PAVEMENT REHABILITATION (ASPHALT ) US-70: FROM 13.5 MILES EAST OF THE CHOCTAW COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 6.004 MILES
- Let date
- Thursday, January 20, 2011
- Contract
- 110100
- J/P numbers
- 28197(04)
- District
- Division 2
- County
- Mccurtain
- Highway
- Limits
- PAVEMENT REHABILITATION (ASPHALT ) US-70: FROM 13.5 MILES EAST OF THE CHOCTAW COUNTY LINE , EXTEND EAST. PROJECT LENGTH = 6.004 MILES
- Project number
- NHY-022N(204)3P
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $2,385,352 | ||
| 1 | THE CUMMINS CONSTRUCTION CO., INC. Low bidder | $2,697,907 | +13.1% | |
| 2 | R. K. Hall, LLC | $2,894,506 | +21.3% | +7.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE CUMMINS CON… | #2 R. K. Hall, LLC |
|---|---|---|---|---|---|---|---|
| 1 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 1,125 | TON | $19.72 | $29.50 | $25.47 |
| 2 | 407(B) 0250 | TACK COAT | 6,655 | GAL | $2.64 | $2.70 | $2.52 |
| 3 | 407(C) 0300 | POLYMER MODIFIED CATIONIC RAPID SET - 1 | 19,165 | GAL | $5.00 | $2.80 | $2.98 |
| 4 | 410(A) 6530 | (SP)HOT-IN-PLACE RECYCLED ASPHALT CONCRETE | 88,978 | SY | $3.89 | $3.80 | $3.42 |
| 5 | 410(B) 6540 | (SP)HOT-IN PLACE ASPHALT EMULSION | 399 | TON | $916.30 | $689.00 | $663.00 |
| 6 | 411(D) 5975 | SUPERPAVE, TYPE S5(PG 64-22 OK) | 5,451 | TON | $60.00 | $70.60 | $80.38 |
| 7 | 411(F) 6100 | STONE MATRIX ASPHALT | 13,416 | TON | $85.00 | $98.95 | $114.87 |
| 8 | 412 5267 | COLD MILLING PAVEMENT | 2,500 | SY | $1.16 | $4.60 | $5.10 |
| 9 | 855(A) 8812 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 75,000 | LF | $0.4700 | $0.4000 | $0.3900 |
| 10 | 855(B) 8818 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 18 | EA | $137.50 | $106.00 | $86.70 |
| 11 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $10,000.00 | $4,300.00 | $4,845.00 |
| 12 | 641 1552 | MOBILIZATION | 1 | LSUM | $20,000.00 | $220,000.00 | $195,475.36 |