| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$63,407.80 |
$5,325.00 |
$15,400.00 |
$15,000.00 |
$4,500.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 6,865 | CY |
$20.00 |
$4.04 |
$7.46 |
$8.75 |
$18.00 |
$15.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 7,437 | CY |
$18.00 |
$5.05 |
$8.52 |
$11.50 |
$18.00 |
$15.00 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$8,500.00 |
$3,030.00 |
$3,195.00 |
$3,550.00 |
$17,000.00 |
$7,500.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 400 | LF |
$3.00 |
$2.98 |
$3.14 |
$2.00 |
$2.00 |
$1.55 |
| 6 | 221(D) 2803 |
TEMPORARY SEDIMENT FILTER | 2 | EA |
$350.00 |
$186.85 |
$197.03 |
$60.00 |
$115.00 |
$100.00 |
| 7 | 221(F) 0100 |
TEMPORARY SILT DIKE | 112 | LF |
$10.00 |
$13.08 |
$13.79 |
$7.50 |
$8.00 |
$7.00 |
| 8 | 230(A) 2806 |
SOLID SLAB SODDING | 12,149 | SY |
$2.00 |
$1.51 |
$1.59 |
$1.80 |
$1.50 |
$1.15 |
| 9 | 230(F) 2812 |
WATERING | 486 | KGAL |
$6.00 |
$6.01 |
$6.34 |
$3.05 |
$12.00 |
$10.00 |
| 10 | 233(A) 2817 |
VEGETATIVE MULCHING | 3 | AC |
$375.00 |
$99.99 |
$105.44 |
$455.00 |
$115.00 |
$100.00 |
| 11 | 234(A) 2824 |
FERTILIZING (10-20-10) | 1 | TON |
$820.00 |
$701.95 |
$740.18 |
$555.00 |
$575.00 |
$500.00 |
| 12 | 241 2832 |
MOWING | 5 | AC |
$120.00 |
$196.95 |
$207.68 |
$88.00 |
$115.00 |
$100.00 |
| 13 | 307(K) 4300 |
STABILIZED SUBGRADE | 17,516 | SY |
$8.00 |
$5.81 |
$6.12 |
$5.25 |
$7.00 |
$15.00 |
| 14 | 407(B) 0250 |
TACK COAT | 3,158 | GAL |
$3.50 |
$6.39 |
$3.00 |
$4.30 |
$5.00 |
$4.25 |
| 15 | 408 5774 |
PRIME COAT | 6,131 | GAL |
$4.50 |
$1.01 |
$7.00 |
$4.25 |
$5.00 |
$4.25 |
| 16 | 411(B) 5935 |
SUPERPAVE, TYPE S3(PG 76-28 OK) | 2,962 | TON |
$85.00 |
$98.73 |
$95.00 |
$99.00 |
$112.00 |
$97.75 |
| 17 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 3,854 | TON |
$90.00 |
$75.75 |
$75.00 |
$77.00 |
$86.00 |
$75.00 |
| 18 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 1,934 | TON |
$110.00 |
$116.15 |
$105.00 |
$116.00 |
$135.00 |
$115.00 |
| 19 | 412 5267 |
COLD MILLING PAVEMENT | 2,110 | SY |
$10.00 |
$8.08 |
$2.66 |
$8.35 |
$10.00 |
$8.00 |
| 20 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 6,519 | LF |
$0.7500 |
$0.7100 |
$0.4200 |
$0.5000 |
$0.8000 |
$0.6600 |
| 21 | 613(B) 0690 |
24" CORR. GALV. STEEL PIPE | 702 | LF |
$30.00 |
$25.09 |
$25.52 |
$25.00 |
$36.00 |
$31.00 |
| 22 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$10,000.00 |
$1,515.00 |
$9,052.50 |
$7,225.00 |
$20,000.00 |
$8,500.00 |
| 23 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 13,308 | SY |
$7.25 |
$4.80 |
$3.20 |
$5.30 |
$6.00 |
$5.25 |
| 24 | 619(B) 5190 |
REMOVAL OF CABLE BARRIER | 3,220 | LF |
$6.50 |
$25.00 |
$13.26 |
$16.00 |
$30.00 |
$24.75 |
| 25 | 619(C) 0924 |
SAWING PAVEMENT | 13,552 | LF |
$3.50 |
$4.04 |
$3.50 |
$3.50 |
$4.50 |
$3.00 |
| 26 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 100 | LF |
$20.00 |
$22.73 |
$19.38 |
$14.00 |
$23.00 |
$20.00 |
| 27 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 8 | EA |
$1,800.00 |
$1,560.45 |
$1,640.10 |
$3,250.00 |
$2,300.00 |
$1,950.00 |
| 28 | 501(G) 6309 |
CLSM BACKFILL | 111 | CY |
$200.00 |
$135.30 |
$137.30 |
$130.00 |
$150.00 |
$300.00 |
| 29 | 502 6116 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$30,000.00 |
$20,800.00 |
$31,950.00 |
$30,000.00 |
$70,000.00 |
$30,000.00 |
| 30 | 504(A) 1304 |
APPROACH SLAB | 356.7 | SY |
$205.00 |
$182.08 |
$212.00 |
$155.00 |
$140.00 |
$275.00 |
| 31 | 504(B) 1305 |
SAW-CUT GROOVING | 1,438.5 | SY |
$5.00 |
$4.21 |
$4.31 |
$4.20 |
$5.00 |
$4.05 |
| 32 | 504(C) 6250 |
SEALED EXPANSION JOINT | 116 | LF |
$290.00 |
$236.29 |
$165.00 |
$185.00 |
$250.00 |
$350.00 |
| 33 | 504(E) 6190 |
42" F-SHAPED PARAPET | 699.9 | LF |
$85.00 |
$84.09 |
$77.73 |
$65.00 |
$105.00 |
$200.00 |
| 34 | 506(A) 1322 |
STRUCTURAL STEEL | 5,170 | LB |
$4.00 |
$4.07 |
$5.03 |
$9.00 |
$4.00 |
$8.00 |
| 35 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 6 | EA |
$850.00 |
$989.25 |
$1,236.15 |
$1,520.00 |
$1,100.00 |
$1,300.00 |
| 36 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 18 | EA |
$1,000.00 |
$989.25 |
$1,236.15 |
$1,520.00 |
$1,100.00 |
$1,300.00 |
| 37 | 509 6152 |
SPECIAL CONCRETE FINISH | 62 | SY |
$125.00 |
$72.80 |
$103.43 |
$200.00 |
$26.00 |
$104.00 |
| 38 | 509(A) 1326 |
CLASS AA CONCRETE | 283.1 | CY |
$600.00 |
$630.24 |
$700.00 |
$875.00 |
$1,000.00 |
$1,000.00 |
| 39 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 87,150 | LB |
$1.10 |
$1.02 |
$1.15 |
$1.20 |
$1.10 |
$1.50 |
| 40 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$50,000.00 |
$45,597.00 |
$46,693.08 |
$50,000.00 |
$55,000.00 |
$43,850.00 |
| 41 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$10,000.00 |
$3,650.40 |
$3,738.15 |
$500.00 |
$4,000.00 |
$3,510.00 |
| 42 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 583 | SY |
$5.00 |
$3.80 |
$3.89 |
$3.75 |
$4.20 |
$3.65 |
| 43 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 61.2 | LF |
$35.00 |
$35.05 |
$35.89 |
$35.00 |
$38.00 |
$35.50 |
| 44 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 8 | GAL |
$85.00 |
$52.00 |
$53.25 |
$52.00 |
$540.00 |
$100.00 |
| 45 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 11.5 | SY |
$800.00 |
$794.56 |
$813.66 |
$775.00 |
$850.00 |
$675.00 |
| 46 | 523(A) 6550 |
SEALER CRACK PREPARATION | 226.3 | LF |
$4.00 |
$4.16 |
$4.26 |
$4.10 |
$5.00 |
$4.00 |
| 47 | 523(B) 6560 |
SEALER RESIN | 2.5 | GAL |
$100.00 |
$156.00 |
$159.75 |
$155.00 |
$175.00 |
$150.00 |
| 48 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 12 | EA |
$500.00 |
$324.48 |
$332.28 |
$500.00 |
$360.00 |
$2,500.00 |
| 49 | 545 4815 |
(PL)REPLACE BRIDGE ITEM (TYPE A) | 24 | EA |
$1,600.00 |
$2,020.20 |
$394.98 |
$2,025.00 |
$1,200.00 |
$600.00 |
| 50 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$125,000.00 |
$78,069.68 |
$49,352.81 |
$97,000.00 |
$130,000.00 |
$215,000.00 |
| 51 | 501(G) 6309 |
CLSM BACKFILL | 111 | CY |
$200.00 |
$135.30 |
$137.30 |
$130.00 |
$150.00 |
$300.00 |
| 52 | 502 6116 |
(PL)FALSEWORK JACKING | 1 | LSUM |
$30,000.00 |
$23,556.00 |
$31,950.00 |
$30,000.00 |
$70,000.00 |
$30,000.00 |
| 53 | 504(A) 1304 |
APPROACH SLAB | 357.6 | SY |
$205.00 |
$182.08 |
$212.00 |
$155.00 |
$140.00 |
$275.00 |
| 54 | 504(B) 1305 |
SAW-CUT GROOVING | 1,441.5 | SY |
$5.00 |
$4.21 |
$4.31 |
$4.20 |
$5.00 |
$4.05 |
| 55 | 504(C) 6250 |
SEALED EXPANSION JOINT | 116.2 | LF |
$290.00 |
$236.29 |
$165.00 |
$185.00 |
$250.00 |
$350.00 |
| 56 | 504(E) 6190 |
42" F-SHAPED PARAPET | 699.9 | LF |
$85.00 |
$84.09 |
$77.73 |
$65.00 |
$105.00 |
$200.00 |
| 57 | 506(A) 1322 |
STRUCTURAL STEEL | 5,170 | LB |
$4.00 |
$4.18 |
$5.03 |
$9.00 |
$4.00 |
$8.00 |
| 58 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 6 | EA |
$850.00 |
$989.25 |
$1,236.15 |
$1,520.00 |
$1,100.00 |
$1,300.00 |
| 59 | 507(B) 6176 |
WEATHERING STEEL EXPANSION BEARING ASSEMBLY | 18 | EA |
$1,000.00 |
$1,015.25 |
$1,236.15 |
$1,520.00 |
$1,100.00 |
$1,300.00 |
| 60 | 509 6152 |
SPECIAL CONCRETE FINISH | 67 | SY |
$125.00 |
$72.80 |
$103.43 |
$200.00 |
$26.00 |
$104.00 |
| 61 | 509(A) 1326 |
CLASS AA CONCRETE | 282.9 | CY |
$600.00 |
$630.24 |
$700.00 |
$875.00 |
$1,000.00 |
$1,000.00 |
| 62 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 87,250 | LB |
$1.10 |
$1.02 |
$1.20 |
$1.20 |
$1.10 |
$1.50 |
| 63 | 512(A) 1323 |
PAINTING EXISTING STRUCTURES | 1 | LSUM |
$50,000.00 |
$45,597.00 |
$46,693.08 |
$50,000.00 |
$55,000.00 |
$43,850.00 |
| 64 | 512(B) 6303 |
COLLECTION AND HANDLING OF WASTE | 1 | LSUM |
$10,000.00 |
$3,650.40 |
$3,738.15 |
$500.00 |
$4,000.00 |
$3,510.00 |
| 65 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 584 | SY |
$5.00 |
$3.80 |
$3.89 |
$3.75 |
$4.20 |
$3.65 |
| 66 | 520(A) 6058 |
PREPARATION OF CRACKS, ABOVE WATER | 54.2 | LF |
$35.00 |
$35.05 |
$35.89 |
$35.00 |
$38.00 |
$35.50 |
| 67 | 520(C) 6060 |
EPOXY RESIN, ABOVE WATER | 7 | GAL |
$85.00 |
$52.00 |
$53.25 |
$52.00 |
$540.00 |
$100.00 |
| 68 | 521(A) 6210 |
PNEUMATICALLY PLACED MORTAR | 3 | SY |
$800.00 |
$794.56 |
$813.66 |
$775.00 |
$850.00 |
$675.00 |
| 69 | 523(A) 6550 |
SEALER CRACK PREPARATION | 226.2 | LF |
$4.00 |
$4.16 |
$4.26 |
$4.10 |
$5.00 |
$4.00 |
| 70 | 523(B) 6560 |
SEALER RESIN | 2.5 | GAL |
$100.00 |
$156.00 |
$159.75 |
$155.00 |
$175.00 |
$150.00 |
| 71 | 540 4515 |
(PL)REPAIR BRIDGE ITEM (TYPE A) | 12 | EA |
$500.00 |
$324.48 |
$332.28 |
$500.00 |
$360.00 |
$2,500.00 |
| 72 | 545 4815 |
(PL)REPLACE BRIDGE ITEM (TYPE A) | 24 | EA |
$1,600.00 |
$2,020.20 |
$394.98 |
$2,025.00 |
$1,200.00 |
$600.00 |
| 73 | 619(B) 2500 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$125,000.00 |
$78,069.68 |
$49,352.81 |
$120,000.00 |
$130,000.00 |
$215,000.00 |
| 74 | 853 9024 |
DELINEATORS(TYPE 1, CODE 1) | 5 | EA |
$20.00 |
$25.25 |
$10.65 |
$14.50 |
$28.00 |
$25.00 |
| 75 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 20,683 | LF |
$0.7500 |
$0.3500 |
$0.3700 |
$0.6000 |
$0.4000 |
$0.3500 |
| 76 | 857(E) 8890 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-2 | 11,775 | EA |
$0.7500 |
$0.4000 |
$0.5300 |
$0.5400 |
$0.4500 |
$0.4000 |
| 77 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 19,325 | LF |
$0.2000 |
$0.2000 |
$0.1100 |
$0.5100 |
$0.2500 |
$0.2000 |
| 78 | 871(B) 8705 |
(SP)CONST.ZONE IMPACT ATTEN. | 360 | SD |
$10.00 |
$5.05 |
$5.33 |
$10.00 |
$6.00 |
$5.00 |
| 79 | 877(B) 8484 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 4,565 | LF |
$25.00 |
$8.08 |
$25.00 |
$25.00 |
$32.00 |
$28.00 |
| 80 | 877(C) 8486 |
RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 7,454 | LF |
$6.00 |
$3.03 |
$3.00 |
$4.00 |
$1.15 |
$1.00 |
| 81 | 880(A) 8800 |
ARROW DISPLAY(TYPE A) | 390 | SD |
$6.00 |
$2.02 |
$15.98 |
$8.25 |
$3.00 |
$2.00 |
| 82 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 5,100 | SD |
$0.2500 |
$1.01 |
$0.3700 |
$1.55 |
$1.30 |
$1.00 |
| 83 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 2,280 | SD |
$0.7500 |
$3.03 |
$2.13 |
$1.55 |
$6.00 |
$3.00 |
| 84 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 6,180 | SD |
$1.00 |
$1.01 |
$2.13 |
$1.55 |
$2.30 |
$1.00 |
| 85 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 2,700 | SD |
$1.00 |
$0.1000 |
$0.5300 |
$0.2600 |
$0.1500 |
$0.1000 |
| 86 | 880(C) 8848 |
WING BARRICADES | 960 | SD |
$1.00 |
$2.02 |
$3.20 |
$0.1600 |
$2.30 |
$2.00 |
| 87 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 11,580 | SD |
$0.2500 |
$0.1000 |
$0.1100 |
$0.2700 |
$0.1500 |
$0.1000 |
| 88 | 880(F) 8878 |
DRUMS | 20,790 | SD |
$0.2500 |
$0.1500 |
$0.2700 |
$0.6200 |
$0.2000 |
$0.1500 |
| 89 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 480 | SD |
$15.00 |
$10.10 |
$24.50 |
$12.00 |
$12.00 |
$10.00 |
| 90 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$15,000.00 |
$12,827.00 |
$13,179.38 |
$12,400.00 |
$15,000.00 |
$10,000.00 |
| 91 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$5,302.50 |
$623.98 |
$1,950.00 |
$2,500.00 |
$2,500.00 |
| 92 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$200,000.00 |
$155,851.34 |
$128,000.00 |
$200,069.00 |
$225,000.00 |
$295,000.00 |