Bid tab 160307

Let Aug 18, 2016 · Division 6 · Woodward Sign up free

‹ Aug 2016 results

BRIDGE AND APPROACHES SH - 34: OVER INDIAN CREEK, 2.3 MILES SOUTH OF THE US -183 JUNCTION NEAR WOODWARD . PROJECT LENGTH = 0.199 MILE

Let date
Thursday, August 18, 2016
Contract
160307
J/P numbers
27924(04)
District
Division 6
County
Woodward
Highway
Limits
BRIDGE AND APPROACHES SH - 34: OVER INDIAN CREEK, 2.3 MILES SOUTH OF THE US -183 JUNCTION NEAR WOODWARD . PROJECT LENGTH = 0.199 MILE
Project number
ACSTP-277B(032)SS

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,260,988
1 SEWELL BROS., INC. Low bidder $2,177,004 -3.7%
2 Bridges, Inc. DBA Scudder Bridge Co. $2,333,725 +3.2% +7.2%
3 RRY SERVICES LLC $2,411,546 +6.7% +10.8%
4 L & M Contractors, Inc. $2,447,008 +8.2% +12.4%
5 A. M. COHRON & SON, INC. $2,524,062 +11.6% +15.9%
6 FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. $2,556,341 +13.1% +17.4%
7 OBC, INC. $2,578,177 +14.0% +18.4%
8 HASKELL LEMON CONSTRUCTION CO. $2,642,179 +16.9% +21.4%

Bid tab: unit prices 80 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SEWELL BROS., I…#2 Bridges, Inc. D…#3 RRY SERVICES LLC#4 L & M Contracto…#5 A. M. COHRON & …#6 FRONTIER BRIDGE…#7 OBC, INC.#8 HASKELL LEMON C…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $8,000.00 $10,000.00 $7,000.00 $15,000.00 $20,000.00 $5,000.00 $8,560.00 $8,520.00 $9,198.00
2202(A) 0183 UNCLASSIFIED EXCAVATION3,069CY $8.00 $7.50 $12.50 $12.00 $8.00 $12.00 $8.56 $8.52 $9.20
3202(D) 0184 UNCLASSIFIED BORROW4,248CY $12.00 $8.50 $11.50 $12.00 $12.00 $17.00 $12.84 $12.78 $13.80
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $18,684.50 $15,000.00 $10,000.00 $35,000.00 $15,000.00 $10,000.00 $16,050.00 $15,975.00 $17,245.00
5221(C) 2801 TEMPORARY SILT FENCE1,038LF $1.70 $1.55 $2.00 $1.39 $1.40 $1.19 $2.30 $1.49 $1.55
6221(F) 0100 TEMPORARY SILT DIKE336LF $6.88 $13.00 $12.50 $6.90 $12.00 $6.99 $9.63 $12.78 $7.80
7221(K) 0600 TEMPORARY FIBER LOG1,972LF $4.00 $5.00 $5.00 $2.65 $4.50 $2.31 $5.62 $4.79 $2.95
8230(A) 2806 SOLID SLAB SODDING3,824SY $2.00 $3.25 $3.10 $1.58 $3.10 $3.10 $5.30 $3.30 $1.75
9233(A) 2817 VEGETATIVE MULCHING3.23AC $430.00 $55.00 $50.00 $400.00 $50.00 $50.00 $963.00 $53.25 $460.00
10241 2832 MOWING7.54AC $200.00 $75.00 $68.00 $75.00 $68.00 $68.00 $267.50 $72.42 $84.70
11307(K) 4300 STABILIZED SUBGRADE4,026SY $7.15 $7.45 $6.95 $6.95 $7.15 $6.95 $7.65 $7.61 $8.20
12310(B) 0149 SUBGRADE, METHOD B4,555SY $5.00 $5.45 $2.25 $2.25 $3.00 $2.25 $3.21 $3.20 $3.45
13402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E151TON $59.00 $42.00 $40.30 $45.00 $60.00 $50.00 $63.13 $62.84 $67.80
14407(B) 0250 TACK COAT1,184GAL $4.00 $4.95 $4.50 $4.50 $4.50 $4.50 $4.82 $4.79 $4.95
15408 5774 PRIME COAT3,265GAL $9.00 $4.95 $4.50 $4.50 $4.50 $4.50 $4.82 $1.00 $9.15
16411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)2,606TON $95.00 $111.00 $92.25 $92.25 $92.25 $92.25 $98.71 $98.25 $85.70
17411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)994TON $110.00 $143.00 $105.00 $105.00 $105.00 $105.00 $112.35 $111.83 $100.50
18613(B) 0692 36" CORR. GALV. STEEL PIPE78LF $46.00 $45.00 $56.60 $100.00 $46.00 $110.00 $49.22 $48.99 $52.90
19613(B) 5739 84" CORR. GALV. STEEL PIPE342LF $150.00 $120.00 $150.00 $125.00 $120.00 $175.00 $128.40 $127.80 $138.00
20613(M) 7196 TYPE A6 CULVERT END TREATMENT1EA $1,045.00 $1,250.00 $1,600.00 $2,300.00 $1,200.00 $2,200.00 $1,284.00 $1,278.00 $1,380.00
21613(M) 7199 TYPE D6 CULVERT END TREATMENT1EA $2,185.00 $1,250.00 $2,200.00 $4,800.00 $3,000.00 $2,800.00 $3,210.00 $3,195.00 $3,449.00
22619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $5,000.00 $5,500.00 $15,000.00 $10,000.00 $1,500.00 $10,700.00 $17,600.00 $11,495.00
23619(B) 4728 REMOVAL OF ASPHALT PAVEMENT4,246SY $6.00 $5.50 $4.80 $4.80 $6.00 $4.80 $9.42 $5.11 $10.20
24619(B) 4780 REMOVAL OF GUARDRAIL1,019LF $5.50 $3.00 $3.50 $3.14 $7.00 $3.00 $3.21 $3.20 $3.45
25619(C) 0924 SAWING PAVEMENT1,107LF $4.50 $4.00 $4.50 $5.00 $7.00 $10.00 $6.48 $5.33 $6.95
26623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE635LF $18.50 $18.15 $19.00 $15.28 $18.00 $16.45 $17.66 $17.57 $19.00
27623(F) 8300 GUARDRAIL TRAIL END TURNDOWN (31")1EA $535.00 $875.00 $800.00 $470.96 $1,000.00 $850.00 $850.65 $846.68 $914.00
28623(G) 8590 GUARDRAIL END TREATMENT (31")3EA $2,250.00 $2,425.00 $2,200.00 $2,200.00 $2,500.00 $2,390.00 $2,354.00 $2,343.00 $2,529.00
29623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $1,800.00 $1,700.00 $1,500.00 $1,650.00 $1,800.00 $2,260.00 $1,658.50 $1,650.75 $1,782.00
30624(B) 4466 GATES-STYLE WWF (4.5'HIGH X 16'LONG)1EA $900.00 $770.00 $700.00 $700.00 $1,000.00 $754.00 $749.00 $745.50 $805.00
31624(C) 7181 FENCE-STYLE SWF (6 BARBED WIRE)1,405LF $5.00 $8.20 $3.95 $3.95 $6.00 $8.49 $7.97 $4.21 $4.55
32853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)19EA $16.50 $14.00 $10.00 $15.00 $15.00 $11.95 $13.38 $13.31 $14.40
33501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON270CY $25.00 $15.00 $24.00 $25.00 $35.00 $20.00 $27.50 $23.65 $20.70
34501(G) 6309 CLSM BACKFILL30.8CY $240.00 $150.00 $180.00 $175.00 $160.00 $210.00 $230.32 $172.47 $166.00
35503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)896LF $268.00 $250.00 $340.00 $265.00 $270.00 $350.00 $280.06 $421.56 $276.00
36504(A) 1304 APPROACH SLAB409.6SY $200.00 $220.00 $170.00 $260.00 $185.00 $200.00 $225.16 $154.97 $253.50
37504(B) 1305 SAW-CUT GROOVING1,385.3SY $5.00 $4.45 $5.00 $4.05 $6.00 $5.00 $4.46 $4.31 $4.65
38504(C) 6250 SEALED EXPANSION JOINT56.9LF $275.00 $230.00 $260.00 $350.00 $300.00 $250.00 $281.59 $280.47 $284.00
39504(D) 6245 CONCRETE RAIL (TR4)623.34LF $90.00 $85.00 $85.00 $90.00 $80.00 $90.00 $97.73 $94.10 $124.00
40506(A) 1322 STRUCTURAL STEEL510LB $4.00 $2.50 $3.50 $3.00 $5.00 $5.00 $3.04 $2.68 $5.25
41507(A) 6170 STAINLESS STEEL FIXED BEARING ASSEMBLY16EA $1,800.00 $1,400.00 $1,500.00 $1,900.00 $1,350.00 $1,500.00 $1,501.11 $1,500.00 $1,759.00
42507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY8EA $1,800.00 $1,400.00 $1,500.00 $1,900.00 $1,350.00 $1,500.00 $1,501.11 $1,500.00 $1,753.00
43509(A) 1326 CLASS AA CONCRETE280.1CY $600.00 $500.00 $550.00 $675.00 $640.00 $735.00 $644.31 $900.00 $623.00
44509(B) 1328 CLASS A CONCRETE227.2CY $600.00 $500.00 $575.00 $675.00 $640.00 $630.00 $667.17 $850.00 $764.00
45509(D) 1331 CLASS C CONCRETE9.3CY $600.00 $500.00 $550.00 $500.00 $400.00 $760.00 $638.25 $1,157.57 $692.00
46511(B) 6010 EPOXY COATED REINFORCING STEEL92,960LB $1.10 $0.9000 $1.00 $1.10 $1.00 $1.00 $1.14 $1.20 $1.30
47514(A) 6010 PILES, FURNISHED (HP 10X42)292LF $40.00 $25.00 $41.00 $35.00 $42.00 $36.00 $30.47 $22.56 $37.10
48514(A) 6011 PILES, FURNISHED (HP 12X53)1,314LF $40.00 $30.00 $50.00 $50.00 $45.00 $42.00 $35.33 $27.04 $39.30
49514(B) 6292 PILES, DRIVEN (HP 10X42)292LF $15.00 $15.00 $9.00 $10.00 $8.00 $5.00 $16.50 $21.76 $21.80
50514(B) 6294 PILES, DRIVEN (HP 12X53)1,314LF $15.00 $15.00 $10.00 $10.00 $8.00 $5.00 $17.60 $22.85 $21.10
51514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
52515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)1,154SY $4.00 $3.50 $4.00 $4.00 $5.50 $4.00 $3.30 $3.20 $3.45
53516(A) 6096 DRILLED SHAFTS 60" DIAMETER300LF $800.00 $850.00 $1,100.00 $1,000.00 $1,055.00 $1,050.00 $1,150.94 $850.00 $854.50
54516(C) 6200 CROSSHOLE SONIC LOGGING1EA $1,800.00 $2,000.00 $2,850.00 $4,000.00 $3,000.00 $1,500.00 $14,850.00 $1,597.50 $4,599.00
55523(A) 6550 SEALER CRACK PREPARATION54.8LF $4.00 $5.00 $6.00 $6.00 $7.50 $6.00 $6.60 $6.39 $6.90
56523(B) 6560 SEALER RESIN0.7GAL $100.00 $200.00 $200.00 $200.00 $310.00 $200.00 $220.00 $213.00 $230.00
57601(B) 1353 TYPE I-A PLAIN RIPRAP1,470TON $55.00 $62.00 $56.00 $75.00 $57.00 $65.00 $65.41 $63.34 $62.80
58601(C) 1355 TYPE I-A FILTER BLANKET268TON $50.00 $44.00 $47.00 $55.00 $50.00 $50.00 $49.33 $44.05 $53.30
59613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND114LF $30.00 $25.00 $28.00 $30.00 $40.00 $27.00 $30.55 $25.28 $53.60
60613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.70LF $30.00 $30.00 $28.00 $30.00 $40.00 $30.00 $29.98 $19.28 $24.00
61619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $50,000.00 $40,000.00 $30,000.00 $45,000.00 $50,000.00 $35,000.00 $110,748.78 $112,250.00 $62,915.00
62857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)6,000LF $0.1500 $0.3700 $0.1500 $0.3500 $0.3500 $0.2800 $0.3900 $0.3700 $0.4000
63857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)7,500LF $0.2600 $0.1200 $0.1500 $0.1000 $0.1000 $0.9500 $0.1100 $0.1100 $0.1100
64880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF3,520SD $0.5500 $0.3700 $0.5000 $0.3500 $0.3500 $0.0300 $0.3900 $0.3700 $0.4000
65880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF3,520SD $1.55 $1.05 $1.00 $1.00 $1.00 $0.0300 $1.10 $1.07 $1.15
66880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF3,520SD $1.00 $2.05 $2.00 $2.00 $2.00 $5.50 $2.20 $2.13 $2.30
67880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)3,080SD $0.4500 $0.3000 $2.00 $0.2500 $0.2500 $0.0500 $0.2800 $0.2700 $0.2900
68880(C) 8848 WING BARRICADES880SD $1.75 $2.10 $1.00 $2.00 $2.00 $1.75 $2.20 $2.13 $2.30
69880(D) 8854 VERTICAL PANELS7,920SD $0.1500 $0.3700 $0.4500 $0.3500 $0.3500 $0.0200 $0.3900 $0.3700 $0.4000
70880(E) 8860 WARNING LIGHTS(TYPE A)8,360SD $0.2000 $0.3700 $1.25 $0.3500 $0.3500 $0.5500 $0.3900 $0.3700 $0.4000
71880(F) 8878 DRUMS6,160SD $0.2500 $0.3700 $0.1500 $0.3500 $0.3500 $0.0200 $0.3900 $0.3700 $0.4000
72880(G) 8890 CHANNELIZER CONES5,280SD $0.2500 $0.3700 $0.5000 $0.3500 $0.3500 $0.0200 $0.3900 $0.3700 $0.4000
73880(I) 8902 FLAGGER30SD $130.00 $150.00 $235.00 $300.00 $50.00 $200.00 $110.00 $306.07 $165.00
74882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN440SD $20.00 $16.00 $15.00 $15.00 $15.00 $18.00 $16.50 $15.98 $17.30
75850(A) 8110 SHEET ALUMINUM SIGNS12.5SF $24.00 $17.00 $30.00 $15.00 $15.00 $50.00 $16.50 $15.98 $17.30
76851(C) 8327 2 1/4" SQUARE TUBE POST28LF $10.00 $14.00 $12.00 $12.00 $12.00 $9.00 $13.20 $12.78 $13.80
77856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)5,667LF $0.6000 $1.05 $1.00 $1.00 $1.00 $1.20 $1.10 $1.07 $1.15
78642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $30,000.00 $15,000.00 $13,000.00 $9,308.00 $16,800.00 $13,200.00 $14,520.00 $9,159.00 $15,405.00
79220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $4,500.00 $3,500.00 $5,500.00 $1,250.00 $5,000.00 $30,000.00 $3,025.00 $752.56 $5,499.00
80641 1399 MOBILIZATION1LSUM $115,000.00 $110,000.00 $145,000.00 $145,000.00 $265,000.00 $202,000.00 $151,315.86 $120,000.00 $341,706.35