$20.01Avg low bid / SF
$23.96Avg of all bids
$23.51Avg engineer's estimate
30Jobs · 49,213.15 SF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 5 | 3,821.4 | $25.33 | $27.15 |
| 2020 | 8 | 6,264.7 | $30.48 | $27.19 |
| 2019 | 10 | 35,013.25 | $16.78 | $22.27 |
| 2018 | 5 | 3,834.3 | $26.77 | $24.57 |
| 2017 | 2 | 279.5 | $23.97 | $35.29 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 20, 2021 | 210133 | EllisDivision 6 | 35 SF | $63.60 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 18, 2021 | 210077 | GarvinDivision 3 | 1,901 SF | $22.82 | IHC Scott, INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 195 SF | $31.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 210030 | McclainDivision 3 | 778.4 SF | $20.74 | IHC Scott, INC. |
| Jan 21, 2021 | 210035 | Pontotoc | 267 SF | $36.05 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 14 SF | $31.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 260 SF | $30.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 371 SF | $30.00 | OVERLAND CORPORATION |
| Nov 19, 2020 | 200346 | ClevelandDivision 3 | 135.75 SF | $42.00 | Redlands Contracting, LLC |
| Oct 15, 2020 | 200334 | TulsaDivision 8 | 2,355 SF | $43.70 | TRAFFIC & LIGHTING SYSTEMS, LLC |
| Sep 17, 2020 | 200291 | PittsburgDivision 2 | 1,017.7 SF | $24.42 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 17, 2020 | 200286 | Mcintosh, Muskogee, Sequoyah | 1,434 SF | $10.00 | Midstate Traffic Control, Inc. |
| Aug 20, 2020 | 200163 | OkfuskeeDivision 3 | 63 SF | $43.60 | HASKELL LEMON CONSTRUCTION CO. |
| Aug 20, 2020 | 200270 | Nhppi-4400(077)pm | 591.5 SF | $44.60 | SHERWOOD CONSTRUCTION CO., INC. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 443.75 SF | $21.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 203 SF | $20.50 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200022 | OttawaDivision 8 | 21 SF | $25.85 | APAC-CENTRAL, INC. |
| Oct 17, 2019 | 190331 | TulsaDivision 8 | 695.25 SF | $42.08 | SHERWOOD CONSTRUCTION CO., INC. |
| Oct 17, 2019 | 190294 | Kay, Noble, Oklahoma | 525 SF | $16.00 | ACTION SAFETY SUPPLY CO., LLC |
| Oct 17, 2019 | 190320 | Carter, Love, Murray | 29,656.85 SF | $15.00 | ACTION SAFETY SUPPLY CO., LLC |
| Sep 19, 2019 | 190216 | McclainDivision 3 | 969.9 SF | $28.24 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 19, 2019 | 190278 | CusterDivision 5 | 1,759 SF | $24.00 | CASWELL CONSTRUCTION, INC. |
| Jun 20, 2019 | 190182 | OkfuskeeDivision 3 | 444 SF | $25.10 | HASKELL LEMON CONSTRUCTION CO. |
| Apr 18, 2019 | 190161 | RogersDivision 8 | 300 SF | $25.00 | BECCO CONTRACTORS, INC. |
| Mar 14, 2019 | 190133 | RogersDivision 8 | 105 SF | $26.22 | SHERWOOD CONSTRUCTION CO., INC. |
| Feb 14, 2019 | 190100 | Stp-205b(076)pm | 510.25 SF | $25.68 | Frontier Bridge, Inc. |
| Jan 17, 2019 | 190019 | OklahomaDivision 4 | 48 SF | $21.50 | CROSSLAND HEAVY CONTRACTORS INC. |
| Nov 15, 2018 | 180359 | OklahomaDivision 4 | 1,747 SF | $25.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Oct 18, 2018 | 180203 | MarshallDivision 2 | 99 SF | $30.00 | JENSEN CONSTRUCTION COMPANY |
| Jul 19, 2018 | 180251 | Nhppi-4000-(064)pm | 367 SF | $24.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Jul 19, 2018 | 180251 | Nhppi-4000-(064)pm | 1,322.5 SF | $24.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180139 | OklahomaDivision 4 | 67 SF | $150.87 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 18, 2018 | 180055 | McintoshDivision 1 | 231.8 SF | $23.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Feb 16, 2017 | 170077 | GarvinDivision 3 | 127.5 SF | $34.00 | M.J. HUGHES CONSTRUCTION, INC. |
| Jan 19, 2017 | 170011 | CimarronDivision 6 | 152 SF | $15.55 | UNIFIED SERVICES OF TEXAS, INC. |