RESURFACE (ASPHALT ) SH-270: FROM THE OKLAHOMA COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 2.35 MILES
- Let date
- Thursday, January 20, 2011
- Contract
- 110136
- J/P numbers
- 28210(04)
- District
- Division 3
- County
- Pottawatomie
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-270: FROM THE OKLAHOMA COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 2.35 MILES
- Project number
- STPY-163C(353)3P
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $304,915 | ||
| 1 | HASKELL LEMON CONSTRUCTION CO. Low bidder | $272,087 | -10.8% | |
| 2 | RUDY CONSTRUCTION CO. | $356,348 | +16.9% | +31.0% |
| 3 | MARKWELL PAVING COMPANY, INC. | $363,052 | +19.1% | +33.4% |
| 4 | K & K CONTRACTING, INC. | $438,107 | +43.7% | +61.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 HASKELL LEMON C… | #2 RUDY CONSTRUCTI… | #3 MARKWELL PAVING… | #4 K & K CONTRACTI… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(D) 0184 | UNCLASSIFIED BORROW | 329 | CY | $8.00 | $21.00 | $13.50 | $30.00 | $17.50 |
| 2 | 407(B) 0250 | TACK COAT | 3,033 | GAL | $2.64 | $2.00 | $1.60 | $3.00 | $4.81 |
| 3 | 411(D) 5970 | SUPERPAVE, TYPE S5(PG 70-28 OK) | 3,582 | TON | $74.00 | $66.00 | $90.00 | $86.50 | $106.70 |
| 4 | 412 5267 | COLD MILLING PAVEMENT | 300 | SY | $17.00 | $15.00 | $10.00 | $10.00 | $39.00 |
| 5 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 43,428 | LF | $0.4400 | $0.3500 | $0.4300 | $0.4200 | $0.4700 |
| 6 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $3,000.00 | $3,000.00 | $13,000.00 | $3,450.00 |