| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$30,000.00 |
$16,350.00 |
$43,650.00 |
$100,000.00 |
$27,500.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 11,787 | CY |
$7.00 |
$4.36 |
$5.25 |
$8.00 |
$8.80 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 131,348 | CY |
$8.00 |
$5.72 |
$7.30 |
$8.00 |
$10.50 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$20,000.00 |
$37,382.64 |
$65,000.00 |
$50,000.00 |
$24,800.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 5,747 | LF |
$2.00 |
$1.30 |
$1.32 |
$1.30 |
$1.30 |
| 6 | 221(F) 0100 |
TEMPORARY SILT DIKE | 70 | LF |
$8.00 |
$8.70 |
$8.00 |
$8.75 |
$15.50 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 47,065 | SY |
$1.50 |
$1.19 |
$1.20 |
$1.19 |
$1.30 |
| 8 | 232(B) 2814 |
SEEDING METHOD B | 8.5 | AC |
$500.00 |
$422.92 |
$388.00 |
$425.00 |
$330.00 |
| 9 | 233(A) 2817 |
VEGETATIVE MULCHING | 8.5 | AC |
$500.00 |
$422.92 |
$388.00 |
$425.00 |
$385.00 |
| 10 | 241 2832 |
MOWING | 17 | AC |
$85.00 |
$97.01 |
$89.00 |
$100.00 |
$99.00 |
| 11 | 307(K) 4300 |
STABILIZED SUBGRADE | 10,694 | SY |
$9.00 |
$6.27 |
$6.55 |
$7.50 |
$7.90 |
| 12 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 77 | TON |
$40.00 |
$31.08 |
$35.00 |
$35.00 |
$38.50 |
| 13 | 407(B) 0250 |
TACK COAT | 3,315 | GAL |
$4.00 |
$3.79 |
$3.83 |
$3.80 |
$2.82 |
| 14 | 408 5774 |
PRIME COAT | 4,086 | GAL |
$7.00 |
$8.45 |
$8.53 |
$8.50 |
$7.60 |
| 15 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 7,116 | TON |
$82.00 |
$68.29 |
$68.92 |
$67.00 |
$78.50 |
| 16 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 1,492 | TON |
$90.00 |
$75.16 |
$75.85 |
$76.00 |
$90.00 |
| 17 | 412 5267 |
COLD MILLING PAVEMENT | 667 | SY |
$9.00 |
$11.48 |
$13.95 |
$11.50 |
$19.50 |
| 18 | 509(D) 0325 |
CLASS C CONCRETE | 76 | CY |
$350.00 |
$357.92 |
$360.00 |
$450.00 |
$509.00 |
| 19 | 609(A) 5864 |
CONCRETE CURB (6" BARRIER-DOWELLED) | 140 | LF |
$15.00 |
$21.80 |
$29.93 |
$25.00 |
$22.00 |
| 20 | 613(A) 0491 |
18" R.C.PIPE CLASS III | 124 | LF |
$50.00 |
$52.32 |
$40.00 |
$35.00 |
$46.00 |
| 21 | 613(M) 7196 |
TYPE A6 CULVERT END TREATMENT | 4 | EA |
$1,320.00 |
$1,311.72 |
$1,400.00 |
$1,500.00 |
$2,500.00 |
| 22 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$20,000.00 |
$9,265.00 |
$14,500.00 |
$15,000.00 |
$6,600.00 |
| 23 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 8,418 | SY |
$3.00 |
$4.36 |
$4.30 |
$3.00 |
$14.50 |
| 24 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 2,743 | LF |
$5.00 |
$4.36 |
$4.00 |
$3.00 |
$2.80 |
| 25 | 619(C) 0924 |
SAWING PAVEMENT | 375 | LF |
$5.00 |
$6.54 |
$5.50 |
$5.00 |
$5.50 |
| 26 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 2,076 | LF |
$20.00 |
$16.90 |
$18.35 |
$20.50 |
$17.00 |
| 27 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$2,400.00 |
$2,234.50 |
$2,255.00 |
$2,155.00 |
$2,260.00 |
| 28 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,000.00 |
$1,689.50 |
$1,900.00 |
$2,025.00 |
$1,710.00 |
| 29 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 4,214 | LF |
$6.00 |
$3.82 |
$5.00 |
$3.85 |
$3.90 |
| 30 | 624(D) 4470 |
GATE, GALVANIZED STEEL | 2 | EA |
$850.00 |
$872.00 |
$825.00 |
$880.00 |
$880.00 |
| 31 | 629(E) 5048 |
REMOVE AND RESET MAILBOX | 1 | EA |
$110.00 |
$272.50 |
$175.00 |
$150.00 |
$27.50 |
| 32 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 210 | CY |
$22.00 |
$18.70 |
$9.80 |
$15.00 |
$19.50 |
| 33 | 501(G) 6309 |
CLSM BACKFILL | 306 | CY |
$135.00 |
$135.64 |
$157.00 |
$150.00 |
$235.00 |
| 34 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 1,491 | LF |
$240.00 |
$251.15 |
$227.00 |
$220.00 |
$237.00 |
| 35 | 504(A) 1304 |
APPROACH SLAB | 318.6 | SY |
$185.00 |
$195.55 |
$202.50 |
$200.00 |
$218.00 |
| 36 | 504(B) 1305 |
SAW-CUT GROOVING | 1,644.4 | SY |
$4.50 |
$3.85 |
$4.30 |
$4.25 |
$3.90 |
| 37 | 504(C) 6250 |
SEALED EXPANSION JOINT | 44.4 | LF |
$350.00 |
$409.78 |
$283.00 |
$262.00 |
$303.00 |
| 38 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 739.7 | LF |
$85.00 |
$84.86 |
$89.50 |
$80.00 |
$114.00 |
| 39 | 506(A) 1322 |
STRUCTURAL STEEL | 1,550 | LB |
$4.00 |
$2.65 |
$3.00 |
$2.00 |
$6.30 |
| 40 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 10 | EA |
$2,200.00 |
$1,661.94 |
$1,550.00 |
$1,650.00 |
$1,850.00 |
| 41 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 20 | EA |
$2,200.00 |
$1,606.94 |
$1,550.00 |
$1,650.00 |
$1,850.00 |
| 42 | 509(A) 1326 |
CLASS AA CONCRETE | 358.4 | CY |
$550.00 |
$596.98 |
$615.00 |
$600.00 |
$575.00 |
| 43 | 509(B) 1328 |
CLASS A CONCRETE | 221.7 | CY |
$600.00 |
$588.78 |
$622.50 |
$600.00 |
$797.00 |
| 44 | 510(C) 6138 |
SLOPE WALL (5") | 1,751 | SY |
$130.00 |
$85.88 |
$120.00 |
$120.00 |
$83.50 |
| 45 | 511(A) 1332 |
REINFORCING STEEL | 1,760 | LB |
$1.00 |
$1.30 |
$1.20 |
$1.00 |
$1.80 |
| 46 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 111,410 | LB |
$1.10 |
$1.11 |
$1.03 |
$1.00 |
$1.20 |
| 47 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 708 | LF |
$40.00 |
$44.69 |
$30.10 |
$35.00 |
$43.00 |
| 48 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 708 | LF |
$16.00 |
$16.50 |
$12.90 |
$15.00 |
$25.00 |
| 49 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 50 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,357 | SY |
$5.00 |
$3.30 |
$4.00 |
$3.50 |
$3.30 |
| 51 | 516(A) 6094 |
DRILLED SHAFTS 48" DIAMETER | 141 | LF |
$800.00 |
$969.91 |
$708.00 |
$700.00 |
$783.00 |
| 52 | 516(C) 6200 |
CROSSHOLE SONIC LOGGING | 2 | EA |
$5,000.00 |
$2,750.00 |
$2,100.00 |
$3,500.00 |
$3,030.00 |
| 53 | 523(A) 6550 |
SEALER CRACK PREPARATION | 42.7 | LF |
$5.00 |
$5.50 |
$11.00 |
$5.50 |
$5.50 |
| 54 | 523(B) 6560 |
SEALER RESIN | 1 | GAL |
$150.00 |
$165.00 |
$220.00 |
$200.00 |
$165.00 |
| 55 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 248 | LF |
$30.00 |
$27.50 |
$27.00 |
$25.00 |
$53.00 |
| 56 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 137 | LF |
$30.00 |
$27.50 |
$28.00 |
$25.00 |
$30.00 |
| 57 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$30,000.00 |
$154,000.00 |
$25,000.00 |
$35,000.00 |
$75,300.00 |
| 58 | 104 0955 |
(SP) RAILROAD FLAGGING(NON-BIDDABLE) | 60 | DAY |
$300.00 |
$300.00 |
$300.00 |
$300.00 |
$300.00 |
| 59 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 35,200 | SD |
$1.35 |
$0.0400 |
$0.1000 |
$0.0600 |
$0.0500 |
| 60 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 3,200 | SD |
$3.40 |
$0.0400 |
$1.00 |
$0.0600 |
$0.0500 |
| 61 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 1,200 | SD |
$1.00 |
$7.92 |
$8.00 |
$7.50 |
$7.90 |
| 62 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 2,400 | SD |
$0.4000 |
$0.8300 |
$6.00 |
$0.8500 |
$0.8500 |
| 63 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 428 | SD |
$20.00 |
$3.30 |
$5.00 |
$4.00 |
$3.30 |
| 64 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 5,770 | LF |
$0.7000 |
$0.9400 |
$0.5000 |
$1.00 |
$0.5000 |
| 65 | 805(A) 8724 |
(PL)REMOVAL OF EXISTING SIGNS | 8 | EA |
$80.00 |
$82.50 |
$138.00 |
$100.00 |
$82.50 |
| 66 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 12,340 | LF |
$0.7000 |
$0.5100 |
$0.5600 |
$0.5000 |
$0.5000 |
| 67 | 857(F) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 1,000 | LF |
$1.10 |
$1.27 |
$1.20 |
$1.20 |
$1.30 |
| 68 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$80,000.00 |
$22,440.00 |
$21,000.00 |
$19,000.00 |
$32,700.00 |
| 69 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$4,675.00 |
$6,500.00 |
$4,000.00 |
$11,000.00 |
| 70 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$225,000.00 |
$206,043.61 |
$218,500.00 |
$225,000.00 |
$162,749.46 |