BRIDGE AND APPROACHES US -77: OVER THE CIMARRON RIVER , 2.7 MILES NORTH OF SH -33 NEAR GUTHRIE. PROJECT LENGTH = 0.610 MILE

Let date
Thursday, May 17, 2018
Contract
170125
J/P numbers
27103(04)
District
Division 4
County
Logan
Highway
Limits
BRIDGE AND APPROACHES US -77: OVER THE CIMARRON RIVER , 2.7 MILES NORTH OF SH -33 NEAR GUTHRIE. PROJECT LENGTH = 0.610 MILE
Project number
STP-242C(055)PM

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$6,073,393
1 FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. Low bidder $5,452,152 -10.2%
2 MANHATTAN ROAD & BRIDGE COMPANY, LLC $5,579,752 -8.1% +2.3%
3 Bridges, Inc. DBA Scudder Bridge Co. $5,648,595 -7.0% +3.6%
4 Cimarron Construction Company, LLC $5,695,144 -6.2% +4.5%
5 RRY SERVICES LLC $5,698,335 -6.2% +4.5%
6 K & R BUILDERS, INC. $5,770,066 -5.0% +5.8%
8 A. M. COHRON & SON, INC. $6,124,562 +0.8% +12.3%
9 SHERWOOD CONSTRUCTION CO., INC. $6,156,910 +1.4% +12.9%

Bid tab: unit prices 82 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 FRONTIER BRIDGE…#2 MANHATTAN ROAD …#3 Bridges, Inc. D…#4 Cimarron Constr…#5 RRY SERVICES LLC#6 K & R BUILDERS,…#8 A. M. COHRON & …#9 SHERWOOD CONSTR…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $12,000.00 $59,482.50 $60,000.00 $10,000.00 $125,000.00 $100,000.00 $23,500.00 $72,215.00 $36,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION33,566CY $5.00 $6.11 $5.25 $6.00 $8.15 $7.33 $6.05 $7.30 $5.20
3202(D) 0184 UNCLASSIFIED BORROW8,824CY $7.00 $5.82 $11.75 $12.00 $10.30 $9.25 $10.33 $9.25 $5.20
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $28,504.00 $19,698.00 $8,750.00 $14,500.00 $26,000.00 $23,450.00 $20,000.00 $23,450.00 $20,000.00
5221(C) 2801 TEMPORARY SILT FENCE4,595LF $1.00 $2.63 $5.00 $3.25 $2.75 $2.99 $2.75 $2.99 $4.20
6221(F) 0100 TEMPORARY SILT DIKE140LF $1.00 $15.75 $50.00 $19.50 $16.00 $18.95 $16.50 $18.95 $9.10
7230(A) 2806 SOLID SLAB SODDING29,319SY $1.40 $2.63 $2.50 $2.49 $2.75 $2.49 $2.75 $2.49 $3.10
8232(A) 2813 SEEDING METHOD A8.04AC $600.00 $1,837.50 $1,000.00 $995.00 $1,750.00 $995.00 $1,925.00 $995.00 $2,200.00
9233(A) 2817 VEGETATIVE MULCHING7.2AC $225.00 $1,050.00 $1,210.00 $1,200.00 $1,000.00 $1,200.00 $1,100.00 $1,200.00 $1,200.00
10233(D) 2820 WOOD CELLULOSE FIBER0.84AC $1,500.00 $2,100.00 $3,000.00 $2,950.00 $2,000.00 $2,950.00 $2,200.00 $2,950.00 $2,500.00
11241 2832 MOWING27.42AC $1.00 $105.00 $200.00 $199.00 $100.00 $199.00 $110.00 $199.00 $120.00
12303(A) 2200 (SP)AGGREGATE BASE TYPE A, PLANT MIXED2,506CY $52.00 $73.50 $76.00 $70.00 $78.00 $70.00 $77.00 $70.00 $78.00
13307(K) 4300 STABILIZED SUBGRADE12,335SY $2.50 $5.51 $5.50 $6.00 $5.75 $5.25 $5.95 $5.25 $6.00
14325 5271 SEPARATOR FABRIC12,845SY $1.50 $1.91 $1.00 $1.25 $1.40 $1.25 $1.40 $1.25 $1.10
15402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,487TON $27.00 $36.22 $33.00 $38.00 $42.35 $38.00 $42.10 $38.00 $40.00
16407(B) 0250 TACK COAT1,535GAL $4.50 $3.78 $2.55 $3.60 $4.00 $2.37 $2.60 $3.60 $3.10
17408 5774 PRIME COAT7,469GAL $6.25 $5.78 $2.55 $5.50 $6.00 $3.69 $4.06 $5.50 $4.70
18411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)3,364TON $78.00 $79.80 $75.50 $76.00 $84.75 $68.32 $75.32 $76.00 $88.00
19411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,228TON $85.00 $87.15 $87.00 $83.00 $92.50 $85.49 $94.50 $83.00 $110.00
20509(D) 0325 CLASS C CONCRETE212CY $370.00 $318.86 $191.00 $325.00 $320.00 $325.00 $312.50 $375.00 $320.00
21619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $15,000.00 $7,245.00 $17,500.00 $10,000.00 $4,750.00 $4,250.00 $9,400.00 $4,250.00 $16,000.00
22619(B) 4728 REMOVAL OF ASPHALT PAVEMENT557SY $3.60 $4.20 $3.50 $5.00 $5.65 $7.00 $25.00 $15.00 $4.00
23619(B) 4763 REMOVAL OF CONCRETE PAVEMENT W/ASPHALT OVERLAY6,342SY $5.00 $3.15 $4.50 $5.00 $7.50 $7.00 $14.50 $13.50 $6.20
24619(B) 4780 REMOVAL OF GUARDRAIL654LF $3.60 $3.52 $3.00 $3.35 $3.35 $3.35 $4.45 $3.35 $3.50
25619(C) 0924 SAWING PAVEMENT48LF $3.50 $10.50 $12.50 $15.00 $6.00 $10.00 $12.00 $10.00 $5.00
26623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE525LF $16.50 $17.51 $19.00 $16.68 $21.00 $16.68 $24.00 $16.68 $22.00
27623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,150.00 $2,572.50 $2,375.00 $2,450.00 $2,635.00 $2,450.00 $3,000.00 $2,450.00 $3,200.00
28623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $1,300.00 $2,310.00 $1,750.00 $2,200.00 $1,925.00 $2,200.00 $2,150.00 $2,200.00 $2,900.00
29624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)1,559LF $5.25 $4.31 $4.15 $4.10 $4.55 $4.10 $4.75 $4.05 $5.50
30853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)17EA $10.00 $13.91 $15.25 $13.25 $16.75 $13.25 $12.00 $13.25 $18.00
31501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON220CY $20.00 $14.14 $45.00 $22.00 $21.00 $15.00 $14.00 $23.00 $14.00
32501(G) 6309 CLSM BACKFILL174CY $140.00 $146.45 $130.00 $140.00 $138.00 $150.00 $141.50 $168.00 $180.00
33503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)3,786.67LF $230.00 $227.94 $216.87 $280.00 $230.00 $240.00 $214.50 $260.00 $230.00
34504(A) 1304 APPROACH SLAB335SY $185.00 $195.82 $185.00 $150.00 $183.00 $230.00 $198.00 $165.00 $240.00
35504(B) 1305 SAW-CUT GROOVING4,533SY $5.00 $3.93 $3.75 $4.50 $4.25 $3.80 $4.18 $3.80 $4.60
36504(C) 6250 SEALED EXPANSION JOINT123LF $325.00 $229.44 $195.00 $225.00 $325.00 $260.00 $295.00 $310.00 $170.00
37504(D) 6245 CONCRETE RAIL (TR4)2,039.2LF $100.00 $72.72 $59.00 $73.00 $89.00 $75.00 $86.50 $82.00 $94.00
38506(A) 1322 STRUCTURAL STEEL5,500LB $4.00 $3.03 $2.50 $3.50 $3.50 $3.40 $2.20 $3.20 $1.90
39507(A) 6170 STAINLESS STEEL FIXED BEARING ASSEMBLY24EA $2,000.00 $1,363.50 $2,550.00 $1,450.00 $1,525.00 $1,400.00 $1,450.00 $1,650.00 $1,500.00
40507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY56EA $2,200.00 $1,262.50 $2,550.00 $1,450.00 $1,550.00 $1,400.00 $1,350.00 $1,450.00 $1,500.00
41509(A) 1326 CLASS AA CONCRETE1,098.2CY $600.00 $510.05 $535.00 $450.00 $580.00 $565.00 $547.00 $705.00 $760.00
42509(B) 1328 CLASS A CONCRETE740.4CY $625.00 $510.05 $555.00 $550.00 $580.00 $600.00 $592.00 $430.00 $740.00
43509(D) 1331 CLASS C CONCRETE10.1CY $500.00 $353.50 $750.00 $525.00 $425.00 $350.00 $600.00 $890.00 $710.00
44511(A) 1332 REINFORCING STEEL6,050LB $1.00 $1.01 $1.55 $1.80 $1.00 $1.00 $1.40 $1.54 $1.00
45511(B) 6010 EPOXY COATED REINFORCING STEEL412,540LB $1.10 $1.11 $1.05 $1.05 $1.05 $1.10 $1.01 $1.05 $1.10
46513(A) 6018 CLASS A BRIDGE DECK REPAIR50SY $200.00 $202.00 $200.00 $285.00 $220.00 $225.00 $200.00 $350.00 $340.00
47513(B) 6019 CLASS B BRIDGE DECK REPAIR50SY $500.00 $454.50 $200.00 $435.00 $400.00 $515.00 $350.00 $350.00 $390.00
48513(C) 6020 CLASS C BRIDGE DECK REPAIR50SY $700.00 $631.25 $255.00 $550.00 $650.00 $685.00 $500.00 $550.00 $460.00
49514(A) 6010 PILES, FURNISHED (HP 10X42)194LF $40.00 $33.26 $45.00 $44.00 $38.00 $35.00 $35.00 $34.00 $31.00
50514(A) 6011 PILES, FURNISHED (HP 12X53)624LF $40.00 $33.74 $55.00 $54.00 $45.00 $45.00 $37.10 $42.00 $39.00
51514(B) 6292 PILES, DRIVEN (HP 10X42)194LF $20.00 $14.14 $10.00 $10.00 $20.00 $10.00 $15.00 $5.85 $33.00
52514(B) 6294 PILES, DRIVEN (HP 12X53)624LF $20.00 $12.12 $10.00 $11.00 $22.00 $10.00 $15.90 $5.85 $32.00
53514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
54515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)4,436SY $4.00 $3.39 $3.25 $3.65 $4.00 $3.65 $4.00 $3.65 $3.90
55516(A) 6096 DRILLED SHAFTS 60" DIAMETER224LF $600.00 $815.92 $900.00 $925.00 $715.00 $675.00 $877.00 $700.00 $810.00
56516(A) 6098 DRILLED SHAFTS 72" DIAMETER574LF $800.00 $981.45 $1,255.00 $1,200.00 $940.00 $850.00 $1,172.00 $975.00 $1,100.00
57516(C) 6200 CROSSHOLE SONIC LOGGING2EA $1,750.00 $2,474.50 $1,825.00 $3,000.00 $1,800.00 $3,500.00 $3,100.00 $1,500.00 $20,000.00
58523(A) 6550 SEALER CRACK PREPARATION192LF $5.00 $4.80 $4.05 $4.00 $4.45 $4.00 $4.40 $4.00 $4.90
59523(B) 6560 SEALER RESIN2.35GAL $200.00 $202.00 $155.00 $150.00 $165.00 $150.00 $165.00 $150.00 $180.00
60601(B) 1353 TYPE I-A PLAIN RIPRAP1,140TON $50.00 $51.51 $55.00 $58.00 $54.50 $60.00 $62.25 $64.00 $55.00
61601(C) 1355 TYPE I-A FILTER BLANKET200TON $40.00 $41.41 $42.00 $44.00 $43.00 $50.00 $44.10 $51.00 $46.00
62613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND98LF $50.00 $30.30 $21.00 $23.00 $18.00 $30.00 $30.00 $32.00 $27.00
63613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.74LF $30.00 $25.25 $21.00 $23.00 $18.00 $30.00 $30.00 $32.00 $11.00
64619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $60,000.00 $136,350.00 $65,000.00 $120,000.00 $164,000.00 $225,000.00 $175,000.00 $180,000.00 $110,000.00
65857(E) 8890 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-2375EA $0.5000 $1.03 $2.10 $1.00 $2.25 $1.00 $2.50 $1.00 $1.30
66876(A) 8482 (PL)TRUCK MOUNTED ATTENUATOR320SD $15.00 $5.15 $5.05 $5.00 $22.00 $5.00 $5.50 $5.00 $6.40
67880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF56,000SD $0.3000 $0.0200 $0.1000 $0.0200 $0.3000 $0.0200 $0.0600 $0.0200 $0.0500
68880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF4,160SD $0.6000 $0.0200 $0.2500 $0.0200 $0.5500 $0.0200 $0.2500 $0.0200 $0.0500
69880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF3,840SD $1.15 $0.0500 $0.5500 $0.0500 $0.8500 $0.0500 $0.5500 $0.0500 $0.0500
70880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)3,840SD $0.7500 $0.0500 $2.55 $0.0500 $1.10 $0.0500 $3.00 $0.0500 $0.0500
71880(C) 8848 WING BARRICADES1,280SD $1.30 $0.4100 $0.5500 $0.4000 $0.8500 $0.4000 $0.7500 $0.4000 $0.5000
72880(E) 8860 WARNING LIGHTS(TYPE A)10,880SD $0.3000 $0.0200 $0.3000 $0.0200 $0.1000 $0.0200 $0.3000 $0.0200 $0.0500
73880(F) 8878 DRUMS3,200SD $0.2000 $1.80 $0.5500 $1.75 $0.8500 $1.75 $0.5500 $1.75 $2.30
74880(G) 8890 CHANNELIZER CONES3,200SD $0.2500 $1.80 $0.5500 $1.75 $0.5500 $1.75 $0.5500 $1.75 $2.30
75882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN668SD $11.00 $18.54 $10.05 $18.00 $11.15 $18.00 $12.00 $18.00 $23.00
76805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS12EA $60.00 $77.25 $101.00 $75.00 $55.75 $75.00 $110.00 $75.00 $97.00
77850(A) 8110 SHEET ALUMINUM SIGNS42SF $15.00 $29.87 $21.00 $29.00 $33.00 $29.00 $22.00 $29.00 $38.00
78851(C) 8330 2 1/2" SQUARE TUBE POST111.5LF $8.00 $6.18 $10.10 $6.00 $14.00 $6.00 $11.00 $6.00 $7.70
79856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)15,200LF $0.7000 $0.6900 $0.7000 $0.6700 $0.8000 $0.6700 $0.7200 $0.6700 $0.8500
80642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $40,000.00 $22,145.00 $27,000.00 $17,320.00 $20,500.00 $18,784.00 $22,500.00 $21,500.00 $41,000.00
81220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $5,150.00 $1,775.00 $6,500.00 $8,000.00 $1,275.00 $30,000.00 $20,000.00 $3,100.00
82641 1399 MOBILIZATION1LSUM $275,000.00 $283,182.06 $288,440.33 $205,000.00 $75,000.00 $273,000.00 $248,000.00 $490,000.00 $280,000.00