$4.14Avg low bid / GAL
$4.06Avg of all bids
$3.22Avg engineer's estimate
7Jobs · 208,903 GAL
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2013 | 7 | 208,903 | $4.14 | $4.06 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 20, 2013 | 130216 | KingfisherDivision 4 | 68,500 GAL | $3.90 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jun 20, 2013 | 130221 | OklahomaDivision 4 | 25,000 GAL | $2.75 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 21, 2013 | 130128 | Nhppy-264n(008)3p | 25,700 GAL | $2.86 | GLOVER & ASSOCIATES, INC. |
| Feb 21, 2013 | 130128 | Nhppy-264n(008)3p | 5,280 GAL | $2.85 | GLOVER & ASSOCIATES, INC. |
| Feb 21, 2013 | 130129 | Stpy-242c(007)3p | 24,000 GAL | $3.25 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 21, 2013 | 130129 | Stpy-242c(007)3p | 1,600 GAL | $3.25 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 21, 2013 | 130129 | Stpy-242c(007)3p | 22,500 GAL | $3.25 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 21, 2013 | 130095 | KingfisherDivision 4 | 3,000 GAL | $3.00 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 17, 2013 | 130018 | ComancheDivision 7 | 25,323 GAL | $10.00 | T & G CONSTRUCTION, INC. |
| Jan 17, 2013 | 130050 | OklahomaDivision 4 | 8,000 GAL | $2.75 | SCHWARZ PAVING CO., INC. |