| 120 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 7,980 | SD |
$0.1900 |
$0.1100 |
$0.1100 |
$0.1200 |
$0.5500 |
| 121 | 880(F) 8878 |
DRUMS | 2,100 | SD |
$0.2500 |
$0.2700 |
$0.2600 |
$0.3000 |
$0.3000 |
| 122 | 880(G) 8890 |
CHANNELIZER CONES | 6,300 | SD |
$0.1600 |
$0.1600 |
$0.1600 |
$0.2000 |
$0.0300 |
| 123 | 880(I) 8902 |
FLAGGER | 60 | SD |
$300.00 |
$307.40 |
$10.00 |
$300.00 |
$150.00 |
| 124 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$47,850.00 |
$18,682.50 |
$20,000.00 |
$24,000.00 |
$22,499.99 |
| 125 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,763.00 |
$3,000.00 |
$7,500.00 |
$7,799.99 |
| 126 | 640(A) 1426 |
FIELD OFFICE | 1 | EA |
$10,000.00 |
$7,367.00 |
$12,000.00 |
$10,000.00 |
$4,999.99 |
| 127 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$211,434.00 |
$192,940.93 |
$217,500.00 |
$185,000.00 |
$230,000.00 |