$98.08Avg low bid / TON
$98.54Avg of all bids
$99.34Avg engineer's estimate
9Jobs · 111,395.5 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 9,988 | $105.00 | $131.00 |
| 2020 | 3 | 37,167 | $102.07 | $107.57 |
| 2019 | 2 | 32,431 | $104.28 | $103.93 |
| 2018 | 3 | 31,809.5 | $84.92 | $86.21 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 20, 2021 | 210160 | Muskogee, Wagoner | 9,988 TON | $105.00 | BECCO CONTRACTORS, INC. |
| Aug 20, 2020 | 200163 | OkfuskeeDivision 3 | 9,231 TON | $102.50 | HASKELL LEMON CONSTRUCTION CO. |
| Mar 19, 2020 | 200096 | BryanDivision 2 | 22,540 TON | $96.40 | OVERLAND CORPORATION |
| Feb 20, 2020 | 190350 | Stp-224b(059)ss | 5,396 TON | $125.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Jun 20, 2019 | 190182 | OkfuskeeDivision 3 | 9,231 TON | $105.00 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 17, 2019 | 190011 | MarshallDivision 2 | 23,200 TON | $104.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 15, 2018 | 180139 | OklahomaDivision 4 | 309.5 TON | $150.65 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 4,457 TON | $92.00 | BECCO CONTRACTORS, INC. |
| Jan 18, 2018 | 180055 | McintoshDivision 1 | 27,043 TON | $83.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |