Bid tab 140308

Let Sep 18, 2014 · Division 7 · Stephens Sign up free

‹ Sep 2014 results

GRADE, DRAIN, SURFACE , AND BRIDGE US-81: SOUTH CONNECTION BYPASS OVER UNNAMED CREEK, 6.7 MILES NORTH OF SH -53 ON EXISTING US-81. PROJECT LENGTH = 0.342 MILES

Let date
Thursday, September 18, 2014
Contract
140308
J/P numbers
20316(22)
District
Division 7
County
Stephens
Highway
Limits
GRADE, DRAIN, SURFACE , AND BRIDGE US-81: SOUTH CONNECTION BYPASS OVER UNNAMED CREEK, 6.7 MILES NORTH OF SH -53 ON EXISTING US-81. PROJECT LENGTH = 0.342 MILES
Project number
NHPPY-269N(019)

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,234,062
1 MANHATTAN ROAD & BRIDGE COMPANY, LLC Low bidder $2,304,690 +3.2%
2 KLAVER CONSTRUCTION COMPANY, INC. $2,675,823 +19.8% +16.1%
3 EARTH BUILDERS, L.P. $2,871,106 +28.5% +24.6%

Bid tab: unit prices 43 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MANHATTAN ROAD …#2 KLAVER CONSTRUC…#3 EARTH BUILDERS,…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $20,000.00 $50,000.00 $70,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION17,705CY $8.00 $5.25 $8.00 $12.00
3202(D) 0184 UNCLASSIFIED BORROW32,870CY $10.00 $6.25 $12.00 $16.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $12,000.00 $12,500.00 $8,000.00 $25,000.00
5221(C) 2801 TEMPORARY SILT FENCE3,475LF $1.75 $1.30 $1.15 $1.50
6221(F) 0100 TEMPORARY SILT DIKE155LF $9.00 $7.25 $13.50 $9.00
7230(A) 2806 SOLID SLAB SODDING19,200SY $1.75 $1.35 $1.30 $1.80
8233(A) 2817 VEGETATIVE MULCHING3.97AC $600.00 $240.00 $800.00 $400.00
9241 2832 MOWING7.94AC $90.00 $90.00 $115.00 $100.00
10303(A) 2100 AGGREGATE BASE TYPE A250CY $50.00 $55.00 $65.00 $65.00
11310(B) 0149 SUBGRADE, METHOD B6,790SY $3.50 $1.55 $4.00 $5.00
12326(B) 0100 GEOGRID REINFORCEMENT1,385SY $2.50 $1.75 $10.00 $5.00
13402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E125TON $28.00 $33.00 $25.00 $50.00
14407(B) 0250 TACK COAT625GAL $3.50 $6.10 $6.00 $7.00
15408 5774 PRIME COAT2,380GAL $6.25 $6.05 $6.00 $7.00
16411(B) 5935 SUPERPAVE, TYPE S3(PG 76-28 OK)1,055TON $85.00 $92.00 $89.00 $100.00
17411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,610TON $80.00 $83.00 $80.00 $90.00
18411(C) 5950 SUPERPAVE, TYPE S4(PG 76-28 OK)110TON $95.00 $155.00 $150.00 $160.00
19411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)535TON $90.00 $95.00 $92.00 $120.00
20412 5267 COLD MILLING PAVEMENT7,867SY $2.50 $3.15 $8.00 $5.00
21509(D) 0325 CLASS C CONCRETE10CY $300.00 $330.00 $450.00 $350.00
22613(B) 4819 96" CORR. GALV. STEEL PIPE132LF $250.00 $250.00 $198.00 $280.00
23619(B) 4728 REMOVAL OF ASPHALT PAVEMENT5,510SY $4.00 $3.10 $4.00 $5.50
24619(C) 0924 SAWING PAVEMENT1,214LF $4.00 $5.00 $10.00 $5.00
25624(A) 4281 FENCE-STYLE WWF1,290LF $8.00 $10.50 $20.00 $9.00
26624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)955LF $5.00 $9.50 $15.00 $8.00
27202(A) 1301 UNCLASSIFIED EXCAVATION9,667CY $8.00 $10.00 $8.00 $10.00
28501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON545CY $20.00 $20.00 $10.00 $20.00
29509(A) 1326 CLASS AA CONCRETE1,380CY $475.00 $560.00 $585.15 $570.00
30511(A) 1332 REINFORCING STEEL264,240LB $0.9000 $1.20 $0.9000 $0.9000
31601(B) 1353 TYPE I-A PLAIN RIPRAP820TON $50.00 $42.00 $48.00 $48.00
32601(C) 1355 TYPE I-A FILTER BLANKET90TON $40.00 $38.00 $40.00 $38.00
33619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $15,000.00 $30,750.00 $14,000.00 $50,000.00
34857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)7,680LF $0.2500 $0.2200 $0.2100 $0.3000
35871(B) 8705 (SP)CONST.ZONE IMPACT ATTEN.320SD $12.00 $26.00 $25.00 $30.00
36877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER1,850LF $25.00 $17.00 $16.45 $18.00
37880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $3,000.00 $14,250.00 $25,000.00 $16,000.00
38882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN300SD $15.00 $8.25 $8.00 $10.00
39855(A) 8812 TRAFFIC STRIPE(PLASTIC)(4" WIDE)7,240LF $0.8000 $0.6300 $0.6100 $0.7000
40857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)2,680LF $0.4000 $0.5300 $0.5000 $0.6000
41642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $20,000.00 $13,750.00 $16,000.00 $18,000.00
42220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $2,139.00 $6,500.00 $3,500.00
43641 1552 MOBILIZATION1LSUM $130,000.00 $140,000.00 $231,127.54 $125,000.00