| 1 | 202(G) 0185 |
EARTHWORK | 1 | LSUM |
$100,000.00 |
$70,000.00 |
$60,969.39 |
$36,711.52 |
$65,380.63 |
$57,500.00 |
$73,568.78 |
| 2 | 223 2801 |
TEMPORARY SILT FENCE | 1,600 | LF |
$2.00 |
$1.50 |
$1.37 |
$1.38 |
$1.30 |
$1.30 |
$2.45 |
| 3 | 227 0100 |
TEMPORARY SILT DIKE | 160 | LF |
$5.00 |
$4.00 |
$6.28 |
$6.36 |
$5.97 |
$5.97 |
$13.16 |
| 4 | 411(S4) 5955 |
(SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 28,580 | TON |
$62.00 |
$53.75 |
$64.76 |
$67.95 |
$70.48 |
$66.50 |
$75.83 |
| 5 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 9,180 | TON |
$56.00 |
$46.55 |
$58.73 |
$62.90 |
$61.55 |
$60.50 |
$68.95 |
| 6 | 413(A) 4861 |
RUMBLE STRIP-METHOD AC-CON | 99,600 | LF |
$0.1500 |
$0.1000 |
$0.0800 |
$0.0900 |
$0.1300 |
$0.0800 |
$0.1800 |
| 7 | 417 4267 |
COLD MILLING BITUMINOUS PAVEMENT | 10,200 | SY |
$1.50 |
$1.00 |
$1.57 |
$1.20 |
$1.93 |
$2.90 |
$4.08 |
| 8 | 420(A) 4242 |
FABRIC REINFORCEMENT | 151,924 | SY |
$0.6500 |
$0.7000 |
$0.9300 |
$0.9100 |
$0.8500 |
$0.8500 |
$0.9400 |
| 9 | 420(B) 4268 |
BITUMINOUS BINDER | 37,982 | GAL |
$1.90 |
$2.60 |
$4.51 |
$3.90 |
$2.30 |
$4.11 |
$3.06 |
| 10 | 504(F) 1381 |
CONCRETE PARAPET | 96 | LF |
$650.00 |
$250.00 |
$263.01 |
$223.72 |
$275.00 |
$349.00 |
$177.24 |
| 11 | 623(A) 0932 |
BEAM GUARD RAIL-W-BEAM-SINGLE | 2,447.5 | LF |
$14.00 |
$25.50 |
$17.19 |
$21.84 |
$16.34 |
$16.34 |
$16.67 |
| 12 | 623(E) 7114 |
THRIE BEAM BRIDGE CONNECTION-TYPE A | 8 | EA |
$2,000.00 |
$2,000.00 |
$1,362.37 |
$2,183.87 |
$1,295.00 |
$2,795.00 |
$2,091.00 |
| 13 | 623(H) 8571 |
(SP)G.E.T. GUARD RAIL END SECTION | 8 | EA |
$2,200.00 |
$3,000.00 |
$2,156.65 |
$2,364.97 |
$2,050.00 |
$2,050.00 |
$1,320.90 |
| 14 | 855(A) 8815 |
TRAFFIC STRIPE(PLASTIC)(THIN-LINE)(4" WIDE) | 119,680 | LF |
$0.3200 |
$0.3500 |
$0.3700 |
$0.3700 |
$0.3500 |
$0.3500 |
$0.3600 |
| 15 | 855(B) 8818 |
TRAFFIC STRIPE(PLASTIC)(ARROWS) | 18 | EA |
$90.00 |
$85.00 |
$89.42 |
$90.55 |
$85.00 |
$85.00 |
$86.70 |
| 16 | 855(B) 8821 |
TRAFFIC STRIPE(PLASTIC)(WORDS) | 9 | EA |
$125.00 |
$125.00 |
$131.50 |
$133.16 |
$125.00 |
$125.00 |
$127.50 |
| 17 | 876(C) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 16 | SD |
$100.00 |
$95.00 |
$99.94 |
$101.20 |
$95.00 |
$95.00 |
$96.90 |
| 18 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$30,000.00 |
$26,500.00 |
$6,312.14 |
$6,391.81 |
$23,555.26 |
$77,050.00 |
$6,720.25 |