RESURFACE (ASPHALT ) CITY STREET (SE 15TH ST.): FROM INDIAN MERIDAN, EXTEND EAST IN THE CITY OF CHOCTAW . PROJECT LENGTH = 0.964 MILES
- Let date
- Thursday, January 20, 2011
- Contract
- 110013
- J/P numbers
- 22232(04)
- District
- Division 4
- County
- Oklahoma
- Highway
- Limits
- RESURFACE (ASPHALT ) CITY STREET (SE 15TH ST.): FROM INDIAN MERIDAN, EXTEND EAST IN THE CITY OF CHOCTAW . PROJECT LENGTH = 0.964 MILES
- Project number
- STP-155B(480)AG
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $452,991 | ||
| 1 | HASKELL LEMON CONSTRUCTION CO. Low bidder | $374,553 | -17.3% | |
| 2 | SCHWARZ PAVING CO., INC. | $390,622 | -13.8% | +4.3% |
| 3 | Silver Star Construction Company, Inc. | $395,639 | -12.7% | +5.6% |
| 4 | MARKWELL PAVING COMPANY, INC. | $454,694 | +0.4% | +21.4% |
| 5 | Atlas Paving Company | $471,820 | +4.2% | +26.0% |
| 6 | RUDY CONSTRUCTION CO. | $487,338 | +7.6% | +30.1% |
| 7 | Shell Construction Company, Inc. | $533,779 | +17.8% | +42.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 HASKELL LEMON C… | #2 SCHWARZ PAVING … | #3 Silver Star Con… | #4 MARKWELL PAVING… | #5 Atlas Paving Co… | #6 RUDY CONSTRUCTI… | #7 Shell Construct… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 303 0192 | AGGREGATE BASE | 800 | CY | $35.00 | $53.00 | $36.30 | $47.10 | $35.00 | $40.00 | $47.25 | $65.00 |
| 2 | 411(S3) 5940 | (SP)ASPHALT CONCRETE TYPE S3(PG 70-28 OK) | 2,350 | TON | $70.00 | $57.25 | $65.00 | $60.70 | $63.00 | $75.00 | $78.00 | $84.00 |
| 3 | 411(S4) 5955 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 2,650 | TON | $85.00 | $63.50 | $70.00 | $67.80 | $80.00 | $70.00 | $90.00 | $88.00 |
| 4 | 619(B) 4728 | REMOVAL OF ASPHALT PAVEMENT | 3,645.7 | SY | $2.00 | $2.75 | $2.35 | $3.70 | $5.00 | $7.50 | $4.00 | $5.00 |
| 5 | 855(A) 8815 | TRAFFIC STRIPE(PLASTIC)(THIN-LINE)(4" WIDE) | 20,900 | LF | $0.5000 | $0.3500 | $0.3500 | $0.3500 | $0.3500 | $0.3300 | $0.4500 | $0.5000 |
| 6 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $7,500.00 | $2,000.00 | $1,050.00 | $1,040.00 | $1,100.00 | $980.00 | $2,250.00 | $7,500.00 |
| 7 | 641 1552 | MOBILIZATION | 1 | LSUM | $10,000.00 | $10,000.00 | $6,400.00 | $13,800.00 | $40,000.00 | $42,850.00 | $1,500.00 | $15,000.00 |