2019-139-I
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Meade Inc. Low bidder | $482,744 | ||
| 2 | William Charles Construction Co, LLC | $684,000 | +41.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Meade Inc. | #2 William Charles… |
|---|---|---|---|---|---|---|---|
| 1 | X1400179 | CCTV DOME CAMERA HD | 44 | EACH | $2,048.44 | $2,154.00 | |
| 2 | X1400390 | REPL EX CCTV CAM/LDV 80 M.H. | 28 | EACH | $9,707.45 | $11,148.00 | |
| 3 | X1400391 | REPL EX CCTV CAM/LDV 50 M.H. | 3 | EACH | $9,348.29 | $9,356.00 | |
| 4 | X1400392 | REPL EX CCTV CAM BR MT | 2 | EACH | $1,309.02 | $4,880.00 | |
| 5 | X1400393 | REPL EX CCTV CAM P MT 50 M.H. | 11 | EACH | $2,097.14 | $3,298.00 | |
| 6 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $30,712.50 | $128,765.00 | |
| 7 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,575.00 | $3,780.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $26,909.79 | $51,529.00 |