46Let jobs
$127,867,005Total low bids
—Total estimates
—Low bids vs estimates
Sep 2022 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Sep 23, 2022 | 66D26 | Kendall District 3 |
(1-1)R,BR1 · The reconstruction of IL 71 from 0 | — | $32,993,337 | D. Construction, Inc. | 3 | |
| Sep 23, 2022 | 68884 | Peoria District 4 |
(72-3HB-2)BR · | — | $11,025,102 | Stark Excavating, Inc. | 2 | |
| Sep 23, 2022 | 60X98 | Cook District 1 |
2014-012LS · | — | $8,491,788 | Martam Construction Incorporated | 3 | |
| Sep 23, 2022 | 70943 | Mclean District 5 |
128RS-2&129RS-4 · | — | $7,188,527 | Rowe Construction, a div of UCM, Inc. | 1 | |
| Sep 23, 2022 | 62N05 | Cook, Lake District 1 |
2020-236-L · | — | $7,139,420 | Meade Inc. | 4 | |
| Sep 23, 2022 | 87726 | Kankakee District 3 |
15-00278-00-FP · | — | $6,698,482 | Kankakee Valley Construction Company, Inc. | 3 | |
| Sep 23, 2022 | 61H96 | Dupage District 1 |
19-DCCSS-04-TL · | — | $6,484,160 | Thorne Electric, Inc. | 4 | |
| Sep 23, 2022 | 62N04 | Cook District 1 |
2020-235-L · | — | $6,060,454 | Meade Inc. | 3 | |
| Sep 23, 2022 | 46576 | Various District 1 |
D1 GRVD INT PVMNT MRK 22-12 · Placing various width of thermoplastic, preform plastic, modified urethane and hot spray thermoplastic pavemen | — | $5,800,895 | ROADSAFE TRAFFIC SYSTEMS, INC. | 1 | |
| Sep 23, 2022 | 76L72 | Madison District 8 |
261RS-2 · | — | $5,485,505 | Charles E. Mahoney Co. | 2 | |
| Sep 23, 2022 | 76R79 | Madison, Jersey District 8 |
DIST 8 GUARDRAIL 2024-2 · | — | $3,153,333 | Lovewell Fencing, Inc. | 2 | |
| Sep 23, 2022 | 99686 | Williamson District 9 |
20-00162-00-RS · | — | $2,744,365 | Southern Illinois Asphalt Co., Inc. | 3 | |
| Sep 23, 2022 | 93794 | Hancock District 6 |
14-07118-00-BR · | — | $1,719,493 | County Contractors, Inc. | 2 | |
| Sep 23, 2022 | 46604 | Will District 1 |
D 1 REFLECTOR REPL 23-14 · Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p | — | $1,669,973 | Superior Road Striping, Inc. | 2 | |
| Sep 23, 2022 | 62P22 | Dupage District 1 |
2021-087-TS&N · | — | $1,558,813 | Geneva Construction Company | 3 | |
| Sep 23, 2022 | 62R81 | Cook District 1 |
2022 TRAFFIC 01 · | — | $1,490,238 | Electric Conduit Construction | 3 | |
| Sep 23, 2022 | 61H92 | Lake District 1 |
19-00082-00-RS · | — | $1,477,000 | Peter Baker & Son Co. | 4 | |
| Sep 23, 2022 | 91597 | Douglas District 5 |
07-08119-01-BR · | — | $1,158,188 | Depew and Owen Builders, Inc. | 3 | |
| Sep 23, 2022 | 61H94 | Cook District 1 |
19-00284-00-CH · | — | $1,137,649 | Acura Inc. | 3 | |
| Sep 23, 2022 | 61H31 | Will District 1 |
15-00024-01-BT · | — | $1,097,532 | D. Construction, Inc. | 3 | |
| Sep 23, 2022 | 66M91 | Bureau, Lasalle District 3 |
[(06-6,7)&50-8]I · Centerline milling and resurfacing 2 feet wide, at a depth of 2", pavement marking, and raised reflectors | — | $1,093,285 | Advanced Asphalt Company | 1 | |
| Sep 23, 2022 | 66F92 | Livingston District 3 |
(108BR-4)BR · Removal and replacement of the existing bridge (SN 053-0029) carrying IL 17 over Manville Drainage Ditch | — | $1,025,425 | Riber Construction, Inc. | 3 | |
| Sep 23, 2022 | 76R49 | Randolph District 8 |
DIST 8 PATCHING 2023-2 · | — | $1,023,182 | Keeley & Sons, Inc. | 5 | |
| Sep 23, 2022 | 95926 | Moultrie District 7 |
20-00031-00-SD · | — | $796,985 | Howell Paving, Inc. | 2 | |
| Sep 23, 2022 | 66M68 | Putnam District 3 |
(78-1)RS-2 · HMA milling and resurfacing (designed overlay), pavement marking, and raised reflectors | — | $762,771 | Advanced Asphalt Company | 1 | |
| Sep 23, 2022 | 46598 | Various District 7 |
D7 HT PVMNT MRK RPR 23-08 · | — | $718,175 | ROADSAFE TRAFFIC SYSTEMS, INC. | 3 | |
| Sep 23, 2022 | 61H90 | Cook District 1 |
21-00150-00-RS · | — | $668,229 | A Lamp Concrete Contractors, Inc. | 7 | |
| Sep 23, 2022 | 62T88 | Various District 1 |
2022 CABLE 01 · Repairing high tension cable median barrier systems throughout District 1 on a work order basis | — | $648,821 | Kujo, Inc. | 1 | |
| Sep 23, 2022 | 78834 | White District 9 |
3CR-1 · | — | $567,891 | Samron Midwest Contracting, Inc. | 2 | |
| Sep 23, 2022 | 74B57 | Richland District 7 |
D7 PATCHING 2023-5 · | — | $539,984 | Kinney Contractors, Inc. | 3 | |
| Sep 23, 2022 | 61H81 | Cook District 1 |
19-00135-00-BT · | — | $539,769 | Capitol Cement Co., Inc. | 6 | |
| Sep 23, 2022 | 66M49 | Iroquois District 3 |
D3 INTERMITTENT RS 2022-1 · Intermittent milling 2" and resurfacing, pavement striping, raised reflective pavement marker removal and repl | — | $509,531 | Iroquois Paving Corporation | 1 | |
| Sep 23, 2022 | 46605 | Kane District 1 |
D 1 REFLECTOR REPL 23-15 · Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p | — | $502,490 | Precision Pavement Markings Inc. | 4 | |
| Sep 23, 2022 | 68H17 | Various District 4 |
D4 ITS SYSTEM 2023 · | — | $470,200 | Oberlander Electric Co. | 2 | |
| Sep 23, 2022 | 68H18 | Various District 4 |
D4 ITS SYSTEM 2023-1 · | — | $455,836 | Laser Electric, Inc. | 2 | |
| Sep 23, 2022 | 66M39 | Various District 3 |
(FY 22 TRAFFIC SIGNAL MOD)SFY · | — | $449,954 | H & H Electric Co. | 1 | |
| Sep 23, 2022 | 70G16 | Champaign District 5 |
(10-7)BR · | — | $449,720 | White Construction LLC | 2 | |
| Sep 23, 2022 | 68H08 | Knox District 4 |
D4 PARKING LOT RESURF 2022 · | — | $436,864 | Illinois Civil Contractors, Inc. | 4 | |
| Sep 23, 2022 | 72402 | Sangamon District 6 |
HANLEY PARKING 2022-1 · | — | $419,811 | White Construction LLC | 2 | |
| Sep 23, 2022 | 64S10 | Various District 2 |
D2 ELE (EAST) 2022 · | — | $370,373 | William Charles Construction Co, LLC | 1 | |
| Sep 23, 2022 | 64S11 | Various District 2 |
D2 ELE (WEST) 2022 · | — | $190,450 | Davenport Electric Contract Company | 1 | |
| Sep 23, 2022 | 61H97 | Kane District 1 |
20-00524-01-SP · | — | $187,124 | Geneva Construction Company | 2 | |
| Sep 23, 2022 | 66M52 | Grundy District 3 |
(32-3)HL · Removal and replacement of highway light poles, luminaries and breakaway couplings | — | $184,785 | Electric Conduit Construction | 1 | |
| Sep 23, 2022 | 64R70 | Winnebago District 2 |
(201-3)TR · | — | $172,588 | Clean Cut Tree Service, Inc. | 3 | |
| Sep 23, 2022 | 76P98 | Calhoun District 8 |
266BR-1-I-7 · | — | $60,001 | Electrico, Inc. | 2 | |
| Sep 23, 2022 | 76P97 | Various District 8 |
DIST 8 ELECTRICAL 2023-1 · | — | $48,508 | Electrico, Inc. | 2 |
1–46 of 46
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.