Bid tab 160090

Let Feb 18, 2016 · Division 3 · Hughes Sign up free

‹ Feb 2016 results

GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (EW-126): FROM 3.0 MILES WEST OF US-75, EXTEND EAST NEAR HOLDENVILLE . PROJECT LENGTH = 2.879 MILES

Let date
Thursday, February 18, 2016
Contract
160090
J/P numbers
28575(04)
District
Division 3
County
Hughes
Highway
Limits
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (EW-126): FROM 3.0 MILES WEST OF US-75, EXTEND EAST NEAR HOLDENVILLE . PROJECT LENGTH = 2.879 MILES
Project number
STP-232C(041)CI

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$3,593,180
1 GLOVER & ASSOCIATES, INC. Low bidder $3,220,801 -10.4%
2 OBC, INC. $3,968,828 +10.5% +23.2%
3 HASKELL LEMON CONSTRUCTION CO. $3,999,955 +11.3% +24.2%

Bid tab: unit prices 70 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 GLOVER & ASSOCI…#2 OBC, INC.#3 HASKELL LEMON C…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $28,000.00 $100,000.00 $31,417.50 $29,500.00
2202(A) 0183 UNCLASSIFIED EXCAVATION17,223CY $7.50 $8.75 $9.38 $8.81
3202(D) 0184 UNCLASSIFIED BORROW2,175CY $9.00 $9.00 $9.59 $9.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $14,250.00 $40,000.00 $42,067.50 $39,500.00
5221(C) 2801 TEMPORARY SILT FENCE10,460LF $1.85 $0.3000 $1.21 $1.46
6221(F) 0100 TEMPORARY SILT DIKE1,112LF $8.00 $1.98 $6.90 $9.76
7230(A) 2806 SOLID SLAB SODDING62,552SY $1.50 $1.35 $1.29 $1.57
8233(A) 2817 VEGETATIVE MULCHING13AC $400.00 $428.84 $381.27 $107.91
9303(A) 2100 AGGREGATE BASE TYPE A5,369CY $55.00 $58.00 $65.79 $61.77
10307(A) 4200 FLY ASH1,919TON $70.00 $63.80 $93.69 $87.97
11307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE51,192SY $2.85 $2.00 $2.13 $2.00
12402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E3,102TON $22.00 $30.00 $29.75 $27.93
13407(B) 0250 TACK COAT3,210GAL $3.15 $2.00 $1.44 $3.50
14408 5774 PRIME COAT30,300GAL $4.30 $1.00 $2.94 $6.63
15411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)7,374TON $85.00 $63.25 $77.62 $73.14
16411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)4,896TON $93.00 $65.00 $79.65 $83.78
17501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED27CY $32.00 $32.03 $21.30 $13.28
18509(A) 0319 CLASS AA CONCRETE154CY $450.00 $690.00 $426.00 $440.58
19511(A) 0332 REINFORCING STEEL13,102LB $1.00 $1.20 $1.04 $1.10
20601(A) 0297 TYPE I PLAIN RIPRAP2,090TON $42.00 $43.70 $41.22 $60.59
21610(B) 0604 6" CONCRETE DRIVEWAY107SY $65.00 $87.83 $69.23 $100.00
22613(A) 0492 24" R.C.PIPE CLASS III104LF $72.00 $91.41 $83.93 $85.90
23613(A) 0496 48" R.C.PIPE CLASS III33LF $185.00 $274.51 $219.98 $225.14
24613(A) 4497 36" X 22" R.C.PIPE ARCH CLASS A-III118LF $125.00 $179.46 $143.02 $146.38
25613(B) 0689 18" CORR. GALV. STEEL PIPE1,200LF $35.00 $26.00 $27.02 $27.65
26613(L) 5738 48" PREFAB. CULVERT END SECTION, ROUND2EA $2,150.00 $3,421.09 $2,556.00 $2,616.00
27613(M) 7186 TYPE A4 CULVERT END TREATMENT50EA $993.76 $504.72 $1,278.00 $981.00
28613(M) 7192 TYPE BB4 CULVERT END TREATMENT4EA $1,850.00 $1,130.05 $2,130.00 $2,398.00
29619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $5,000.00 $30,000.00 $7,295.25 $6,850.00
30619(B) 4728 REMOVAL OF ASPHALT PAVEMENT32,822SY $4.00 $1.25 $2.71 $3.70
31619(B) 4766 REMOVAL OF CONCRETE DRIVEWAY163SY $9.15 $80.65 $3.88 $10.00
32619(B) 4780 REMOVAL OF GUARDRAIL240LF $4.00 $18.00 $10.65 $10.00
33619(C) 0924 SAWING PAVEMENT153LF $3.50 $8.57 $8.30 $15.89
34623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE100LF $17.75 $21.56 $15.71 $16.08
35623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,800.00 $2,000.00 $1,144.88 $1,171.75
36623(G) 8571 GUARDRAIL END TREATMENT (GET)4EA $2,315.00 $2,814.99 $2,235.44 $2,287.91
37624(C) 4458 FENCE-STYLE SWF (4 BARBED WIRE)259LF $6.00 $17.97 $4.26 $4.36
38624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,840LF $6.00 $8.80 $4.21 $4.31
39629(E) 5048 REMOVE AND RESET MAILBOX9EA $185.00 $119.79 $106.50 $100.00
40501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON180CY $22.00 $25.00 $50.00 $19.86
41501(F) 6352 GRANULAR BACKFILL66CY $60.00 $67.03 $279.97 $123.87
42503(A) 1311 PRESTRESSED CONCRETE BEAMS (TYPE II)268LF $215.00 $251.20 $230.00 $226.52
43503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)224LF $235.00 $235.07 $230.00 $239.42
44504(A) 1304 APPROACH SLAB115SY $210.00 $123.69 $220.00 $287.32
45504(B) 1305 SAW-CUT GROOVING496SY $5.00 $6.95 $6.18 $6.38
46504(C) 6250 SEALED EXPANSION JOINT29.17LF $360.00 $251.06 $280.00 $292.90
47504(D) 6239 CONCRETE RAIL (TR3)388.8LF $83.00 $90.00 $111.06 $106.74
48506(A) 1322 STRUCTURAL STEEL1,070LB $3.85 $14.11 $3.58 $5.92
49507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY6EA $1,000.00 $993.02 $953.56 $1,356.30
50507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY12EA $2,250.00 $881.92 $2,500.00 $1,323.70
51509(A) 1326 CLASS AA CONCRETE130.3CY $600.00 $990.00 $1,000.00 $707.76
52509(B) 1328 CLASS A CONCRETE114.4CY $620.00 $720.00 $1,000.00 $873.34
53511(A) 1332 REINFORCING STEEL47,040LB $1.05 $1.05 $1.50 $1.10
54514(A) 6010 PILES, FURNISHED (HP 10X42)202LF $42.50 $29.09 $35.00 $37.40
55514(A) 6011 PILES, FURNISHED (HP 12X53)476LF $42.00 $38.26 $38.00 $41.97
56514(B) 6292 PILES, DRIVEN (HP 10X42)202LF $18.00 $52.21 $34.47 $19.28
57514(B) 6294 PILES, DRIVEN (HP 12X53)476LF $16.50 $24.24 $34.47 $23.05
58514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00
59516(A) 6094 DRILLED SHAFTS 48" DIAMETER136LF $815.00 $343.12 $1,200.00 $710.11
60601(B) 1353 TYPE I-A PLAIN RIPRAP1,670TON $42.00 $49.00 $41.22 $56.17
61601(C) 1355 TYPE I-A FILTER BLANKET370TON $35.00 $40.00 $32.63 $44.02
62613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND52LF $30.00 $7.00 $84.52 $64.10
63613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.78LF $27.00 $7.00 $28.91 $17.16
64619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $35,000.00 $40,000.00 $183,453.70 $88,421.68
65805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS7EA $150.00 $179.68 $159.75 $163.50
66855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)60,828LF $0.2500 $0.4100 $0.3600 $0.4400
67880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $24,000.00 $14,000.00 $11,715.00 $20,710.00
68642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $12,000.00 $22,000.00 $70,183.50 $171,609.72
69220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,600.00 $1,000.00 $677.69 $7,500.00
70641 1552 MOBILIZATION1LSUM $175,000.00 $125,000.00 $210,890.00 $215,126.22