Bid tab 110377

Let Aug 18, 2011 · Division 8 · Creek Sign up free

‹ Aug 2011 results

BRIDGE AND APPROACHES SH -16: OVER ROCK CREEK, 2.2 MILES EAST OF THE SH -48 JUNCTION. PROJECT LENGTH = 0.099 MILES

Let date
Thursday, August 18, 2011
Contract
110377
J/P numbers
20890(04)
District
Division 8
County
Creek
Highway
Limits
BRIDGE AND APPROACHES SH -16: OVER ROCK CREEK, 2.2 MILES EAST OF THE SH -48 JUNCTION. PROJECT LENGTH = 0.099 MILES
Project number
BRFY-119C(102)

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,166,250
1 OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) Low bidder $955,790 -18.0%
2 C-GAWF CONSTRUCTION, INC. $994,101 -14.8% +4.0%
3 KLAVER CONSTRUCTION COMPANY, INC. $1,131,342 -3.0% +18.4%
4 WITTWER CONSTRUCTION CO., INC. $1,150,064 -1.4% +20.3%
5 BELK BRIDGE, INC. $1,189,869 +2.0% +24.5%
6 Cimarron Construction Company, LLC $1,257,453 +7.8% +31.6%

Bid tab: unit prices 55 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 OBC, INC./PLAIN…#2 C-GAWF CONSTRUC…#3 KLAVER CONSTRUC…#4 WITTWER CONSTRU…#5 BELK BRIDGE, IN…#6 Cimarron Constr…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $8,160.00 $13,500.00 $15,000.00 $14,000.00 $9,000.00 $16,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION13,183CY $5.00 $4.48 $4.50 $6.25 $4.00 $4.50 $5.75
3202(D) 0184 UNCLASSIFIED BORROW22,444CY $5.00 $5.27 $6.00 $6.25 $8.00 $5.00 $7.75
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $15,000.00 $7,140.00 $7,000.00 $15,000.00 $15,000.00 $15,000.00 $7,000.00
5221(C) 2801 TEMPORARY SILT FENCE1,890LF $2.00 $2.03 $1.95 $1.99 $2.00 $1.50 $2.25
6221(F) 0100 TEMPORARY SILT DIKE210LF $14.00 $10.15 $6.95 $9.95 $10.45 $6.99 $8.00
7229 4318 DITCH LINER PROTECTION108LF $2.50 $1.78 $1.95 $1.74 $1.83 $1.40 $1.15
8230(A) 2806 SOLID SLAB SODDING13,186SY $1.50 $1.27 $1.45 $1.24 $1.30 $1.29 $1.70
9232(A) 2813 SEEDING METHOD A7.21AC $500.00 $402.90 $250.00 $395.00 $414.75 $1,299.00 $500.00
10233(A) 2817 VEGETATIVE MULCHING7.21AC $500.00 $504.90 $1,250.00 $495.00 $519.75 $300.00 $500.00
11241 2832 MOWING14.42AC $60.00 $55.08 $10.00 $54.00 $57.00 $75.00 $40.00
12303(B) 2110 AGGREGATE BASE TYPE B664CY $36.00 $53.12 $41.00 $66.00 $52.20 $57.00 $76.00
13307(A) 4200 FLY ASH350TON $70.00 $60.67 $60.00 $63.00 $59.00 $54.00 $73.00
14307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE6,745SY $2.00 $2.63 $2.00 $4.50 $2.50 $3.00 $5.30
15325 5271 SEPARATOR FABRIC3,632SY $1.00 $1.61 $1.25 $2.00 $2.00 $1.50 $2.35
16402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E519TON $20.00 $20.53 $21.00 $31.50 $23.00 $30.00 $37.00
17407(B) 0250 TACK COAT621GAL $6.50 $2.34 $3.00 $5.00 $2.40 $2.29 $5.50
18408 5774 PRIME COAT1,886GAL $5.00 $4.25 $4.00 $9.50 $4.40 $4.17 $11.00
19411(B) 5940 SUPERPAVE, TYPE S3(PG 70-28 OK)230TON $75.00 $87.16 $82.75 $88.80 $92.30 $85.45 $104.00
20411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,335TON $72.00 $78.63 $85.35 $84.50 $83.30 $77.09 $99.00
21411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)151TON $76.00 $100.13 $86.32 $99.75 $106.00 $98.17 $117.00
22411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)472TON $73.00 $82.36 $95.77 $87.75 $87.20 $80.74 $103.00
23509(D) 0325 CLASS C CONCRETE21CY $300.00 $295.47 $350.00 $300.00 $240.00 $350.00 $300.00
24613(A) 0492 24" R.C.PIPE CLASS III128LF $65.00 $55.99 $55.00 $60.00 $93.00 $65.00 $60.00
25613(H) 0450 6" PERFORATED PIPE UNDERDRAIN ROUND75LF $10.00 $22.44 $5.00 $55.00 $15.00 $40.00 $20.00
26613(I) 1096 6" NON-PERF.PIPE UNDERDRAIN RND.25LF $14.00 $22.44 $5.00 $45.00 $15.00 $40.00 $20.00
27613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND1EA $900.00 $780.30 $775.00 $1,000.00 $750.00 $900.00 $775.00
28613(M) 7197 TYPE B6 CULVERT END TREATMENT2EA $1,000.00 $1,187.71 $980.00 $2,000.00 $1,200.00 $950.00 $1,500.00
29613(Q) 5946 OUTLET LATERAL HEADWALL2EA $800.00 $470.41 $250.00 $1,000.00 $350.00 $3,000.00 $1,750.00
30619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $4,590.00 $7,500.00 $3,000.00 $12,500.00 $5,000.00 $9,000.00
31619(B) 4728 REMOVAL OF ASPHALT PAVEMENT4,401SY $4.00 $2.04 $2.80 $3.00 $2.50 $5.00 $4.60
32619(C) 0924 SAWING PAVEMENT1,144LF $4.00 $4.08 $2.24 $4.00 $3.50 $5.00 $3.70
33624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,986LF $4.50 $3.96 $5.00 $3.75 $4.10 $3.75 $4.55
34202(A) 1301 UNCLASSIFIED EXCAVATION3,553CY $7.00 $4.83 $6.00 $6.25 $6.00 $5.00 $11.00
35501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED228CY $10.00 $8.80 $8.00 $5.00 $30.00 $60.00 $19.00
36509(A) 1326 CLASS AA CONCRETE646.1CY $500.00 $327.35 $325.00 $267.45 $429.00 $400.00 $467.00
37511(A) 1332 REINFORCING STEEL129,280LB $0.8500 $0.7500 $0.8700 $0.9000 $0.7000 $1.50 $0.8000
38619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $15,000.00 $13,200.00 $11,200.00 $15,000.00 $9,000.00 $25,000.00 $9,000.00
39856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)2,000LF $0.4100 $1.53 $1.68 $1.50 $2.00 $1.50 $1.70
40857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)5,300LF $0.1600 $0.2600 $0.1700 $0.2500 $0.2600 $0.1500 $0.2900
41857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)1,600LF $0.2100 $0.2600 $0.5100 $0.2500 $0.2600 $0.4500 $0.2900
42876(A) 8482 (PL)TRUCK MOUNTED ATTENUATOR180SD $12.67 $1.02 $1.12 $1.00 $1.05 $1.00 $1.18
43880(A) 8812 ARROW DISPLAY(TYPE C)180SD $6.82 $1.02 $1.12 $1.00 $1.05 $1.00 $1.18
44880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF1,530SD $0.2300 $0.5100 $0.2800 $0.5000 $0.5300 $0.2500 $0.5900
45880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF810SD $0.5600 $2.04 $1.12 $2.00 $2.10 $1.00 $2.36
46880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF1,620SD $1.04 $1.02 $2.08 $1.00 $1.05 $1.85 $1.18
47880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)270SD $0.4200 $3.06 $2.80 $3.00 $3.15 $2.50 $3.53
48880(C) 8848 WING BARRICADES450SD $1.01 $0.2600 $1.12 $0.2500 $0.2600 $1.00 $0.2900
49880(E) 8860 WARNING LIGHTS(TYPE A)1,620SD $0.1100 $0.5100 $0.4000 $0.5000 $0.5300 $0.3500 $0.5900
50880(F) 8878 DRUMS4,050SD $0.1100 $0.1000 $0.4000 $0.1000 $0.1100 $0.3500 $0.1200
51880(G) 8890 CHANNELIZER CONES675SD $0.1300 $0.2600 $0.2800 $0.2500 $0.2600 $0.2500 $0.2900
52882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN180SD $10.48 $5.10 $11.20 $5.00 $8.00 $10.00 $5.89
53642(A) 0095 CONSTRUCTION STAKING LEVEL I1LSUM $35,000.00 $6,534.00 $12,500.00 $1,200.00 $6,498.37 $9,000.00 $4,000.00
54220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $4,120.00 $4,750.00 $2,500.00 $1,600.00 $4,400.00 $8,000.00
55641 1399 MOBILIZATION1LSUM $92,000.00 $43,806.93 $26,000.00 $120,565.00 $82,000.00 $72,472.00 $12,750.00