| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$100,000.00 |
$17,500.00 |
$25,651.50 |
$10,742.90 |
$70,000.00 |
$66,000.00 |
$29,000.00 |
$32,864.40 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 6,878 | CY |
$9.90 |
$5.87 |
$6.13 |
$6.07 |
$7.35 |
$6.34 |
$5.75 |
$6.36 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 55,140 | CY |
$8.70 |
$6.87 |
$6.84 |
$6.88 |
$8.85 |
$8.88 |
$7.00 |
$7.21 |
| 4 | 202(E) 0186 |
SELECT BORROW | 1,450 | CY |
$21.40 |
$30.00 |
$9.45 |
$9.27 |
$27.00 |
$11.83 |
$15.35 |
$9.72 |
| 5 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$20,000.00 |
$17,250.00 |
$8,750.00 |
$8,497.50 |
$15,000.00 |
$26,989.85 |
$13,000.00 |
$8,910.00 |
| 6 | 221(C) 2801 |
TEMPORARY SILT FENCE | 3,000 | LF |
$1.60 |
$2.55 |
$3.07 |
$3.04 |
$2.10 |
$3.98 |
$2.95 |
$3.19 |
| 7 | 221(F) 0100 |
TEMPORARY SILT DIKE | 250 | LF |
$8.10 |
$12.00 |
$15.55 |
$15.40 |
$9.25 |
$6.42 |
$14.95 |
$16.15 |
| 8 | 221(G) 0150 |
TEMPORARY ROCK FILTER DAM TYPE 1 | 5 | CY |
$104.90 |
$125.00 |
$49.50 |
$108.15 |
$170.00 |
$53.48 |
$125.00 |
$486.00 |
| 9 | 230(A) 2806 |
SOLID SLAB SODDING | 15,000 | SY |
$1.50 |
$3.11 |
$2.28 |
$2.05 |
$2.05 |
$1.73 |
$1.99 |
$2.15 |
| 10 | 232(B) 2814 |
SEEDING METHOD B | 1 | AC |
$533.00 |
$3,000.00 |
$2,550.00 |
$2,569.85 |
$2,550.00 |
$3,743.84 |
$2,495.00 |
$2,694.60 |
| 11 | 233(A) 2817 |
VEGETATIVE MULCHING | 4 | AC |
$244.20 |
$750.00 |
$1,200.00 |
$1,024.85 |
$1,025.00 |
$320.90 |
$995.00 |
$1,074.60 |
| 12 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 1,426 | CY |
$60.00 |
$39.95 |
$40.68 |
$39.92 |
$57.50 |
$41.41 |
$42.00 |
$41.86 |
| 13 | 325 5271 |
SEPARATOR FABRIC | 5,778 | SY |
$1.60 |
$1.22 |
$1.25 |
$1.21 |
$1.40 |
$3.33 |
$0.9400 |
$1.26 |
| 14 | 326(B) 0100 |
GEOGRID REINFORCEMENT | 1,382 | SY |
$2.10 |
$1.44 |
$2.28 |
$2.24 |
$1.80 |
$1.38 |
$1.24 |
$2.34 |
| 15 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 250 | TON |
$28.10 |
$21.22 |
$25.82 |
$19.39 |
$27.50 |
$46.03 |
$23.00 |
$20.33 |
| 16 | 407(B) 0250 |
TACK COAT | 815 | GAL |
$3.40 |
$3.75 |
$5.20 |
$3.35 |
$3.35 |
$3.51 |
$3.25 |
$3.51 |
| 17 | 408 5774 |
PRIME COAT | 3,768 | GAL |
$5.00 |
$5.75 |
$5.94 |
$5.67 |
$5.60 |
$5.94 |
$5.50 |
$5.94 |
| 18 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 1,318 | TON |
$85.00 |
$82.00 |
$76.96 |
$79.31 |
$78.00 |
$83.19 |
$77.00 |
$83.16 |
| 19 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 1,085 | TON |
$95.00 |
$84.00 |
$82.00 |
$81.37 |
$81.00 |
$85.35 |
$79.00 |
$85.32 |
| 20 | 412 5267 |
COLD MILLING PAVEMENT | 122 | SY |
$10.00 |
$77.00 |
$37.50 |
$72.10 |
$72.00 |
$75.62 |
$70.00 |
$64.80 |
| 21 | 509(D) 0325 |
CLASS C CONCRETE | 15 | CY |
$334.90 |
$295.00 |
$325.00 |
$360.50 |
$450.00 |
$395.42 |
$300.00 |
$216.00 |
| 22 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 7 | TON |
$50.00 |
$55.00 |
$48.50 |
$103.00 |
$150.00 |
$42.48 |
$120.00 |
$216.00 |
| 23 | 613(A) 0492 |
24" R.C.PIPE CLASS III | 90 | LF |
$78.50 |
$49.00 |
$81.24 |
$77.50 |
$55.00 |
$91.12 |
$87.00 |
$81.26 |
| 24 | 613(A) 0494 |
36" R.C.PIPE CLASS III | 174 | LF |
$104.60 |
$59.00 |
$138.35 |
$132.20 |
$100.00 |
$133.94 |
$127.00 |
$138.62 |
| 25 | 613(B) 5717 |
15" CORR. GALV. STEEL PIPE | 66 | LF |
$65.00 |
$25.00 |
$32.60 |
$27.40 |
$26.00 |
$101.59 |
$23.00 |
$28.73 |
| 26 | 613(H) 0450 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 500 | LF |
$12.30 |
$25.00 |
$30.00 |
$15.45 |
$17.50 |
$13.17 |
$28.00 |
$16.20 |
| 27 | 613(I) 1096 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 100 | LF |
$15.60 |
$25.00 |
$35.00 |
$15.45 |
$10.75 |
$75.43 |
$28.00 |
$16.20 |
| 28 | 613(L) 5724 |
15" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$750.00 |
$475.00 |
$655.00 |
$468.65 |
$180.00 |
$435.35 |
$135.00 |
$491.40 |
| 29 | 613(L) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$1,000.00 |
$947.00 |
$1,272.00 |
$1,104.16 |
$700.00 |
$497.40 |
$970.00 |
$1,157.76 |
| 30 | 613(L) 5734 |
36" PREFAB. CULVERT END SECTION, ROUND | 1 | EA |
$1,434.10 |
$1,247.00 |
$2,115.00 |
$1,766.45 |
$1,375.00 |
$481.35 |
$1,190.00 |
$1,852.20 |
| 31 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$22,104.40 |
$7,250.00 |
$7,900.00 |
$7,107.00 |
$20,000.00 |
$67,000.00 |
$8,300.00 |
$7,452.00 |
| 32 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 5,388 | SY |
$3.90 |
$2.22 |
$3.50 |
$4.64 |
$5.75 |
$5.01 |
$4.50 |
$9.40 |
| 33 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 900 | LF |
$17.00 |
$21.30 |
$17.50 |
$17.00 |
$25.00 |
$19.98 |
$16.50 |
$18.09 |
| 34 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,867.00 |
$2,211.00 |
$1,875.00 |
$1,493.50 |
$1,775.00 |
$2,406.75 |
$1,450.00 |
$1,620.00 |
| 35 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,284.10 |
$2,633.00 |
$2,570.00 |
$2,266.00 |
$2,550.00 |
$1,925.40 |
$2,200.00 |
$2,700.00 |
| 36 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 558 | LF |
$8.60 |
$15.00 |
$14.75 |
$12.88 |
$6.15 |
$6.71 |
$12.50 |
$7.36 |
| 37 | 504 6176 |
INSERTS | 52 | EA |
$75.00 |
$440.00 |
$410.00 |
$412.00 |
$40.00 |
$51.34 |
$400.00 |
$420.00 |
| 38 | 504 6224 |
HANGERS | 52 | EA |
$200.00 |
$440.00 |
$410.00 |
$412.00 |
$113.00 |
$422.52 |
$400.00 |
$420.00 |
| 39 | 616(A) 5810 |
6" DUCTILE IRON PIPE RESTRAINED JOINT | 530 | LF |
$75.00 |
$135.00 |
$122.80 |
$123.60 |
$108.00 |
$77.02 |
$120.00 |
$126.00 |
| 40 | 616(D) 0760 |
1" AIR RELIEF VALVE & VAULT | 2 | EA |
$2,500.00 |
$2,250.00 |
$2,150.00 |
$2,060.00 |
$1,500.00 |
$2,460.24 |
$2,000.00 |
$2,100.00 |
| 41 | 616(D) 0861 |
6" VALVES | 2 | EA |
$1,500.00 |
$1,350.00 |
$1,500.00 |
$1,236.00 |
$830.00 |
$1,262.21 |
$1,200.00 |
$1,260.00 |
| 42 | 616(D) 7051 |
STANDARD VALVE BOX | 2 | EA |
$200.00 |
$175.00 |
$250.00 |
$154.50 |
$190.00 |
$893.17 |
$150.00 |
$157.50 |
| 43 | 616(I) 5440 |
6" HDPE CASING | 310 | LF |
$30.00 |
$120.00 |
$110.00 |
$108.15 |
$17.60 |
$73.81 |
$105.00 |
$110.25 |
| 44 | 616(P) 0200 |
6" HDPE PIPE | 1,900 | LF |
$25.00 |
$120.00 |
$109.00 |
$111.24 |
$19.00 |
$58.27 |
$108.00 |
$113.40 |
| 45 | 616(P) 0500 |
12" HDPE PIPE | 268 | LF |
$50.00 |
$145.00 |
$132.00 |
$133.90 |
$72.50 |
$131.57 |
$130.00 |
$136.50 |
| 46 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 200 | CY |
$17.00 |
$25.00 |
$14.00 |
$30.90 |
$35.00 |
$37.26 |
$15.00 |
$33.00 |
| 47 | 501(G) 6309 |
CLSM BACKFILL | 80 | CY |
$172.10 |
$165.00 |
$151.68 |
$203.58 |
$130.00 |
$105.54 |
$135.00 |
$150.15 |
| 48 | 503(A) 1311 |
PRESTRESSED CONCRETE BEAMS (TYPE II) | 477.34 | LF |
$210.00 |
$192.00 |
$188.57 |
$200.74 |
$220.00 |
$230.71 |
$250.00 |
$231.15 |
| 49 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 1,594.68 | LF |
$240.00 |
$202.00 |
$186.23 |
$197.61 |
$235.00 |
$217.36 |
$260.00 |
$259.53 |
| 50 | 504(A) 1304 |
APPROACH SLAB | 141.6 | SY |
$194.30 |
$155.00 |
$218.76 |
$186.59 |
$170.00 |
$180.11 |
$205.00 |
$224.82 |
| 51 | 504(B) 1305 |
SAW-CUT GROOVING | 1,727.4 | SY |
$3.90 |
$4.25 |
$3.78 |
$4.74 |
$3.65 |
$3.72 |
$3.60 |
$3.96 |
| 52 | 504(C) 6250 |
SEALED EXPANSION JOINT | 70.32 | LF |
$256.40 |
$265.00 |
$251.66 |
$242.69 |
$245.00 |
$228.00 |
$275.00 |
$256.09 |
| 53 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 1,098.8 | LF |
$70.00 |
$59.65 |
$68.50 |
$80.91 |
$65.00 |
$105.30 |
$75.00 |
$70.58 |
| 54 | 506(A) 1322 |
STRUCTURAL STEEL | 2,480 | LB |
$3.00 |
$3.65 |
$2.71 |
$2.15 |
$1.85 |
$1.07 |
$3.00 |
$3.37 |
| 55 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 16 | EA |
$1,336.90 |
$1,250.00 |
$550.00 |
$635.51 |
$2,050.00 |
$624.42 |
$850.00 |
$768.28 |
| 56 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 32 | EA |
$1,170.70 |
$1,250.00 |
$525.00 |
$635.51 |
$2,050.00 |
$639.19 |
$850.00 |
$783.48 |
| 57 | 509 6153 |
SPECIAL CONCRETE FINISH | 1 | LSUM |
$50,000.00 |
$75,000.00 |
$55,500.00 |
$55,620.00 |
$62,500.00 |
$2,206.72 |
$54,000.00 |
$59,400.00 |
| 58 | 509(A) 1326 |
CLASS AA CONCRETE | 493.2 | CY |
$600.00 |
$545.00 |
$500.00 |
$679.13 |
$600.00 |
$953.85 |
$650.00 |
$850.51 |
| 59 | 509(B) 1328 |
CLASS A CONCRETE | 288.2 | CY |
$550.00 |
$555.00 |
$515.00 |
$679.13 |
$770.00 |
$798.35 |
$650.00 |
$775.71 |
| 60 | 511(A) 1332 |
REINFORCING STEEL | 159,621 | LB |
$1.10 |
$1.12 |
$1.04 |
$0.9600 |
$1.00 |
$0.6100 |
$0.9500 |
$1.41 |
| 61 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 130 | LF |
$37.00 |
$44.25 |
$28.10 |
$26.50 |
$50.00 |
$23.28 |
$40.00 |
$37.77 |
| 62 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 260 | LF |
$46.40 |
$48.66 |
$30.73 |
$32.08 |
$50.00 |
$27.39 |
$50.00 |
$50.04 |
| 63 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 130 | LF |
$12.60 |
$10.00 |
$14.00 |
$15.45 |
$15.00 |
$76.36 |
$10.00 |
$19.80 |
| 64 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 260 | LF |
$19.30 |
$10.00 |
$14.00 |
$15.45 |
$15.00 |
$54.12 |
$10.00 |
$22.00 |
| 65 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 66 | 516(A) 6096 |
DRILLED SHAFTS 60" DIAMETER | 190.5 | LF |
$1,000.00 |
$750.00 |
$1,758.73 |
$2,288.66 |
$2,050.00 |
$1,084.28 |
$1,750.00 |
$1,043.75 |
| 67 | 516(C) 6200 |
CROSSHOLE SONIC LOGGING | 3 | EA |
$3,500.00 |
$25,000.00 |
$1,850.00 |
$2,729.50 |
$1,850.00 |
$1,764.95 |
$1,650.00 |
$7,315.00 |
| 68 | 535 6760 |
GEOTECHNICAL INVESTIGATION | 1 | LSUM |
$5,000.00 |
$12,500.00 |
$11,500.00 |
$15,450.00 |
$3,350.00 |
$12,836.01 |
$10,000.00 |
$13,750.00 |
| 69 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 2,144 | TON |
$50.00 |
$34.65 |
$44.35 |
$35.73 |
$34.00 |
$33.93 |
$38.00 |
$35.06 |
| 70 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 399 | TON |
$40.00 |
$29.88 |
$38.10 |
$28.54 |
$26.00 |
$31.59 |
$28.87 |
$27.79 |
| 71 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 64 | LF |
$29.40 |
$25.00 |
$35.00 |
$30.90 |
$22.50 |
$16.71 |
$30.00 |
$51.25 |
| 72 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 40 | LF |
$21.50 |
$25.00 |
$25.00 |
$30.90 |
$22.50 |
$26.74 |
$30.00 |
$34.75 |
| 73 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$75,000.00 |
$50,000.00 |
$45,000.00 |
$61,800.00 |
$52,000.00 |
$100,548.74 |
$125,000.00 |
$198,000.00 |
| 74 | 624(E) 4300 |
FENCE-STYLE CLF (6' HIGH, VINYL COATED) | 398 | LF |
$50.00 |
$150.00 |
$135.20 |
$133.90 |
$37.50 |
$13.44 |
$140.00 |
$36.49 |
| 75 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 200 | SD |
$123.10 |
$82.50 |
$78.75 |
$77.25 |
$75.50 |
$44.93 |
$75.00 |
$81.00 |
| 76 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 136.93 | SF |
$15.00 |
$15.99 |
$14.50 |
$14.42 |
$14.25 |
$32.08 |
$14.00 |
$15.12 |
| 77 | 851(C) 8324 |
2" SQUARE TUBE POST | 264 | LF |
$8.70 |
$9.90 |
$9.36 |
$9.27 |
$9.25 |
$8.56 |
$9.00 |
$9.72 |
| 78 | 853 9069 |
GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 44 | EA |
$13.90 |
$16.50 |
$20.00 |
$15.45 |
$15.25 |
$13.52 |
$15.00 |
$14.58 |
| 79 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 11,000 | LF |
$0.6000 |
$0.6100 |
$0.5600 |
$0.5600 |
$0.5500 |
$1.02 |
$0.5400 |
$0.5800 |
| 80 | 857(A) 8839 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 2,000 | LF |
$0.1000 |
$0.5700 |
$0.5200 |
$0.5200 |
$0.5500 |
$0.8000 |
$0.5000 |
$0.5400 |
| 81 | 857(E) 8887 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 1,000 | EA |
$0.9000 |
$2.25 |
$2.25 |
$2.06 |
$2.05 |
$0.7000 |
$2.00 |
$2.16 |
| 82 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 1,220 | LF |
$40.60 |
$36.00 |
$35.50 |
$25.75 |
$35.00 |
$37.70 |
$34.00 |
$43.20 |
| 83 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 650 | LF |
$3.40 |
$10.00 |
$3.12 |
$4.12 |
$5.00 |
$10.70 |
$3.00 |
$5.40 |
| 84 | 880(I) 8902 |
FLAGGER | 20 | SD |
$200.00 |
$50.00 |
$4,800.00 |
$206.00 |
$400.00 |
$267.42 |
$400.00 |
$237.60 |
| 85 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$15,000.00 |
$14,789.00 |
$13,750.00 |
$13,905.00 |
$13,750.00 |
$28,126.91 |
$13,500.00 |
$14,580.00 |
| 86 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 270 | SD |
$12.40 |
$12.50 |
$10.40 |
$10.30 |
$10.25 |
$10.70 |
$10.00 |
$10.80 |
| 87 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$40,000.00 |
$15,266.00 |
$13,000.00 |
$12,257.00 |
$20,000.00 |
$25,087.00 |
$10,000.00 |
$21,222.00 |
| 88 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$3,365.00 |
$3,500.00 |
$5,150.00 |
$5,500.00 |
$6,418.00 |
$1,250.00 |
$8,100.00 |
| 89 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$190,000.00 |
$100,000.00 |
$140,913.08 |
$153,579.46 |
$206,066.09 |
$205,000.00 |
$230,000.00 |
$202,728.69 |