2018-002I
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | John Burns Construction Company Low bidder | $1,900,000 | ||
| 2 | Utility Dynamics Corporation | $2,256,609 | +18.8% | |
| 3 | Meade Inc. | $2,762,446 | +45.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 John Burns Cons… | #2 Utility Dynamic… | #3 Meade Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 1,334 | SQ FT | $6.00 | $3.30 | $6.30 | |
| 2 | X1400301 | FOC MICRO 96F S MODE | 49,324 | FOOT | $2.30 | $5.00 | $4.78 | |
| 3 | X1400360 | DIR BORING THR ROCK | 2,500 | FOOT | $60.00 | $120.00 | $148.22 | |
| 4 | X4021000 | TEMP ACCESS- PRIV ENT | 4 | EACH | $900.00 | $2,000.00 | $6,051.40 | |
| 5 | X4022000 | TEMP ACCESS- COM ENT | 4 | EACH | $1,300.00 | $2,000.00 | $6,576.40 | |
| 6 | X4400220 | CURB REM & REPLACEMT | 100 | FOOT | $55.00 | $30.00 | $97.79 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $12,700.00 | $32,170.00 | $15,750.00 | |
| 8 | X8100863 | INTERCEPT EX CONDUIT | 7 | EACH | $850.00 | $335.00 | $1,403.60 | |
| 9 | X8101100 | UNDRGRD C MULTI 7-16 | 18,047 | FOOT | $12.00 | $12.00 | $18.29 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,700.00 | $11,550.00 | $21,000.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 278 | SQ FT | $10.00 | $22.00 | $39.37 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 14 | 20101100 | TREE TRUNK PROTECTION | 94 | EACH | $70.00 | $385.00 | $194.25 | |
| 15 | 20101200 | TREE ROOT PRUNING | 45 | EACH | $85.00 | $200.00 | $210.00 | |
| 16 | 20101300 | TREE PRUN 1-10 | 20 | EACH | $50.00 | $65.00 | $157.50 | |
| 17 | 20101350 | TREE PRUN OVER 10 | 20 | EACH | $80.00 | $130.00 | $210.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 150 | CU YD | $365.00 | $50.00 | $108.54 | |
| 19 | 20200200 | ROCK EXCAVATION | 75 | CU YD | $180.00 | $500.00 | $256.98 | |
| 20 | 20201200 | REM & DISP UNS MATL | 25 | CU YD | $55.00 | $145.00 | $128.15 | |
| 21 | 20400800 | FURNISHED EXCAVATION | 70 | CU YD | $95.00 | $25.00 | $33.00 | |
| 22 | 21101505 | TOPSOIL EXC & PLAC | 40 | CU YD | $100.00 | $30.00 | $34.73 | |
| 23 | 21301048 | EXPLOR TRENCH 48 | 600 | FOOT | $110.00 | $65.00 | $34.54 | |
| 24 | 25200110 | SODDING SALT TOLERANT | 270 | SQ YD | $24.00 | $46.75 | $25.20 | |
| 25 | 28000400 | PERIMETER EROS BAR | 400 | FOOT | $6.00 | $7.15 | $6.30 | |
| 26 | 28000510 | INLET FILTERS | 30 | EACH | $275.00 | $467.50 | $288.75 | |
| 27 | 40601005 | HMA REPL OVER PATCH | 7 | TON | $851.00 | $825.00 | $893.55 | |
| 28 | 42001300 | PROTECTIVE COAT | 386 | SQ YD | $5.00 | $1.10 | $5.25 | |
| 29 | 42400200 | PC CONC SIDEWALK 5 | 1,575 | SQ FT | $15.00 | $6.60 | $12.60 | |
| 30 | 44000600 | SIDEWALK REM | 1,575 | SQ FT | $10.00 | $10.00 | $6.83 | |
| 31 | 44002209 | HMA RM OV PATCH 2 1/4 | 720 | SQ YD | $19.00 | $28.05 | $19.65 | |
| 32 | 44201349 | CL C PATCH T1 10 | 180 | SQ YD | $325.00 | $110.00 | $648.50 | |
| 33 | 44201353 | CL C PATCH T2 10 | 180 | SQ YD | $170.00 | $110.00 | $535.90 | |
| 34 | 44201357 | CL C PATCH T3 10 | 180 | SQ YD | $160.00 | $110.00 | $423.30 | |
| 35 | 44201359 | CL C PATCH T4 10 | 180 | SQ YD | $50.00 | $110.00 | $310.70 | |
| 36 | 48101500 | AGGREGATE SHLDS B 6 | 2,223 | SQ YD | $20.00 | $13.20 | $27.90 | |
| 37 | 66900200 | NON SPL WASTE DISPOSL | 250 | CU YD | $70.00 | $81.00 | $90.25 | |
| 38 | 66900530 | SOIL DISPOSAL ANALY | 5 | EACH | $1,250.00 | $990.00 | $1,312.50 | |
| 39 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,100.00 | $2,530.00 | $2,205.00 | |
| 40 | 66901002 | ON-SITE MON REG SUB | 45 | CAL DA | $500.00 | $660.00 | $756.00 | |
| 41 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $1,800.00 | $3,850.00 | $1,890.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $112,118.29 | $367,120.00 | $165,000.00 | |
| 43 | 70107025 | CHANGEABLE MESSAGE SN | 280 | CAL DA | $25.00 | $27.50 | $26.25 | |
| 44 | 70300100 | SHORT TERM PAVT MKING | 4,000 | FOOT | $0.7500 | $0.8300 | $0.7900 | |
| 45 | 70300150 | SHRT TRM PAVT MK REM | 1,334 | SQ FT | $2.25 | $2.50 | $2.36 | |
| 46 | 78000100 | THPL PVT MK LTR & SYM | 150 | SQ FT | $40.00 | $44.00 | $42.00 | |
| 47 | 78009000 | MOD URETH PM LTR-SYM | 150 | SQ FT | $40.00 | $44.00 | $42.00 | |
| 48 | 78100300 | REPLACEMENT REFLECTOR | 50 | EACH | $40.00 | $44.00 | $42.00 | |
| 49 | 78300200 | RAISED REF PVT MK REM | 50 | EACH | $0.1000 | $1.00 | $26.25 | |
| 50 | 81028240 | UNDRGRD C GALVS 4 | 8,969 | FOOT | $60.00 | $52.00 | $66.32 | |
| 51 | 81028790 | UNDRGRD C CNC 4 | 2,199 | FOOT | $20.00 | $38.00 | $39.45 | |
| 52 | 81101005 | CON AT ST 4 PVC GALVS | 95 | FOOT | $250.00 | $126.00 | $157.96 | |
| 53 | 81300960 | JUN BX SS AS 42X36X12 | 2 | EACH | $8,800.00 | $1,730.00 | $3,129.50 | |
| 54 | 81400100 | HANDHOLE | 15 | EACH | $3,615.00 | $1,210.00 | $3,478.20 | |
| 55 | 81400200 | HD HANDHOLE | 23 | EACH | $3,825.00 | $1,650.00 | $4,279.00 |