51Let jobs
$66,741,046Total low bids
$57,777,793Total estimates
+15.5%Low bids vs estimates
Jan 2011 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jan 20, 2011 | 110017BRFY-158B(055) | Ottawa Division 8 |
BRIDGE AND APPROACHES US -59: OVER THE BNSF RAILROAD , 2.6 MILES NORTH OF THE DELAWARE COUNTY LINE . PROJECT LENGTH = 0.400 MILES · | — | $4,944,607 | MANHATTAN ROAD & BRIDGE COMPANY, LLC | 4 | |
| Jan 20, 2011 | 110034NHY-013N(139)3P | Atoka Division 2 |
RESURFACE (CONCRETE) US-69: FROM THE PITTSBURG COUNTY LINE , EXTEND SOUTH. PROJECT LENGTH = 8.00 MILES · | $5,394,750 | $4,781,054 | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | -11.4% | 6 |
| Jan 20, 2011 | 110079NHY-018N(055)3P | Kay Division 4 |
RESURFACE (ASPHALT ) US-60: FROM 1.66 MILES EAST OF US -177, EXTEND EAST. PROJECT LENGTH = 6.38 MILES · | $3,627,300 | $3,718,849 | Evans & Associates Construction Co., Inc. | +2.5% | 3 |
| Jan 20, 2011 | 110140SSR-166A(253)SR | Rogers Division 8 |
RESURFACE (ASPHALT ) SH-66: FROM 6.45 MILES NORTH OF THE I -44 JUNCTION, EXTEND NORTHEAST . PROJECT LENGTH = 4.06 MILES · | $3,285,329 | $2,959,790 | Paragon Contractors, LLC | -9.9% | 3 |
| Jan 20, 2011 | 110100NHY-022N(204)3P | Mccurtain Division 2 |
PAVEMENT REHABILITATION (ASPHALT ) US-70: FROM 13.5 MILES EAST OF THE CHOCTAW COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 6.004 MILES · | $2,385,352 | $2,697,907 | THE CUMMINS CONSTRUCTION CO., INC. | +13.1% | 2 |
| Jan 20, 2011 | 110025STPY-122C(078)3P | Stpy-122c(079)3p |
BLAINE, DEWEY RESURFACE (ASPHALT ) SH-51: FROM THE US -270 JUNCTION, EXTEND EAST. PROJECT LENGTH = 12.95 MILES · | $2,497,719 | $2,495,827 | THE CUMMINS CONSTRUCTION CO., INC. | -0.1% | 7 |
| Jan 20, 2011 | 110046NHY-020N(038)3P | Comanche Division 7 |
RESURFACE (ASPHALT ) US-62: FROM THE KIOWA COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 4.98 MILES · | $2,794,104 | $2,460,778 | T & G CONSTRUCTION, INC. | -11.9% | 6 |
| Jan 20, 2011 | 110161STPY-138C(186)3P | Stpy-175c(128)3p |
KIOWA, WASHITA RESURFACE (ASPHALT ) SH-54: FROM THE SH -9 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 15.36 MILES · | $2,615,094 | $2,415,188 | CORNELL CONSTRUCTION COMPANY, INC. | -7.6% | 7 |
| Jan 20, 2011 | 110165STPY-109C(176)3P | Stpy-109c(177)3p |
28252(04) STPY-109C(178)3P BLAINE, CANADIAN RESURFACE (ASPHALT ) US-270: FROM THE US -281 JUNCTION, EXTEND EAST THEN SOUTH AT 3RD STREET IN THE TOWN OF CALUMET . PROJECT LENGTH = 16.56 MILES · | $2,180,636 | $2,399,756 | SCHWARZ PAVING CO., INC. | +10.0% | 3 |
| Jan 20, 2011 | 110162SSR-101A(073)SR | Ssr-101a(074)sr |
ADAIR RESURFACE (ASPHALT ) US-59: FROM 0.25 MILES NORTH OF THE SH -51 WEST JUNCTION , EXTEND NORTH . PROJECT LENGTH = 13.50 MILES · | $2,164,739 | $2,117,391 | APAC-CENTRAL, INC. | -2.2% | 6 |
| Jan 20, 2011 | 110057SSR-121B(145)SR | Ssr-121b(146)sr |
27612(04) SSR-121B(147)SR DELAWARE RESURFACE (ASPHALT ) US-59: FROM THE US -412A JUNCTION, EXTEND NORTH . PROJECT LENGTH = 17.24 MILES · | $2,256,631 | $2,082,726 | GLOVER & ASSOCIATES, INC. | -7.7% | 5 |
| Jan 20, 2011 | 110092STPY-142C(211)3P | Stpy-142c(212)3p |
28254(04) STPY-142C(213)3P LOGAN RESURFACE (ASPHALT ) US-77:FROM 4.0 MILES SOUTH OF THE SH -51 JUNT, EXTEND NORTH . SH-74F: FROM 4.9 MILES WEST OF SH -74 JCT., EXT EAST . SH-51: FROM 5.6 MILES EAST OF THE SH-74 JCT., EXTEND EAST. PROJECT LENGTH = 14.59 MI · | $1,647,980 | $1,985,150 | HASKELL LEMON CONSTRUCTION CO. | +20.5% | 2 |
| Jan 20, 2011 | 110014STP-155B(813)AG | Oklahoma Division 4 |
GRADE, DRAIN, AND SURFACE CITY STREET (HEFNER RD): FROM THE BROADWAY EXTENSION , EXTEND EAST IN OKLAHOMA CITY . PROJECT LENGTH = 5.280 MILES · | — | $1,967,951 | HASKELL LEMON CONSTRUCTION CO. | 5 | |
| Jan 20, 2011 | 110164STPY-163B(350)3P | Stpy-163b(351)3p |
28209(06) STPY-163B(352)3P POTTAWATOMIE RESURFACE (UTBWC) US-177: FROM THE SH -39 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 19.01 MILES · | $2,433,869 | $1,955,646 | HASKELL LEMON CONSTRUCTION CO. | -19.6% | 3 |
| Jan 20, 2011 | 110027NHY-020N(036)3P | Harmon Division 5 |
RESURFACE (ASPHALT ) US-62: FROM 1.0 MILE EAST OF THE SH -30 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.00 MILES · | $1,824,075 | $1,765,815 | CORNELL CONSTRUCTION COMPANY, INC. | -3.2% | 7 |
| Jan 20, 2011 | 110109STPY-165C(119)3P | Stpy-165c(120)3p |
ROGER MILLS RESURFACE (ASPHALT ) SH-30: FROM THE BECKHAM COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 14.02 MILES · | $1,653,507 | $1,618,009 | CASWELL CONSTRUCTION, INC. | -2.1% | 7 |
| Jan 20, 2011 | 110167STPY-168A(216)3P | Stpy-168c(217)3p |
SEQUOYAH RESURFACE (ASPHALT ) US-59: FROM THE SH -101 JUNCTION, EXTEND NORTH . SH-101: FROM THE US-59 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.28 MILES · | $1,696,906 | $1,599,833 | JOB CONSTRUCTION CO., INC. | -5.7% | 4 |
| Jan 20, 2011 | 110005SSR-114A(270)SR | Cleveland Division 3 |
RESURFACE (ASPHALT ) SH-9: FROM 24TH AVENUE IN THE CITY OF NORMAN, EXTEND EAST. PROJECT LENGTH = 4.16 MILES · | — | $1,485,574 | HASKELL LEMON CONSTRUCTION CO. | 4 | |
| Jan 20, 2011 | 110112STPY-152C(185)3P | Noble Division 4 |
RESURFACE (ASPHALT ) US-64: FROM THE US -177 JUNCTION, EXTEND EAST. PROJECT LENGTH = 8.00 MILES · | $1,228,634 | $1,316,214 | THE QUAPAW COMPANY | +7.1% | 3 |
| Jan 20, 2011 | 110111STPY-176C(173)3P | Woods Division 6 |
RESURFACE (ASPHALT ) SH-45: FROM THE US -281 JUNCTION, EXTEND EAST. PROJECT LENGTH = 4.5 MILES · | $1,249,914 | $1,203,747 | Venture Corporation dba VCO Paving | -3.7% | 2 |
| Jan 20, 2011 | 110049SSR-119B(175)SR | Ssr-119b(210)sr |
CREEK RESURFACE (ASPHALT ) SH-117: FROM THE US -75A JUNCTION, EXTEND EAST. SH-117A: FROM THE SH-117 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 5.45 MILES · | — | $1,152,074 | BECCO CONTRACTORS, INC. | 5 | |
| Jan 20, 2011 | 110056SSR-121C(144)SR | Ssr-121c(149)sr |
DELAWARE RESURFACE (ASPHALT ) SH-20: FROM 10.0 MILES EAST OF THE SH -10 JCT, EXTEND NORTH . SH-10: FROM THE ADAIR COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 9.18 MILES · | — | $1,116,503 | HUTCHENS ASPHALT PAVING CO. DBA HUTCHENS CONSTRUCTION CO. | 4 | |
| Jan 20, 2011 | 110106BRF-118C(070)CI | Craig Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-19): OVER BIG CABIN CREEK, 2.3 MILES WEST OF THE SH-2 JUNCTION. PROJECT LENGTH = 0.610 MILES · | $1,159,199 | $969,553 | BELK BRIDGE, INC. | -16.4% | 4 |
| Jan 20, 2011 | 110132STPY-163A(355)3P | Pottawatomie Division 3 |
RESURFACE (ASPHALT ) SH-18: FROM THE US -270B JUNCTION, EXTEND EAST. PROJECT LENGTH = 4.61 MILES · | — | $962,818 | HASKELL LEMON CONSTRUCTION CO. | 1 | |
| Jan 20, 2011 | 110145STPY-168C(218)3P | Sequoyah Division 1 |
RESURFACE (ASPHALT ) US-64: FROM 3.0 MILES WEST OF THE US -59 SOUTH JUNCTION, EXTEND EAST. PROJECT LENGTH = 3.00 MILES · | $1,150,540 | $937,172 | JOB CONSTRUCTION CO., INC. | -18.5% | 4 |
| Jan 20, 2011 | 110052SBR-119C(209)SB | Creek Division 8 |
BRIDGE REHABILITATION SH -66: OVER LITTLE POLECAT CREEK , 13.4 MILES NORTHEAST OF THE SH-48 JUNCTION. · | $1,052,128 | $885,774 | MANHATTAN ROAD & BRIDGE COMPANY, LLC | -15.8% | 5 |
| Jan 20, 2011 | 110102SBR-150N(082)SB | Murray Division 7 |
BRIDGE REHABILITATION I-35: OVER SH-77D, 4.8 MILES NORTH OF THE CARTER COUNTY LINE. · | $939,045 | $838,024 | SCR CONSTRUCTION CO., INC. | -10.8% | 5 |
| Jan 20, 2011 | 110069SSP-126N(177)SS | Grady Division 7 |
WIDEN AND RESURFACE (ASPHALT ) US-81: FROM 1.5 MILES NORTH OF SH -19E, EXTEND NORTH . PROJECT LENGTH = 0.799 MILES · | $882,769 | $789,462 | SCHWARZ PAVING CO., INC. | -10.6% | 7 |
| Jan 20, 2011 | 110115IMY-35-2(299)126 3P | Oklahoma Division 4 |
PAVEMENT REHABILITATION (P.C. CONCRETE) I-35: FROM S.E. 15TH STREET, EXTEND NORTH IN OKLAHOMA CITY . PROJECT LENGTH = 0.44 MILES · | $694,594 | $784,352 | IOWA CIVIL CONTRACTING, INC. | +12.9% | 5 |
| Jan 20, 2011 | 110028STP-142C(176)AG | Logan Division 4 |
RESURFACE (ASPHALT ) CITY STREET (WESTERN AVE ): FROM WATERLOO ROAD , EXTEND NORTH IN THE TOWN OF SEWARD . PROJECT LENGTH = 3.50 MILES · | $921,405 | $781,210 | Atlas Paving Company | -15.2% | 5 |
| Jan 20, 2011 | 110099SBR-145C(169)SB | Mccurtain Division 2 |
BRIDGE REHABILITATION SH -37: OVER WATERHOLE CREEK , 6.2 MILES EAST OF THE OKLAHOMA/ TEXAS STATE LINE . · | $870,885 | $768,909 | HUB Construction, Inc. | -11.7% | 3 |
| Jan 20, 2011 | 110007SBR-116C(190)SB | Comanche Division 7 |
BRIDGE REHABILITATION SH -65: OVER WEST FORK OF BEAVER CREEK , 4.2 MILES NORTH OF THE SH-7 JUNCTION. PROJECT LENGTH = 0.191 MILES · | $977,365 | $749,505 | PBX Corporation | -23.3% | 4 |
| Jan 20, 2011 | 110008BRO-119D(044)CO | Creek Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-67): OVER BUCKEYE CREEK, 4.7 MILES EAST OF THE SH-99 JUNCTION. PROJECT LENGTH = 0.207 MILES · | $742,530 | $736,532 | BRIDGECO CONTRACTORS, INC. | -0.8% | 6 |
| Jan 20, 2011 | 110151STPY-172B(514)3P | Tulsa Division 8 |
RESURFACE (ASPHALT ) SH-117: FROM THE CREEK COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 1.01 MILES · | $865,265 | $719,318 | BECCO CONTRACTORS, INC. | -16.9% | 4 |
| Jan 20, 2011 | 110060STPY-121B(148)3P | Delaware Division 8 |
RESURFACE (ASPHALT ) US-59: FROM THE SH -20 WEST JUNCTION , EXTEND NORTH . PROJECT LENGTH = 1.71 MILES · | $783,647 | $711,100 | GLOVER & ASSOCIATES, INC. | -9.3% | 4 |
| Jan 20, 2011 | 110130SSR-162B(220)SR | Pontotoc |
RESURFACE (ASPHALT ) SH-99: FROM 8.17 MILES NORTH OF THE JOHNSTON COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 7.4 MILES · | $718,110 | $707,628 | THE CUMMINS CONSTRUCTION CO., INC. | -1.5% | 3 |
| Jan 20, 2011 | 110159NHY-017N(240)3P | Woodward Division 6 |
RESURFACE (ASPHALT ) US-183: FROM THE SH -34 SOUTH JUNCTION, EXTEND NORTH . PROJECT LENGTH = 3.71 MILES · | — | $697,824 | THE CUMMINS CONSTRUCTION CO., INC. | 1 | |
| Jan 20, 2011 | 110139BHFY-NBIP(437) | Choctaw, Leflore, Pittsburg, Pushmataha |
BRIDGE PAINTING US-70/SH-2/SH-3/SH-93/SH-113: AT VARIOUS LOCATIONS IN DIVISION II. · | $836,318 | $653,670 | Panther Industrial Painting, LLC | -21.8% | 10 |
| Jan 20, 2011 | 110127STPY-160B(209)3P | Payne Division 4 |
RESURFACE (ASPHALT ) SH-33: FROM THE US -177 NORTH JUNCTION , EXTEND EAST. PROJECT LENGTH = 1.54 MILES · | $600,990 | $603,614 | THE QUAPAW COMPANY | +0.4% | 3 |
| Jan 20, 2011 | 110020BRF-177C(072)CI | Woodward Division 6 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-54): OVER HACKBERRY CREEK , 4.4 MILES EAST OF THE SH -34 JUNCTION. PROJECT LENGTH = 0.150 MILES · | $512,456 | $510,648 | OBC, INC. | -0.4% | 11 |
| Jan 20, 2011 | 110009CIRB-120C(157)RB | Custer Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-208): OVER PANTHER CREEK , 3.0 MILES SOUTH OF THE SH-33 JUNCTION. PROJECT LENGTH = 0.210 MILES · | $507,220 | $498,657 | K & R BUILDERS, INC. | -1.7% | 5 |
| Jan 20, 2011 | 110019BRO-173D(122)CI | Wagoner Division 1 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-79): OVER RAILROAD CREEK, 0.4 MILES WEST OF THE SH-16 JUNCTION. PROJECT LENGTH = 0.227 MILES · | $514,997 | $449,607 | C-GAWF CONSTRUCTION, INC. | -12.7% | 4 |
| Jan 20, 2011 | 110013STP-155B(480)AG | Oklahoma Division 4 |
RESURFACE (ASPHALT ) CITY STREET (SE 15TH ST.): FROM INDIAN MERIDAN, EXTEND EAST IN THE CITY OF CHOCTAW . PROJECT LENGTH = 0.964 MILES · | $452,991 | $374,553 | HASKELL LEMON CONSTRUCTION CO. | -17.3% | 7 |
| Jan 20, 2011 | 110002BRO-106D(089)CI | Blaine Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-67): OVER MINNEHAHA CREEK , 1.2 MILES WEST OF THE SH -58 JUNCTION. PROJECT LENGTH = 0.226 MILES · | $361,397 | $322,668 | BRIDGECO CONTRACTORS, INC. | -10.7% | 8 |
| Jan 20, 2011 | 110136STPY-163C(353)3P | Pottawatomie Division 3 |
RESURFACE (ASPHALT ) SH-270: FROM THE OKLAHOMA COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 2.35 MILES · | $304,915 | $272,087 | HASKELL LEMON CONSTRUCTION CO. | -10.8% | 4 |
| Jan 20, 2011 | 110138BHFY-164F(164) | Choctaw, Pittsburg, Pushmataha |
JOINT SEAL / REPAIR SH-2/SH-93/SH-113: AT MULTIPLE LOCATIONS IN DIVISION II. · | $458,315 | $247,851 | PBX Corporation | -45.9% | 5 |
| Jan 20, 2011 | 110131SSR-163C(347)SR | Pottawatomie Division 3 |
RESURFACE (ASPHALT ) SH-102: FROM 1.6 MILES SOUTH OF THE SH -39 JUNCTION, EXTEND NORTH . PROJECT LENGTH = 1.7 MILES · | $273,842 | $212,174 | HASKELL LEMON CONSTRUCTION CO. | -22.5% | 5 |
| Jan 20, 2011 | 110142SEC117-168E(211)SG | Sequoyah Division 1 |
SURFACE (P.C. CONCRETE) ACCESS ROAD (GEORGE GLEN BLVD ): FROM HOUSER INDUSTRIAL BLVD EXTEND SOUTH THEN EAST IN THE CITY OF SALLISAW. PROJECT LENGTH = 0.24 MILES · | $183,970 | $146,740 | GLOVER & ASSOCIATES, INC. | -20.2% | 9 |
| Jan 20, 2011 | 110004STPG-114B(260)AG | Cleveland Division 3 |
TRAFFIC SIGNAL CITY STREET(NE 12TH ST.): AT BUCK THOMAS DRIVE IN THE CITY OF MOORE. · | — | $79,491 | TRAFFIC SIGNALS, INC. | 4 | |
| Jan 20, 2011 | 110010SSP-104C(080)SS | Beaver, Woodward |
JOINT SEAL/REPAIR US-270/SH-50: AT MULTIPLE LOCATIONS IN DIVISIONS VI. · | $45,190 | $61,793 | BEHNE CONSTRUCTION CO., INC. | +36.7% | 5 |
| Jan 20, 2011 | 110030STPG-155B(804)AG | Oklahoma Division 4 |
PEDESTRIAN IMPROVEMENTS CITY STREET (PENNSYLVANIA AVE .): FROM GLADSTONE TERRACE , EXTEND NORTH IN THE CITY OF THE VILLAGE . PROJECT LENGTH = 0.123 MILES · | $31,172 | $27,929 | RUDY CONSTRUCTION CO. | -10.4% | 6 |
1–51 of 51
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.