Filtered by: County: Will Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 18, 2019 | 46485 | WillDistrict 1 | Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings, and placing new raised pavement marker castings. | — | Executed | Superior Road Striping, Inc. $371,419 · | ||
| Jan 18, 2019 | 60M99 | WillDistrict 1 | Bridge deck repairs and thin polymer overlay of the existing bridge deck of SN 099-0263 carrying US 30 (Cass Street) over Spring Creek in the City of Joliet. | — | Executed | MYS, Incorporated $88,200 · | ||
| Jan 18, 2019 | 61F12 | WillDistrict 1 | Rehabilitate the bridge carrying IL 7 Frontage Road over the Des Plaines River in the City of Lockport. | — | Rejected | ICC Group Inc. $2,191,000 · | ||
| Jan 18, 2019 | 62G14 | WillDistrict 1 | Insatallation of a fiber optic line to provide local centralized control and operation of 6 moveable bridges over the Des Plaines River in Joliet. | — | Executed | John Burns Construction Company $1,900,000 · | ||
| Jan 18, 2019 | 62G66 | DuPageWillDistrict 1 | Installation of seven truss mounted LED dynamic message signs, CCTBV, fiber optic networks and roadside bluetooth detectors at various locations. | — | Executed | John Burns Construction Company $5,592,292 · | ||
| Jan 18, 2019 | 62G99 | WillDistrict 1 | Bridge deck overlay, joint repairs, structural repair of concrete, and drainage repairs on 099-0264 carrying US 30 over WCL RR in Joliet. | — | Executed | D. Construction, Inc. $1,673,197 · | ||
| Jan 18, 2019 | 78667 | WilliamsonDistrict 9 | Bridge repairs and approach work on SN 100-0062 carrying Cambria Rd. over Big Muddy River, 1 mile south of Hurst. | — | Executed | E. T. Simonds Construction Company $299,154 · | ||
| Jan 18, 2019 | 99610 | WilliamsonDistrict 9 | Pavement widening, resurfacing, and water main improvements on East Grand Avenue, from Hofer Road to Hurricane Road in Crainville. | — | Executed | Samron Midwest Contracting, Inc. $872,797 · | ||
| Mar 8, 2019 | 60N00 | WillDistrict 1 | Bridge deck overlay and joint repairs on the bridge carrying US 52 over Forked Creek. | — | Executed | MYS, Incorporated $301,046 · | ||
| Mar 8, 2019 | 61F40 | WillDistrict 1 | Construct an extension of Kings Road from Rodeo Drive to Hassert Boulevard in Bollingbrook. | — | Executed | K-Five Construction Corporation & Herlihy Mid-Continent Company $7,485,866 · | ||
| Mar 8, 2019 | 61F44 | WillDistrict 1 | Replace the bridge carrying TR 68 over Lily Creek, 0.1 mil north of Caton Farm Road in Plainfield Township. | — | Executed | D. Construction, Inc. $945,717 · | ||
| Mar 8, 2019 | 61F61 | WillDistrict 1 | Resurfacing Burville Road from stte Street to IL 394 in the Village of Crete. | — | Executed | Iroquois Paving Corporation $395,403 · | ||
| Mar 8, 2019 | 62F49 | CookWillDistrict 1 | 6.45 miles of 3P resurfacing and ADA ramps on IL 43 from north of US 30 to just north of US 6. | — | Executed | D. Construction, Inc. $5,880,439 · | ||
| Mar 8, 2019 | 62G98 | WillDistrict 1 | Removal and replacement of bridge decks of SN 099-0286, 099-0005 and 099-0304 c carrying I-55 over BNSF Railroad and Grant Creek in Wilminton and Channahon Townships. | — | Executed | D. Construction, Inc. $7,870,946 · | ||
| Mar 8, 2019 | 62H35 | WillDistrict 1 | Repairs on SN 099-0056 carrying I-80 over the Des Plaines River in Joliet. | — | Executed | Lakes & Rivers Contracting, Inc. $847,500 · | ||
| Mar 8, 2019 | 62H55 | WillDistrict 1 | 9.62 miles of Shoulder rumble strip installation on I-80 at various locations between the Will County line and US 30. | — | Executed | D. Construction, Inc. $277,857 · | ||
| Mar 8, 2019 | 62H68 | WillDistrict 1 | Bridge structural steel repair and bearing replacement of the bridges carrying I-80 over Des Plaines River in Joliet | — | Executed | ICC Group Inc. $4,978,000 · | ||
| Mar 8, 2019 | 78637 | WilliamsonDistrict 9 | Installation of sidewalks, ADA improvements and installation of pedestrian crossing signals on IL 13 from Johnson Street to Railroad Street in Marion. | — | Executed | Samron Midwest Contracting, Inc. $158,480 · | ||
| Mar 8, 2019 | 78662 | WilliamsonDistrict 9 | Joint reconstruction, approach slab and deck slab repairs, waterproofing membrane system, HMA overlays and substructure repairs on SN 100-0032 and SN 100-0033 carrying IL 148 over the Big Muddy River and Pond Creek | — | Executed | Samron Midwest Contracting, Inc. $497,797 · | ||
| Apr 26, 2019 | 60R52 | WillDistrict 1 | Approximately 3 miles of roadway reconstruction, resurfacing, replacement of bridge structures carrying US 6 over Marley Creek, drainage improvement, pavement markings, and aesthetic landscaping from Cedar Rd to Will-Cook Rd in Homer Glen. | — | Executed | D. Construction, Inc. $14,392,722 · | ||
| Apr 26, 2019 | 60R74 | WillDistrict 1 | Bridge deck overlay and bridge joint repair of the bridge carrying IL 50 over rock creek in unincorporated Wilton Township. | — | Executed | Iroquois Paving Corporation $658,368 · | ||
| Apr 26, 2019 | 61D48 | WillDistrict 1 | Construction of a multi-use path and sidewalk replacement algon the west parkway of Farrell Road from Division Street to south of 7th Street in the City of Lockport. | — | Executed | P. T. Ferro Construction Co. $334,680 · | ||
| Apr 26, 2019 | 61F64 | WillDistrict 1 | Reconstruct the intersection of Rodeo Drive at Kings Road in Bolingbrook. | — | Executed | K-Five Construction Corporation $2,914,616 · | ||
| Apr 26, 2019 | 61F67 | WillDistrict 1 | Resurfacing University Parkway from Steger-Monee Road to Western Avenue in the Village of University Park. | — | Executed | D. Construction, Inc. $583,358 · | ||
| Apr 26, 2019 | 61F68 | WillDistrict 1 | Intersection improvement on US 52 at Gougar Road in the Village of Manhattan. | — | Executed | P. T. Ferro Construction Co. $874,335 · | ||
| Apr 26, 2019 | 62G97 | WillDistrict 1 | Jack column retrofitting, repairing bascule girders, modification of center and tail lock, repairing steel grid deck and railings, and painting of Brandon Rd over the Des Plaines River in Joliet. | — | Executed | D. Construction, Inc. $3,391,575 · | ||
| Apr 26, 2019 | 62H13 | KendallWillDistrict 1 | Clean and paint SN 099-0083 carrying US 52 over Hickory Creek in Joliet, and SN 047-0006 carrying IL 31 over BNSF RR in Oswego. | — | Executed | Eagle Painting & Maintenance Company, Inc. $279,700 · | ||
| Apr 26, 2019 | 78694 | WilliamsonDistrict 9 | Single pass microsurfacing, bump removal and fiber-modified asphalt crack sealing on IL 13 eastbound lane from west of Main Street to East Crab Orchard Road. | — | Executed | Beniach Construction Company, Inc. and Pavement Maintenance Systems, LLC $456,657 · | ||
| Apr 26, 2019 | 99613 | WilliamsonDistrict 9 | Resurfacing CH 18 from Stonefort Road to East Boundary Road north of Creal Springs. | — | Executed | Southern Illinois Asphalt Co., Inc. $605,762 · | ||
| Jun 14, 2019 | 46507 | LakeWillDistrict 1 | Apply water borne, lead free, white and yellow paint pavement marking lines, 4, 6, and 8 inches in width in Lake and Will counties. | — | Executed | STF, LLC d/b/a Traffic Control Company $593,000 · | ||
| Jun 14, 2019 | 61F76 | WillDistrict 1 | Construction of a multi-use path adjacent to University Parkway from Steger- Monee Road to Western Avenue in the Village of University Park. | — | Executed | Iroquois Paving Corporation $525,868 · | ||
| Jun 14, 2019 | 62H11 | CookWillDistrict 1 | Guardrail end section replacement at various locations in Cook and Will Counties. | — | Executed | Midwest Fence Corporation $559,277 · | ||
| Jun 14, 2019 | 62J08 | WillDistrict 1 | Intermittent pavement resurfacing project located on various state maintained arterial routes. | — | Executed | P. T. Ferro Construction Co. $425,756 · | ||
| Jun 14, 2019 | 62J12 | CookWillDistrict 1 | Intermittent resurfacing on various state maintained expressway routes in Cook and Will counties. | — | Executed | D. Construction, Inc. $826,171 · | ||
| Jun 14, 2019 | 66K23 | KankakeeWillDistrict 3 | Radii widening at the intersection of IL 1 and E 1200N Road at the Kankakee/Will County Line. Includes new foreslopes and ditches and 0.75 mile centerline milling and resurfacing to add rumble strips. | — | Executed | Iroquois Paving Corporation $148,374 · | ||
| Jun 14, 2019 | 99620 | WilliamsonDistrict 9 | Replace the bridge carrying Grassy Road over Little Wolf Creek, located 0.2 miles West of IL 148. | — | Executed | E. T. Simonds Construction Company $389,831 · | ||
| Jun 14, 2019 | 99624 | WilliamsonDistrict 9 | Resurfacing Grassy Road from Spillway Road to West of Caney Branch Lane and resurfacing Spillway Road from Hayton Shcool Road to Grassy Road. | — | Executed | E. T. Simonds Construction Company $512,791 · | ||
| Jul 12, 2019 | 62G13 | WillDistrict 1 | 2.73 miles of shoulder widening and milled rumble strips with ditch regrading on IL 53 between Murphey Drive to IL 7 in Romeoville. | — | Executed | D. Construction, Inc. $1,458,014 · | ||
| Jul 12, 2019 | 62H93 | WillDistrict 1 | 1.3 miles of resurfacing along IL 50 from Cicero Avenue to Manhattan-Monee Road in Monee Township | — | Executed | Iroquois Paving Corporation $1,177,820 · | ||
| Jul 12, 2019 | 78608 | FranklinWilliamsonDistrict 9 | 2.6 miles of resurfacing on IL 148 from Maple Street in Zeigler to 0.8 miles south of Franklin/Williamson County line. | — | Executed | Southern Illinois Asphalt Co., Inc. $881,036 · | ||
| Jul 12, 2019 | 78639 | WilliamsonDistrict 9 | 2.1 miles of resurfacing on Herrin Road from Christmas Tree Road to just east of I-57. | — | Executed | E. T. Simonds Construction Company $835,539 · | ||
| Jul 12, 2019 | 78692 | WilliamsonDistrict 9 | 0.8 miles of milling and resurfacing on IL 13 from IL 37 to Fair Street in Marion. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,005,135 · | ||
| Aug 2, 2019 | 61F18 | WillDistrict 1 | Construction of a multi-use path from McKinley Woods road to IandM Canal and the construction of a pedestrian bridge over the IandM Canal. Project is located along US Route 6 and Bridge Street, beginning west of McKinley Drive and ending east of the IandM Canal at Bridge Street in the Village of Channahon. | — | Executed | D. Construction, Inc. $734,856 · | ||
| Sep 20, 2019 | 99631 | WilliamsonDistrict 9 | Resurfacing Paulton Road from 0.3 miles north of Grant Brick Road to Toledo Road. | — | Executed | E. T. Simonds Construction Company $477,971 · | ||
| Nov 8, 2019 | 62K13 | WillDistrict 1 | Surveillance camera replacement on I-55 (Lorenzo Rd to Joliet Rd) and I-80 (IL 43 to US 30). | — | Executed | Meade Inc. $482,744 · | ||
| Nov 8, 2019 | 78636 | WilliamsonDistrict 9 | Convert existing intersection of Cambria Road and Herrin Road into a roundabout. Includes HMA surface removal, PCC pavement, HMA surfacing and storm sewers. | — | Executed | E. T. Simonds Construction Company $1,624,828 · | ||
| Nov 8, 2019 | 78732 | JeffersonWilliamsonDistrict 9 | Inserting culvert liners at three locations: 1) SN 100-7039 on IL 148 approximately 2 miles northwest of I-57 near Neber Road in Williamson County; 2) SN 041-7075 on IL 15 approximately 0.2 miles west of Shepherd Lane in Jefferson County; 3) SN 041-7076 on IL 15 approximately 0.3 miles east of Shepherd Lane in Jefferson County. | — | Executed | Samron Midwest Contracting, Inc. $219,125 · |
1–47 of 47
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.