Bid tab 110483

Let Oct 20, 2011 · Division 4 · Kay Sign up free

‹ Oct 2011 results

BRIDGE AND APPROACHES I-35: OVER US-177. PROJECT LENGTH = 0.359 MILES

Let date
Thursday, October 20, 2011
Contract
110483
J/P numbers
27063(04)
District
Division 4
County
Kay
Highway
Limits
BRIDGE AND APPROACHES I-35: OVER US-177. PROJECT LENGTH = 0.359 MILES
Project number
BRIY-0035-4(239)232

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$3,337,394
1 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES Low bidder $4,078,821 +22.2%
2 OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) $4,590,773 +37.6% +12.6%

Bid tab: unit prices 111 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 WILDCAT CONSTRU…#2 OBC, INC./PLAIN…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $5,000.00 $20,000.00 $21,650.00
2202(A) 0183 UNCLASSIFIED EXCAVATION1,436CY $5.00 $6.00 $5.75
3202(D) 0184 UNCLASSIFIED BORROW9,513CY $6.25 $10.00 $11.50
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $15,000.00 $15,000.00 $11,500.00
5221(C) 2801 TEMPORARY SILT FENCE3,400LF $2.00 $1.40 $1.61
6221(D) 2803 TEMPORARY SEDIMENT FILTER2EA $220.00 $260.00 $298.60
7221(F) 0100 TEMPORARY SILT DIKE160LF $6.00 $8.00 $9.20
8230(A) 2806 SOLID SLAB SODDING15,751SY $2.00 $1.87 $1.82
9241 2832 MOWING6.5AC $50.00 $63.00 $72.45
10303(A) 2100 AGGREGATE BASE TYPE A5,480CY $34.00 $65.00 $68.92
11325 5271 SEPARATOR FABRIC18,262SY $1.50 $1.50 $1.45
12326(B) 0100 GEOGRID REINFORCEMENT18,262SY $2.20 $2.15 $2.94
13402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E3,267TON $25.00 $40.00 $44.85
14407(B) 0250 TACK COAT3,233GAL $3.00 $2.33 $2.63
15408 5774 PRIME COAT7,151GAL $4.00 $6.21 $7.01
16411(B) 5935 SUPERPAVE, TYPE S3(PG 76-28 OK)1,706TON $70.00 $89.34 $100.90
17411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)5,937TON $66.00 $82.93 $93.67
18411(C) 5950 SUPERPAVE, TYPE S4(PG 76-28 OK)1,129TON $75.00 $110.00 $124.24
19411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)506TON $70.00 $94.39 $106.60
20411(I) 6310 SUPERPAVE, TYPE S4(PATCH)(PG64-22OK)100TON $150.00 $222.44 $251.23
21414(E) 0225 FULL DEPTH P.C. CONCRETE PATCHING(PLACEMENT ONLY)25SY $100.00 $175.00 $172.50
22414(G) 5275 P.C. CONCRETE FOR PAVEMENT5.5CY $500.00 $150.00 $404.81
23509(D) 0325 CLASS C CONCRETE10CY $250.00 $100.00 $453.85
24613(A) 0492 24" R.C.PIPE CLASS III170LF $60.00 $50.00 $52.13
25613(M) 7197 TYPE B6 CULVERT END TREATMENT2EA $1,200.00 $2,000.00 $1,242.60
26619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $4,000.00 $23,000.00 $5,750.00
27619(B) 4727 REMOVAL OF CONCRETE PAVEMENT1,827SY $10.00 $7.50 $6.90
28619(B) 4728 REMOVAL OF ASPHALT PAVEMENT12,053SY $4.00 $5.00 $5.75
29619(B) 4780 REMOVAL OF GUARDRAIL1,423LF $2.50 $2.50 $2.30
30623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE1,000LF $17.00 $15.75 $17.07
31623(G) 8571 GUARDRAIL END TREATMENT (GET)4EA $2,000.00 $2,100.00 $2,357.50
32623(I) 8675 GUARDRAIL BRIDGE CONNECTION-TYPE A4EA $1,600.00 $1,575.00 $1,495.00
33501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON90CY $10.00 $40.00 $23.00
34501(G) 6309 CLSM BACKFILL230CY $150.00 $120.00 $160.30
35503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)636LF $185.00 $220.00 $192.11
36504(A) 1304 APPROACH SLAB437.4SY $150.00 $175.00 $161.20
37504(B) 1305 SAW-CUT GROOVING1,084SY $5.00 $3.60 $4.14
38504(E) 6190 42" F-SHAPED PARAPET513LF $75.00 $100.00 $86.46
39506(A) 1322 STRUCTURAL STEEL1,040LB $3.50 $2.00 $3.81
40507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY8EA $2,500.00 $400.00 $762.40
41507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY16EA $2,500.00 $3,000.00 $3,152.27
42507(C) 6282 ELASTOMERIC BEARING PADS16EA $350.00 $100.00 $554.23
43509(A) 1326 CLASS AA CONCRETE213.7CY $425.00 $485.00 $601.12
44509(B) 1328 CLASS A CONCRETE142.8CY $400.00 $415.00 $583.36
45510(C) 6138 SLOPE WALL (5")929SY $35.00 $75.00 $68.35
46511(A) 1332 REINFORCING STEEL860LB $0.9000 $1.40 $1.76
47511(B) 6010 EPOXY COATED REINFORCING STEEL73,640LB $0.9500 $1.15 $1.02
48514(A) 6010 PILES, FURNISHED (HP 10X42)408LF $30.00 $30.00 $43.23
49514(B) 6292 PILES, DRIVEN (HP 10X42)408LF $15.00 $20.00 $17.25
50515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)814SY $5.00 $3.50 $4.03
51516(A) 6098 DRILLED SHAFTS 72" DIAMETER132LF $600.00 $650.00 $794.17
52523(A) 6550 SEALER CRACK PREPARATION152LF $5.00 $4.00 $4.60
53523(B) 6560 SEALER RESIN2GAL $200.00 $150.00 $172.50
54613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND246LF $15.00 $20.00 $23.00
55613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.110LF $15.00 $20.00 $11.50
56619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $50,000.00 $50,000.00 $149,500.00
57501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON90CY $10.00 $40.00 $24.00
58501(G) 6309 CLSM BACKFILL230CY $150.00 $120.00 $167.27
59503(A) 1312 PRESTRESSED CONCRETE BEAMS (TYPE III)636LF $200.00 $220.00 $200.47
60504(A) 1304 APPROACH SLAB437.4SY $200.00 $175.00 $168.72
61504(B) 1305 SAW-CUT GROOVING1,084SY $5.00 $3.60 $4.32
62504(E) 6190 42" F-SHAPED PARAPET513LF $120.00 $100.00 $90.22
63506(A) 1322 STRUCTURAL STEEL1,040LB $3.50 $2.00 $3.98
64507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY8EA $2,500.00 $400.00 $795.61
65507(B) 6174 STAINLESS STEEL EXPANSION BEARING ASSEMBLY16EA $2,500.00 $3,000.00 $3,289.33
66507(C) 6282 ELASTOMERIC BEARING PADS16EA $500.00 $100.00 $578.32
67509(A) 1326 CLASS AA CONCRETE213.7CY $425.00 $485.00 $627.26
68509(B) 1328 CLASS A CONCRETE142.8CY $400.00 $415.00 $608.72
69510(C) 6138 SLOPE WALL (5")941SY $35.00 $75.00 $71.32
70511(A) 1332 REINFORCING STEEL860LB $0.8000 $1.50 $1.83
71511(B) 6010 EPOXY COATED REINFORCING STEEL73,640LB $1.20 $1.15 $1.07
72514(A) 6010 PILES, FURNISHED (HP 10X42)408LF $30.00 $30.00 $45.11
73514(B) 6292 PILES, DRIVEN (HP 10X42)408LF $15.00 $20.00 $18.00
74515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)814SY $5.00 $3.50 $4.20
75516(A) 6098 DRILLED SHAFTS 72" DIAMETER132LF $600.00 $650.00 $828.70
76523(A) 6550 SEALER CRACK PREPARATION152LF $5.00 $4.00 $4.80
77523(B) 6560 SEALER RESIN2GAL $200.00 $150.00 $180.00
78613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND246LF $15.00 $20.00 $24.00
79613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.110LF $15.00 $20.00 $12.00
80619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $50,000.00 $50,000.00 $156,000.00
81857(A) 8839 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE)9,800LF $0.2000 $0.1600 $0.1700
82857(E) 8887 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-16,080EA $0.5000 $0.3600 $0.4000
83857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)3,800LF $0.3500 $0.5200 $0.5800
84877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER4,150LF $15.00 $20.00 $19.55
85877(C) 8486 RELOCATION OF PORTABLE LONGITUDINAL BARRIER4,000LF $5.00 $2.50 $5.75
86878(B) 8487 MODULAR GLARE SCREEN (TEMPORARY)67,200SD $0.1500 $0.0200 $0.0200
87880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF9,270SD $0.2000 $0.1600 $0.1700
88880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF6,528SD $0.3000 $1.04 $1.15
89880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF7,228SD $0.4000 $2.08 $2.30
90880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)3,648SD $0.4500 $0.1000 $0.1200
91880(C) 8848 WING BARRICADES960SD $0.4000 $0.2600 $0.2900
92880(D) 8854 VERTICAL PANELS3,480SD $0.1500 $0.1000 $0.1200
93880(E) 8860 WARNING LIGHTS(TYPE A)7,296SD $0.3500 $0.1000 $0.1200
94880(F) 8878 DRUMS27,240SD $0.2000 $0.1600 $0.1700
95880(G) 8890 CHANNELIZER CONES2,640SD $0.1500 $0.2600 $0.2900
96880(L) 8911 TRAFFIC SURVEILLANCE, POLICE1,920HOUR $60.00 $60.00 $28.75
97882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN536SD $15.00 $5.20 $5.75
98413(A) 4861 RUMBLE STRIP-METHOD HMA-CON6,690LF $0.7000 $0.5500 $0.9200
99619(B) 5190 REMOVAL OF CABLE BARRIER6,055LF $3.00 $6.00 $6.50
100628 5180 INSTALLATION OF CABLE BARRIER SYSTEM6,055LF $7.00 $10.00 $14.03
101628(C) 5110 END ANCHORS4EA $5,000.00 $1,250.00 $1,299.50
102805(A) 8720 (PL)REMOVAL OF GROUND MOUNTED SIGNS1LSUM $500.00 $250.00 $287.50
103850(A) 8110 SHEET ALUMINUM SIGNS36SF $15.00 $20.00 $23.00
104851(C) 8324 2" SQUARE TUBE POST43LF $10.00 $10.00 $11.50
105853 9066 GUARDRAIL DELINEATORS(TYPE 1, CODE 1)24EA $20.00 $22.50 $25.88
106856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)15,200LF $0.6000 $0.6300 $0.6300
107856(A) 8535 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE)2,040LF $0.8000 $0.9800 $0.9800
108642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $24,345.00 $25,000.00 $18,400.00
109220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $2,500.00 $4,025.00
110640(A) 1426 FIELD OFFICE1EA $10,000.00 $5,000.00 $17,250.00
111641 1552 MOBILIZATION1LSUM $130,000.00 $222,275.00 $225,957.47