‹ Jul 2017 results
BRIDGE AND APPROACHES COUNTY ROAD (OLD SH-3): OVER EAST FORK ROCK CREEK TRIBUTARY , 4.2 MILES NORTHWEST OF SH -48 NEAR TUPELO . PROJECT LENGTH = 0.207 MILE
Let date Thursday, July 20, 2017
Contract 170221
J/P numbers 30012(04) District Division 3
County Coal
Highway
Limits BRIDGE AND APPROACHES COUNTY ROAD (OLD SH-3): OVER EAST FORK ROCK CREEK TRIBUTARY , 4.2 MILES NORTHWEST OF SH -48 NEAR TUPELO . PROJECT LENGTH = 0.207 MILE Project number STP-215D(026)CI
Bidders 9
# Contractor Total bid vs estimate vs low
EE Engineer's estimate $579,198
1
Treas Construction Inc Low bidder
$456,713
-21.1%
2
K & R BUILDERS, INC.
$484,995
-16.3%
+6.2%
3
Frontier Bridge, Inc.
$500,262
-13.6%
+9.5%
4
L & N BRIDGE, LLC
$521,077
-10.0%
+14.1%
5
HUB Construction, Inc.
$536,930
-7.3%
+17.6%
6
T. McDonald Construction, Inc.
$537,421
-7.2%
+17.7%
7
C3 Construction, Inc.
$545,954
-5.7%
+19.5%
8
RRY SERVICES LLC
$556,893
-3.9%
+21.9%
9
HASKELL LEMON CONSTRUCTION CO.
$642,263
+10.9%
+40.6%
Bid tab: unit prices 48 items ExcelCSV Print
Seq Bid code Description Qty Unit Estimate
#1 Treas Construct… #2 K & R BUILDERS,… #3 Frontier Bridge… #4 L & N BRIDGE, L… #5 HUB Constructio… #6 T. McDonald Con… #7 C3 Construction… #8 RRY SERVICES LLC
1 201(A) 0102
CLEARING AND GRUBBING 1 LSUM
$5,000.00
$13,125.00
$8,250.00
$28,875.00
$12,000.00
$8,000.00
$8,000.00
$4,900.88
$16,000.00
2 202(A) 0183
UNCLASSIFIED EXCAVATION 134 CY
$15.00
$6.82
$11.50
$6.82
$10.00
$12.50
$25.00
$9.10
$16.00
3 202(D) 0184
UNCLASSIFIED BORROW 2,334 CY
$12.00
$7.35
$10.50
$7.35
$16.00
$13.00
$9.00
$15.40
$15.00
4 205(A) 4229
TYPE A-SALVAGED TOPSOIL 1 LSUM
$6,000.00
$2,709.00
$6,500.00
$7,959.00
$2,500.00
$6,000.00
$3,000.00
$5,881.06
$10,000.00
5 221(C) 2801
TEMPORARY SILT FENCE 2,133 LF
$1.50
$1.54
$1.65
$1.54
$1.47
$3.50
$2.50
$2.06
$1.47
6 230(A) 2806
SOLID SLAB SODDING 1,764 SY
$4.00
$6.25
$7.00
$6.25
$5.95
$2.26
$7.50
$8.33
$5.95
7 233(A) 2817
VEGETATIVE MULCHING 0.64 AC
$800.00
$1,312.50
$200.00
$1,312.50
$1,250.00
$500.00
$5,000.00
$1,750.31
$1,250.00
8 241 2832
MOWING 3.5 AC
$200.00
$236.25
$50.00
$236.25
$225.00
$50.00
$200.00
$315.06
$100.00
9 303(A) 2100
AGGREGATE BASE TYPE A 246.48 CY
$75.00
$63.00
$62.80
$74.11
$50.00
$60.00
$45.00
$52.93
$75.00
10 402(E) 0225
TRAFFIC BOUND SURFACE COURSE TYPE E 91.1 TON
$40.00
$33.60
$34.00
$42.30
$30.00
$40.00
$46.00
$31.93
$45.00
11 407(B) 0250
TACK COAT 505.08 GAL
$5.00
$3.83
$4.00
$3.83
$3.65
$4.00
$4.60
$5.11
$3.65
12 409(A) 4242
FABRIC REINFORCEMENT 1,109.45 SY
$3.00
$2.88
$5.00
$4.46
$4.25
$5.00
$4.00
$5.95
$4.25
13 411(C) 5960
SUPERPAVE, TYPE S4(PG 64-22 OK) 606.75 TON
$120.00
$94.34
$100.00
$94.34
$89.85
$94.00
$95.00
$125.81
$90.00
14 412 5267
COLD MILLING PAVEMENT 800 SY
$12.00
$12.54
$13.50
$11.81
$11.81
$13.00
$9.00
$12.25
$15.00
15 509(D) 0325
CLASS C CONCRETE 50 CY
$600.00
$440.31
$307.50
$407.87
$400.00
$300.00
$400.00
$317.86
$350.00
16 613(B) 0689
18" CORR. GALV. STEEL PIPE 76 LF
$40.00
$31.50
$25.00
$40.84
$25.00
$25.24
$42.00
$35.01
$45.00
17 619(A) 0920
REMOVAL OF STRUCTURES & OBSTRUCTIONS 1 LSUM
$5,000.00
$3,150.00
$4,250.00
$5,250.00
$3,500.00
$5,517.25
$5,000.00
$3,500.63
$5,000.00
18 619(B) 4763
REMOVAL OF CONCRETE PAVEMENT W/ASPHALT OVERLAY 79 SY
$75.00
$10.50
$80.00
$73.50
$12.00
$32.10
$15.00
$70.01
$15.00
19 619(C) 0924
SAWING PAVEMENT 96 LF
$15.00
$10.50
$10.00
$10.50
$8.00
$3.00
$8.00
$4.20
$5.00
20 623(A) 0932
BEAM GUARDRAIL W-BEAM SINGLE 300 LF
$25.00
$17.85
$18.70
$17.85
$17.00
$19.08
$19.00
$28.01
$17.00
21 623(F) 5686
GUARDRAIL ANCHOR UNIT (TYPE D-BF) 4 EA
$2,500.00
$1,522.50
$1,600.00
$1,149.75
$1,450.00
$1,900.00
$1,250.00
$1,750.32
$1,450.00
22 623(F) 8300
GUARDRAIL TRAIL END TURNDOWN (31") 4 EA
$1,500.00
$525.00
$600.00
$1,086.75
$500.00
$12,000.00
$1,100.00
$1,050.19
$500.00
23 624(C) 4459
FENCE-STYLE SWF (5 BARBED WIRE) 284 LF
$10.00
$10.50
$12.00
$10.50
$10.00
$6.50
$6.00
$9.80
$10.00
24 501(B) 1307
SUBSTRUCTURE EXCAVATION COMMON 100 CY
$40.00
$26.25
$13.00
$21.00
$12.00
$18.50
$18.00
$14.00
$25.00
25 501(F) 6352
GRANULAR BACKFILL 46 CY
$60.00
$52.50
$77.00
$69.89
$85.00
$85.00
$75.00
$23.10
$85.00
26 503(A) 1311
PRESTRESSED CONCRETE BEAMS (TYPE II) 179 LF
$225.00
$192.69
$223.00
$216.07
$280.00
$220.00
$285.00
$229.64
$235.00
27 504(A) 1304
APPROACH SLAB 115 SY
$225.00
$199.56
$185.00
$197.19
$175.00
$185.00
$240.00
$224.91
$240.00
28 504(B) 1305
SAW-CUT GROOVING 236.7 SY
$7.00
$12.60
$8.80
$11.55
$11.00
$15.00
$6.00
$15.40
$11.00
29 504(D) 6239
CONCRETE RAIL (TR3) 172.6 LF
$90.00
$89.07
$85.00
$86.32
$90.00
$91.25
$80.00
$75.61
$120.00
30 506(A) 1322
STRUCTURAL STEEL 100 LB
$2.50
$2.19
$4.75
$3.22
$2.00
$3.10
$5.00
$6.65
$4.00
31 507(A) 6172
WEATHERING STEEL FIXED BEARING ASSEMBLY 6 EA
$1,500.00
$691.42
$450.00
$741.82
$400.00
$280.00
$350.00
$618.63
$700.00
32 509(A) 1326
CLASS AA CONCRETE 63.1 CY
$650.00
$725.60
$707.50
$681.56
$900.00
$615.00
$810.00
$588.11
$850.00
33 509(B) 1328
CLASS A CONCRETE 37 CY
$700.00
$667.40
$752.50
$675.96
$900.00
$615.00
$850.00
$646.92
$850.00
34 511(A) 1332
REINFORCING STEEL 16,950 LB
$1.05
$0.9700
$0.8800
$1.02
$1.00
$1.00
$1.00
$0.8400
$1.10
35 514(A) 6010
PILES, FURNISHED (HP 10X42) 375 LF
$50.00
$27.80
$35.00
$33.88
$30.00
$35.78
$55.00
$29.13
$40.00
36 514(B) 6292
PILES, DRIVEN (HP 10X42) 375 LF
$20.00
$15.75
$15.00
$10.50
$13.00
$10.00
$30.00
$56.01
$15.00
37 514(L) 6220
PILE SPLICE, H-PILE (NON-BIDDABLE) 1 EA
$400.00
$400.00
$400.00
$400.00
$400.00
$400.00
$400.00
$400.00
$400.00
38 601(B) 1353
TYPE I-A PLAIN RIPRAP 400 TON
$50.00
$15.75
$45.30
$45.10
$32.00
$40.69
$43.00
$42.36
$55.00
39 601(C) 1355
TYPE I-A FILTER BLANKET 70 TON
$50.00
$15.75
$36.00
$34.94
$26.00
$36.80
$35.00
$42.36
$40.00
40 613(H) 6204
6" PERFORATED PIPE UNDERDRAIN ROUND 52 LF
$25.00
$31.50
$30.00
$28.57
$30.00
$20.00
$40.00
$28.01
$35.00
41 613(I) 6207
6" NON-PERF.PIPE UNDERDRAIN RND. 50 LF
$30.00
$31.50
$30.00
$28.69
$20.00
$20.00
$40.00
$28.01
$35.00
42 619(D) 1397
REMOVAL OF EXISTING BRIDGE STRUCTURE 1 LSUM
$15,000.00
$12,600.00
$9,750.00
$6,825.00
$25,000.00
$37,000.00
$15,000.00
$14,002.53
$16,000.00
43 853 9033
DELINEATORS(TYPE 2, CODE 1) 12 EA
$40.00
$21.00
$20.00
$21.00
$20.00
$23.98
$20.00
$28.01
$15.00
44 854(A) 8800
TRAFFIC STRIPE(PAINT)(4" WIDE) 4,400 LF
$0.7000
$0.4200
$0.4500
$0.4200
$0.4000
$0.4000
$0.3000
$0.5600
$0.4000
45 880(J) 8905
CONSTRUCTION TRAFFIC CONTROL 1 LSUM
$4,000.00
$2,520.00
$3,000.00
$2,520.00
$2,400.00
$2,877.19
$7,000.00
$3,360.61
$2,400.00
46 642(B) 0096
CONSTRUCTION STAKING LEVEL II 1 LSUM
$15,000.00
$5,565.00
$6,100.00
$5,565.00
$6,000.00
$8,000.00
$10,000.00
$10,361.87
$8,150.00
47 220 2800
SWPPP DOCUMENTATION AND MANAGEMENT 1 LSUM
$10,000.00
$2,625.00
$3,000.00
$3,465.00
$2,000.00
$2,500.00
$5,000.00
$4,620.83
$1,275.00
48 641 1552
MOBILIZATION 1 LSUM
$60,000.00
$45,036.57
$43,500.00
$45,542.93
$50,000.00
$40,000.00
$50,000.00
$59,020.65
$53,000.00
Showing the first 8 bidders. The Excel and CSV downloads include all 9.