| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$14,000.00 |
$15,000.00 |
$10,754.04 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 41,001 | CY |
$8.00 |
$8.00 |
$9.05 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 500 | CY |
$15.00 |
$9.00 |
$1.00 |
| 4 | 202(D) 4781 |
UNCLASSIFIED BORROW (TOPSOIL) | 3,790 | CY |
$17.00 |
$25.00 |
$11.76 |
| 5 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$40,000.00 |
$20,000.00 |
$31,304.79 |
| 6 | 221(C) 2801 |
TEMPORARY SILT FENCE | 9,407 | LF |
$2.00 |
$2.21 |
$2.55 |
| 7 | 221(D) 2803 |
TEMPORARY SEDIMENT FILTER | 42 | EA |
$135.00 |
$276.10 |
$214.94 |
| 8 | 221(F) 0100 |
TEMPORARY SILT DIKE | 140 | LF |
$12.00 |
$11.04 |
$6.98 |
| 9 | 230(A) 2806 |
SOLID SLAB SODDING | 63,832 | SY |
$1.75 |
$1.44 |
$1.41 |
| 10 | 232(B) 2814 |
SEEDING METHOD B | 5.1 | AC |
$850.00 |
$1,656.63 |
$1,132.00 |
| 11 | 233(A) 2817 |
VEGETATIVE MULCHING | 5.1 | AC |
$700.00 |
$1,104.42 |
$452.80 |
| 12 | 241 2832 |
MOWING | 20.5 | AC |
$80.00 |
$110.44 |
$113.20 |
| 13 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 7,386 | CY |
$40.00 |
$50.00 |
$26.02 |
| 14 | 310(B) 0149 |
SUBGRADE, METHOD B | 38,769 | SY |
$3.00 |
$3.50 |
$1.61 |
| 15 | 325 5271 |
SEPARATOR FABRIC | 38,769 | SY |
$1.25 |
$1.40 |
$1.10 |
| 16 | 326(B) 0100 |
GEOGRID REINFORCEMENT | 38,769 | SY |
$3.00 |
$1.50 |
$3.03 |
| 17 | 407(B) 0250 |
TACK COAT | 5,509 | GAL |
$3.00 |
$1.10 |
$2.83 |
| 18 | 411(B) 5935 |
SUPERPAVE, TYPE S3(PG 76-28 OK) | 6,080 | TON |
$73.00 |
$74.00 |
$84.90 |
| 19 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 7,427 | TON |
$65.00 |
$63.00 |
$73.12 |
| 20 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 4,114 | TON |
$79.00 |
$85.00 |
$95.77 |
| 21 | 412 5267 |
COLD MILLING PAVEMENT | 19,027 | SY |
$3.00 |
$1.10 |
$3.11 |
| 22 | 414(A) 0210 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 1,122 | SY |
$14.00 |
$20.00 |
$20.85 |
| 23 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 1,817 | SY |
$29.00 |
$30.00 |
$25.95 |
| 24 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 735 | CY |
$95.00 |
$120.00 |
$118.12 |
| 25 | 509(B) 0321 |
CLASS A CONCRETE | 110 | CY |
$350.00 |
$510.00 |
$676.73 |
| 26 | 509(C) 0322 |
CLASS A CONCRETE, SMALL STRUCTURES | 7 | CY |
$400.00 |
$800.00 |
$462.77 |
| 27 | 509(D) 0325 |
CLASS C CONCRETE | 99 | CY |
$300.00 |
$385.00 |
$268.40 |
| 28 | 510(D) 0350 |
(SP)GRAFFITI TREATMENT | 4,700 | SF |
$1.90 |
$1.80 |
$1.81 |
| 29 | 510(D) 6341 |
MSE RETAINING WALL | 643 | SY |
$700.00 |
$535.00 |
$496.52 |
| 30 | 514(J) 6390 |
TEMPORARY SHEET PILING | 1 | LSUM |
$50,000.00 |
$100,000.00 |
$14,669.75 |
| 31 | 609(B) 0394 |
2'-8" COMB. CURB & GUTTER (6" MNTBLE-NOTCHED) | 6,191 | LF |
$18.00 |
$26.00 |
$24.65 |
| 32 | 609(B) 0396 |
2'-8" COMB. CURB & GUTTER (8" BARRIER-NOTCHED) | 16,506 | LF |
$18.00 |
$26.00 |
$21.63 |
| 33 | 610(A) 0602 |
4" CONCRETE SIDEWALK | 301 | SY |
$44.00 |
$46.00 |
$31.33 |
| 34 | 610(B) 5016 |
8" CONCRETE DRIVEWAY | 331 | SY |
$60.00 |
$70.00 |
$56.39 |
| 35 | 611(A) 2657 |
MANHOLE (4' DIAMETER) | 12 | EA |
$750.00 |
$3,000.00 |
$1,268.81 |
| 36 | 611(B) 2680 |
ADD'L.DEPTH IN MANHOLE (4' DIAMETER) | 3 | VF |
$125.00 |
$325.00 |
$92.01 |
| 37 | 611(G) 5112 |
INLET CI DES. 2 (STD) | 1 | EA |
$2,000.00 |
$3,300.00 |
$2,292.09 |
| 38 | 611(G) 5113 |
INLET CI DES. 2 (B) | 10 | EA |
$2,500.00 |
$4,200.00 |
$3,904.67 |
| 39 | 611(G) 5115 |
INLET CI DES. 2 (D) | 5 | EA |
$3,000.00 |
$5,300.00 |
$3,713.36 |
| 40 | 611(G) 5117 |
INLET CI DES. 2 (2B) | 12 | EA |
$3,000.00 |
$5,900.00 |
$3,560.90 |
| 41 | 611(G) 5120 |
INLET CI DES. 3 (STD) | 3 | EA |
$3,250.00 |
$6,100.00 |
$4,212.19 |
| 42 | 611(G) 5122 |
INLET CI DES. 3 (D) | 3 | EA |
$3,750.00 |
$7,300.00 |
$5,285.64 |
| 43 | 611(G) 5125 |
INLET CI DES. 3 (2D) | 1 | EA |
$4,000.00 |
$9,300.00 |
$6,667.97 |
| 44 | 611(H) 5325 |
ADD'L DEPTH IN INLET CI DES. 2 | 8 | VF |
$250.00 |
$350.00 |
$474.08 |
| 45 | 611(H) 5330 |
ADD'L DEPTH IN INLET CI DES. 3 | 7 | VF |
$500.00 |
$1,200.00 |
$276.95 |
| 46 | 611(L) 0487 |
JUNCTION BOXES | 225 | CF |
$75.00 |
$34.00 |
$47.56 |
| 47 | 613(A) 0491 |
18" R.C.PIPE CLASS III | 2,026 | LF |
$60.00 |
$58.00 |
$56.74 |
| 48 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 398 | LF |
$65.00 |
$61.00 |
$69.66 |
| 49 | 613(J) 5915 |
EDGE DRAIN CONDUIT-PERFORATED | 1,400 | LF |
$80.00 |
$16.00 |
$6.93 |
| 50 | 613(K) 5916 |
EDGE DRAIN OUTLET LATERAL-NONPERFORATED | 100 | LF |
$170.00 |
$18.00 |
$3.65 |
| 51 | 613(L) 5726 |
18" PREFAB. CULVERT END SECTION, ROUND | 1 | EA |
$2,500.00 |
$700.00 |
$584.53 |
| 52 | 613(Q) 5946 |
OUTLET LATERAL HEADWALL | 4 | EA |
$1,600.00 |
$540.00 |
$409.66 |
| 53 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$45,000.00 |
$25,000.00 |
$19,210.21 |
| 54 | 619(B) 4727 |
REMOVAL OF CONCRETE PAVEMENT | 47,687 | SY |
$2.00 |
$4.00 |
$2.71 |
| 55 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 14,741 | SY |
$2.50 |
$2.20 |
$2.74 |
| 56 | 619(B) 4741 |
REMOVAL OF DRAINAGE INLETS | 22 | EA |
$500.00 |
$195.00 |
$283.00 |
| 57 | 619(B) 4763 |
REMOVAL OF CONCRETE PAVEMENT W/ASPHALT OVERLAY | 8,548 | SY |
$2.00 |
$6.00 |
$4.84 |
| 58 | 619(B) 4915 |
REMOVAL OF CONCRETE MEDIAN BARRIER | 8,721 | LF |
$10.00 |
$5.00 |
$6.92 |
| 59 | 619(B) 5918 |
REMOVAL OF EXISTING PIPE | 1,238 | LF |
$2.00 |
$9.00 |
$9.50 |
| 60 | 619(C) 0924 |
SAWING PAVEMENT | 9,959 | LF |
$3.25 |
$4.50 |
$3.65 |
| 61 | 627(A) 4317 |
CONCRETE LONGITUDINAL BARRIER, DESIGN 1 | 3,497 | LF |
$75.00 |
$85.00 |
$47.75 |
| 62 | 501(G) 6309 |
CLSM BACKFILL | 5 | CY |
$300.00 |
$130.00 |
$422.64 |
| 63 | 504(C) 6250 |
SEALED EXPANSION JOINT | 125.7 | LF |
$250.00 |
$290.00 |
$398.49 |
| 64 | 504(E) 1381 |
CONCRETE PARAPET | 52 | LF |
$100.00 |
$240.00 |
$362.26 |
| 65 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,435 | SY |
$40.00 |
$35.00 |
$42.26 |
| 66 | 509 6152 |
SPECIAL CONCRETE FINISH | 752 | SY |
$13.00 |
$14.00 |
$14.04 |
| 67 | 510(C) 6137 |
SLOPE WALL (4") | 50 | SY |
$80.00 |
$155.00 |
$144.91 |
| 68 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$30,000.00 |
$28,300.09 |
| 69 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 27 | SY |
$320.00 |
$265.00 |
$301.89 |
| 70 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 224.4 | SY |
$550.00 |
$365.00 |
$615.85 |
| 71 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 406 | SY |
$4.00 |
$4.00 |
$4.13 |
| 72 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 100 | LF |
$30.00 |
$33.00 |
$36.22 |
| 73 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 8 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 74 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 30 | SY |
$650.00 |
$510.00 |
$706.42 |
| 75 | 523(A) 6550 |
SEALER CRACK PREPARATION | 513.7 | LF |
$5.00 |
$4.40 |
$4.53 |
| 76 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 77 | 501(G) 6309 |
CLSM BACKFILL | 5 | CY |
$300.00 |
$130.00 |
$422.64 |
| 78 | 504(C) 6250 |
SEALED EXPANSION JOINT | 125.8 | LF |
$250.00 |
$300.00 |
$398.49 |
| 79 | 504(E) 1381 |
CONCRETE PARAPET | 52 | LF |
$100.00 |
$240.00 |
$362.26 |
| 80 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,435 | SY |
$40.00 |
$35.00 |
$42.26 |
| 81 | 509 6152 |
SPECIAL CONCRETE FINISH | 750 | SY |
$13.00 |
$14.00 |
$14.04 |
| 82 | 510(C) 6137 |
SLOPE WALL (4") | 50 | SY |
$80.00 |
$155.00 |
$144.91 |
| 83 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$31,000.00 |
$28,300.09 |
| 84 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 4.8 | SY |
$320.00 |
$265.00 |
$301.89 |
| 85 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 223.2 | SY |
$550.00 |
$375.00 |
$615.85 |
| 86 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 406 | SY |
$4.00 |
$4.00 |
$4.13 |
| 87 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 100 | LF |
$30.00 |
$33.00 |
$36.22 |
| 88 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 8 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 89 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 30 | SY |
$650.00 |
$510.00 |
$706.42 |
| 90 | 523(A) 6550 |
SEALER CRACK PREPARATION | 513.8 | LF |
$5.00 |
$4.40 |
$4.53 |
| 91 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 92 | 501(G) 6309 |
CLSM BACKFILL | 5 | CY |
$300.00 |
$135.00 |
$422.64 |
| 93 | 504(C) 6250 |
SEALED EXPANSION JOINT | 124.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 94 | 504(E) 1381 |
CONCRETE PARAPET | 52 | LF |
$100.00 |
$240.00 |
$362.26 |
| 95 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,550 | SY |
$40.00 |
$35.00 |
$42.26 |
| 96 | 509 6152 |
SPECIAL CONCRETE FINISH | 876 | SY |
$13.00 |
$14.00 |
$14.04 |
| 97 | 510(C) 6137 |
SLOPE WALL (4") | 95 | SY |
$80.00 |
$150.00 |
$144.91 |
| 98 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$31,000.00 |
$28,300.09 |
| 99 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 61.5 | SY |
$320.00 |
$265.00 |
$301.89 |
| 100 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 230.4 | SY |
$550.00 |
$375.00 |
$615.85 |
| 101 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 464 | SY |
$4.00 |
$4.00 |
$4.13 |
| 102 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 100 | LF |
$30.00 |
$33.00 |
$36.22 |
| 103 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 8 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 104 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 35 | SY |
$650.00 |
$510.00 |
$706.42 |
| 105 | 523(A) 6550 |
SEALER CRACK PREPARATION | 512.1 | LF |
$5.00 |
$4.40 |
$4.53 |
| 106 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 107 | 501(G) 6309 |
CLSM BACKFILL | 5 | CY |
$300.00 |
$265.00 |
$422.64 |
| 108 | 504(C) 6250 |
SEALED EXPANSION JOINT | 124.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 109 | 504(E) 1381 |
CONCRETE PARAPET | 64 | LF |
$100.00 |
$240.00 |
$362.26 |
| 110 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,550 | SY |
$40.00 |
$35.00 |
$42.26 |
| 111 | 509 6152 |
SPECIAL CONCRETE FINISH | 879 | SY |
$13.00 |
$14.00 |
$14.04 |
| 112 | 510(C) 6137 |
SLOPE WALL (4") | 95 | SY |
$80.00 |
$150.00 |
$144.91 |
| 113 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$31,000.00 |
$28,300.09 |
| 114 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 28.4 | SY |
$320.00 |
$265.00 |
$301.89 |
| 115 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 223.2 | SY |
$550.00 |
$375.00 |
$615.85 |
| 116 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 464 | SY |
$4.00 |
$4.00 |
$4.13 |
| 117 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 100 | LF |
$30.00 |
$33.00 |
$36.22 |
| 118 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 8 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 119 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 35 | SY |
$650.00 |
$510.00 |
$706.42 |
| 120 | 523(A) 6550 |
SEALER CRACK PREPARATION | 512 | LF |
$5.00 |
$4.40 |
$4.53 |
| 121 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 122 | 501(G) 6309 |
CLSM BACKFILL | 10 | CY |
$300.00 |
$135.00 |
$422.64 |
| 123 | 504(C) 6250 |
SEALED EXPANSION JOINT | 126.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 124 | 504(E) 1381 |
CONCRETE PARAPET | 40 | LF |
$100.00 |
$240.00 |
$362.26 |
| 125 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 972 | SY |
$40.00 |
$35.00 |
$42.26 |
| 126 | 509 6152 |
SPECIAL CONCRETE FINISH | 485 | SY |
$13.00 |
$14.00 |
$14.04 |
| 127 | 510(C) 6137 |
SLOPE WALL (4") | 10 | SY |
$80.00 |
$200.00 |
$144.91 |
| 128 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$25,000.00 |
$28,300.09 |
| 129 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 27 | SY |
$320.00 |
$265.00 |
$301.89 |
| 130 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 168.2 | SY |
$550.00 |
$380.00 |
$615.85 |
| 131 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 485 | SY |
$4.00 |
$4.00 |
$4.13 |
| 132 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$30.00 |
$33.00 |
$36.22 |
| 133 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 4 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 134 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 62 | SY |
$650.00 |
$510.00 |
$706.42 |
| 135 | 523(A) 6550 |
SEALER CRACK PREPARATION | 504 | LF |
$5.00 |
$4.40 |
$4.53 |
| 136 | 523(B) 6560 |
SEALER RESIN | 6 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 137 | 501(G) 6309 |
CLSM BACKFILL | 10 | CY |
$300.00 |
$135.00 |
$422.64 |
| 138 | 504(C) 6250 |
SEALED EXPANSION JOINT | 126.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 139 | 504(E) 1381 |
CONCRETE PARAPET | 40 | LF |
$100.00 |
$240.00 |
$362.26 |
| 140 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 972 | SY |
$40.00 |
$35.00 |
$42.26 |
| 141 | 509 6152 |
SPECIAL CONCRETE FINISH | 485 | SY |
$13.00 |
$14.00 |
$14.04 |
| 142 | 510(C) 6137 |
SLOPE WALL (4") | 10 | SY |
$80.00 |
$200.00 |
$144.91 |
| 143 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$25,000.00 |
$28,300.09 |
| 144 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 27 | SY |
$320.00 |
$265.00 |
$301.89 |
| 145 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 168.2 | SY |
$550.00 |
$380.00 |
$615.85 |
| 146 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 485 | SY |
$4.00 |
$4.00 |
$4.13 |
| 147 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$30.00 |
$33.00 |
$36.22 |
| 148 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 4 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 149 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 60.5 | SY |
$650.00 |
$510.00 |
$706.42 |
| 150 | 523(A) 6550 |
SEALER CRACK PREPARATION | 504 | LF |
$5.00 |
$4.40 |
$4.53 |
| 151 | 523(B) 6560 |
SEALER RESIN | 6 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 152 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 75 | CY |
$10.00 |
$23.00 |
$42.26 |
| 153 | 501(G) 6309 |
CLSM BACKFILL | 80 | CY |
$300.00 |
$135.00 |
$229.43 |
| 154 | 502 6116 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$15,000.00 |
$5,500.00 |
$12,075.42 |
| 155 | 504(A) 1304 |
APPROACH SLAB | 142.3 | SY |
$220.00 |
$180.00 |
$271.70 |
| 156 | 504(C) 6250 |
SEALED EXPANSION JOINT | 124.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 157 | 504(E) 1381 |
CONCRETE PARAPET | 88 | LF |
$100.00 |
$240.00 |
$362.26 |
| 158 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,005 | SY |
$40.00 |
$35.00 |
$42.26 |
| 159 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 6 | EA |
$800.00 |
$900.00 |
$3,018.86 |
| 160 | 509 6152 |
SPECIAL CONCRETE FINISH | 557 | SY |
$13.00 |
$14.00 |
$14.04 |
| 161 | 509(B) 1328 |
CLASS A CONCRETE | 7.6 | CY |
$600.00 |
$950.00 |
$1,123.01 |
| 162 | 510(C) 6137 |
SLOPE WALL (4") | 50 | SY |
$80.00 |
$160.00 |
$144.91 |
| 163 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 780 | LB |
$1.10 |
$1.35 |
$3.14 |
| 164 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$26,000.00 |
$28,300.09 |
| 165 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 81.7 | SY |
$320.00 |
$265.00 |
$301.89 |
| 166 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 205.2 | SY |
$550.00 |
$365.00 |
$615.85 |
| 167 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 282 | SY |
$4.00 |
$4.00 |
$4.13 |
| 168 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 200 | LF |
$30.00 |
$33.00 |
$36.22 |
| 169 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 16 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 170 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 60 | SY |
$650.00 |
$510.00 |
$706.42 |
| 171 | 523(A) 6550 |
SEALER CRACK PREPARATION | 512.1 | LF |
$5.00 |
$4.40 |
$4.53 |
| 172 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 173 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$25,000.00 |
$28,000.00 |
$12,075.42 |
| 174 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 47.5 | CY |
$10.00 |
$23.00 |
$42.26 |
| 175 | 501(G) 6309 |
CLSM BACKFILL | 57.5 | CY |
$300.00 |
$135.00 |
$229.43 |
| 176 | 504(A) 1304 |
APPROACH SLAB | 142.3 | SY |
$220.00 |
$180.00 |
$271.70 |
| 177 | 504(C) 6250 |
SEALED EXPANSION JOINT | 124.1 | LF |
$250.00 |
$300.00 |
$398.49 |
| 178 | 504(E) 1381 |
CONCRETE PARAPET | 88 | LF |
$100.00 |
$240.00 |
$362.26 |
| 179 | 505(C) 6075 |
MULTIPLE LAYER POLYMER CONCRETE OVERLAY | 1,005 | SY |
$40.00 |
$35.00 |
$42.26 |
| 180 | 509 6152 |
SPECIAL CONCRETE FINISH | 559 | SY |
$13.00 |
$14.00 |
$14.04 |
| 181 | 510(C) 6137 |
SLOPE WALL (4") | 30 | SY |
$80.00 |
$170.00 |
$144.91 |
| 182 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$30,000.00 |
$26,000.00 |
$28,300.09 |
| 183 | 513(B) 6019 |
CLASS B BRIDGE DECK REPAIR | 16.9 | SY |
$320.00 |
$265.00 |
$301.89 |
| 184 | 513(C) 6020 |
CLASS C BRIDGE DECK REPAIR | 205.2 | SY |
$550.00 |
$365.00 |
$615.85 |
| 185 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 282 | SY |
$4.00 |
$4.00 |
$4.13 |
| 186 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 200 | LF |
$30.00 |
$33.00 |
$36.22 |
| 187 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 5 | GAL |
$100.00 |
$88.00 |
$86.95 |
| 188 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 60 | SY |
$650.00 |
$510.00 |
$706.42 |
| 189 | 523(A) 6550 |
SEALER CRACK PREPARATION | 512.1 | LF |
$5.00 |
$4.40 |
$4.53 |
| 190 | 523(B) 6560 |
SEALER RESIN | 7 | GAL |
$200.00 |
$110.00 |
$113.20 |
| 191 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$15,000.00 |
$18,000.00 |
$12,075.42 |
| 192 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$100,000.00 |
$120,000.00 |
$72,452.51 |
| 193 | 802(A) 8306 |
1 1/4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED | 200 | LF |
$12.00 |
$24.30 |
$19.24 |
| 194 | 802(B) 8340 |
2" PVC SCH.40 PLASTIC CONDUIT BORED | 1,045 | LF |
$20.10 |
$15.46 |
$15.85 |
| 195 | 802(B) 8342 |
2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 8,445 | LF |
$4.18 |
$4.42 |
$4.81 |
| 196 | 803(A) 8065 |
PULL BOX(SIZE I) | 75 | EA |
$263.73 |
$358.94 |
$328.28 |
| 197 | 804(A) 2915 |
STRUCTURAL CONCRETE | 32.48 | CY |
$469.25 |
$552.21 |
$553.55 |
| 198 | 804(B) 2916 |
REINFORCING STEEL | 1,870.4 | LB |
$1.02 |
$1.38 |
$1.57 |
| 199 | 806(D) 8989 |
40' MTG.HT.HL.PTP.(G.STL.) | 56 | EA |
$4,500.00 |
$2,255.22 |
$2,433.81 |
| 200 | 807 8092 |
BREAKAWAY BASE (DES. B) | 48 | EA |
$400.00 |
$546.69 |
$526.38 |
| 201 | 809(A) 8090 |
ROADWAY LUMINAIRE | 56 | EA |
$1,150.00 |
$839.36 |
$894.29 |
| 202 | 810(A) 3118 |
SERVICE POLE | 2 | EA |
$3,000.00 |
$5,632.53 |
$5,286.46 |
| 203 | 811 8038 |
1/C NO.4 ELECTRICAL CONDUCTOR | 20,350 | LF |
$2.00 |
$1.93 |
$2.09 |
| 204 | 811 8046 |
1/C NO.12 ELECTRICAL CONDUCTOR | 7,000 | LF |
$0.6000 |
$0.3900 |
$1.13 |
| 205 | 802(B) 8340 |
2" PVC SCH.40 PLASTIC CONDUIT BORED | 140 | LF |
$20.10 |
$17.67 |
$15.85 |
| 206 | 802(B) 8342 |
2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 800 | LF |
$4.18 |
$6.63 |
$5.66 |
| 207 | 802(B) 8344 |
3" PVC SCH.40 PLASTIC CONDUIT BORED | 140 | LF |
$15.00 |
$24.30 |
$19.24 |
| 208 | 802(B) 8346 |
3" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 760 | LF |
$7.50 |
$13.25 |
$9.06 |
| 209 | 802(B) 8352 |
6" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 652 | LF |
$10.00 |
$18.78 |
$24.90 |
| 210 | 802(B) 8354 |
6" PVC SCH. 40 PLASTIC CONDUIT (BORED) | 140 | LF |
$25.00 |
$40.86 |
$44.15 |
| 211 | 804(A) 2915 |
STRUCTURAL CONCRETE | 19.3 | CY |
$469.25 |
$309.24 |
$316.96 |
| 212 | 804(B) 2916 |
REINFORCING STEEL | 3,334 | LB |
$1.02 |
$1.10 |
$1.13 |
| 213 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 471 | SF |
$18.00 |
$13.25 |
$13.58 |
| 214 | 850(B) 8112 |
EXTRUDED ALUMINUM PANEL SIGNS | 887 | SF |
$21.50 |
$18.78 |
$19.24 |
| 215 | 851(A) 3206 |
4"@13 GALV.STEEL WIDE FLANGE BEAM POST | 87 | LF |
$17.00 |
$18.78 |
$19.24 |
| 216 | 851(A) 3208 |
6"@20 GALV.STEEL WIDE FLANGE BEAM POST | 236 | LF |
$32.00 |
$26.51 |
$27.17 |
| 217 | 851(A) 3210 |
8"@31 GALV.STEEL WIDE FLANGE BEAM POST | 54 | LF |
$48.00 |
$33.13 |
$33.96 |
| 218 | 851(B) 3218 |
3"@7.58 GALV.STEEL PIPE POST | 504 | LF |
$18.00 |
$15.46 |
$15.85 |
| 219 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 6,325 | LF |
$1.00 |
$0.5600 |
$0.5800 |
| 220 | 856(A) 8535 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 16,782 | LF |
$1.50 |
$0.6200 |
$0.6300 |
| 221 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 4,776 | LF |
$2.00 |
$0.8800 |
$0.9100 |
| 222 | 856(A) 8548 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 6,479 | LF |
$3.00 |
$1.10 |
$1.13 |
| 223 | 856(A) 8555 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 58 | LF |
$6.00 |
$11.04 |
$11.32 |
| 224 | 856(B) 8525 |
TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | 20 | EA |
$500.00 |
$84.49 |
$86.60 |
| 225 | 871(A) 8325 |
(SP)IMPACT ATTENUATOR | 1 | EA |
$20,000.00 |
$20,542.16 |
$21,055.27 |
| 226 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 1,224 | LF |
$18.50 |
$6.10 |
$38.44 |
| 227 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$12,500.00 |
$5,853.41 |
$5,999.62 |
| 228 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$90,000.00 |
$42,243.95 |
$57,720.30 |
| 229 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,897.96 |
$2,830.01 |
| 230 | 640(A) 1426 |
FIELD OFFICE | 1 | EA |
$10,000.00 |
$17,246.37 |
$2,830.01 |
| 231 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$406,500.00 |
$385,000.00 |
$550,000.00 |