20-00524-01-SP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Geneva Construction Company Low bidder | $187,124 | ||
| 2 | Alliance Contractors, Inc. | $253,434 | +35.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Geneva Construc… | #2 Alliance Contra… |
|---|---|---|---|---|---|---|---|
| 1 | X0301339 | REM EX PARKING BLOCKS | 5 | EACH | $41.00 | $50.00 | |
| 2 | X0323378 | CONC PARKING BLOCKS | 11 | EACH | $85.00 | $250.00 | |
| 3 | X1400326 | R R FL BEACON A COMP | 1 | EACH | $7,777.00 | $86,925.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,611.81 | $1,500.00 | |
| 5 | 20100110 | TREE REMOV 6-15 | 76 | UNIT | $35.00 | $35.00 | |
| 6 | 20101000 | TEMPORARY FENCE | 249 | FOOT | $5.00 | $3.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 125 | CU YD | $122.00 | $5.00 | |
| 8 | 21101505 | TOPSOIL EXC & PLAC | 320 | CU YD | $73.00 | $7.50 | |
| 9 | 21101615 | TOPSOIL F & P 4 | 187 | SQ YD | $10.90 | $7.00 | |
| 10 | 25000210 | SEEDING CL 2A | 0.32 | ACRE | $1,573.00 | $3,851.00 | |
| 11 | 25000400 | NITROGEN FERT NUTR | 29 | POUND | $3.19 | $3.00 | |
| 12 | 25000500 | PHOSPHORUS FERT NUTR | 29 | POUND | $3.19 | $3.00 | |
| 13 | 25000600 | POTASSIUM FERT NUTR | 29 | POUND | $3.19 | $3.00 | |
| 14 | 25100630 | EROSION CONTR BLANKET | 1,540 | SQ YD | $1.35 | $1.20 | |
| 15 | 28000250 | TEMP EROS CONTR SEED | 32 | POUND | $9.80 | $6.00 | |
| 16 | 28000400 | PERIMETER EROS BAR | 671 | FOOT | $2.40 | $2.80 | |
| 17 | 30300112 | AGG SUBGRADE IMPR 12 | 39 | SQ YD | $30.00 | $24.00 | |
| 18 | 35102000 | AGG BASE CSE B 8 | 331 | SQ YD | $14.50 | $16.00 | |
| 19 | 35501316 | HMA BASE CSE 8 | 326 | SQ YD | $58.00 | $62.00 | |
| 20 | 40600275 | BIT MATLS PR CT | 743.5 | POUND | $0.0100 | $0.0100 | |
| 21 | 40600290 | BIT MATLS TACK CT | 208.2 | POUND | $0.0100 | $0.0100 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 33 | SQ YD | $20.00 | $24.00 | |
| 23 | 40602978 | HMA BC IL-9.5 N50 | 37.1 | TON | $170.00 | $166.00 | |
| 24 | 40602985 | HMA BC IL-9.5 N70 | 13.2 | TON | $300.00 | $295.00 | |
| 25 | 40604060 | HMA SC IL-9.5 D N50 | 73.6 | TON | $160.00 | $158.00 | |
| 26 | 40604062 | HMA SC IL-9.5 D N70 | 11.3 | TON | $350.00 | $332.00 | |
| 27 | 42001300 | PROTECTIVE COAT | 73 | SQ YD | $0.0100 | $0.0100 | |
| 28 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $37.00 | $40.00 | |
| 29 | 44000100 | PAVEMENT REM | 472 | SQ YD | $18.00 | $20.00 | |
| 30 | 44000160 | HMA SURF REM 2 3/4 | 138 | SQ YD | $32.00 | $23.00 | |
| 31 | 44000200 | DRIVE PAVEMENT REM | 18 | SQ YD | $52.00 | $20.00 | |
| 32 | 44000500 | COMB CURB GUTTER REM | 20 | FOOT | $25.00 | $25.00 | |
| 33 | 44201690 | CL D PATCH T1 4 | 21 | SQ YD | $55.00 | $125.00 | |
| 34 | 48101500 | AGGREGATE SHLDS B 6 | 81 | SQ YD | $47.00 | $46.00 | |
| 35 | 48203029 | HMA SHOULDERS 8 | 39 | SQ YD | $101.00 | $95.00 | |
| 36 | 60603800 | COMB CC&G TB6.12 | 164.5 | FOOT | $53.00 | $85.75 | |
| 37 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $3,500.00 | $500.00 | |
| 38 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $15,000.00 | |
| 39 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $3,250.00 | $25,525.00 | |
| 40 | 70106800 | CHANGEABLE MESSAGE SN | 4 | CAL MO | $1,000.00 | $1,000.00 | |
| 41 | 70307160 | TEMP PVT MK L12 T4 TAPE | 180 | FOOT | $5.00 | $5.00 | |
| 42 | 72000100 | SIGN PANEL T1 | 53 | SQ FT | $35.00 | $35.00 | |
| 43 | 72400500 | RELOC SIN PAN ASSY TA | 2 | EACH | $300.00 | $300.00 | |
| 44 | 72800100 | TELES STL SIN SUPPORT | 193 | FOOT | $15.00 | $15.00 | |
| 45 | 73400200 | DRILL SHAFT CONC FDN | 1 | CU YD | $600.00 | $1.00 | |
| 46 | 78009000 | MOD URETH PM LTR-SYM | 36 | SQ FT | $8.00 | $8.00 | |
| 47 | 78009004 | MOD URETH PM LINE 4 | 839 | FOOT | $4.00 | $4.00 | |
| 48 | 78009008 | MOD URETH PM LINE 8 | 37 | FOOT | $4.96 | $4.96 | |
| 49 | 78009012 | MOD URETH PM LINE 12 | 130 | FOOT | $8.32 | $8.32 | |
| 50 | 78009024 | MOD URETH PM LINE 24 | 32 | FOOT | $8.00 | $8.00 |