| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Apr 24, 2020 | 62K22 | DuPageWillDistrict 1 | ADA improvements along various state routes in Dupage and Will Counties. | — | Executed | Davis Concrete Construction Co. $558,989 · | ||
| Jun 12, 2020 | 61G55 | DuPageDistrict 1 | Construction of a multi-use path, pedestrian bridge and boardwalk adjacent to Hager Road from west of Salt Creek to Yorkshire Road in Oak Brook. | — | Executed | P. T. Ferro Construction Co. $1,692,755 · | ||
| Jun 12, 2020 | 62F20 | CookDuPageDistrict 1 | (18.3 mi), IL 83 between IL 171 and Third Ave, guardrail installation, shoulder rumble strip, re-striping pavement markings, wireless interconnect and reflecto ized traffic signal backplates. | — | Executed | K-Five Construction Corp & Quality Seal & Saw, Inc & Midwest Fence Corp Tri-Venture $1,074,369 · | ||
| Jun 12, 2020 | 62K97 | CookDuPageDistrict 1 | Entire concrete bridge deck, top of sidewalks, inside and top of parapets. Drai age system repairs and cleaning. Structures located at various locations within Cook and DuPage County. | — | Executed | Vixen Construction, Inc. $285,533 · | ||
| Jul 31, 2020 | 61G62 | DuPageDistrict 1 | Resurfacing, sidewalks, landscaping and contruction of a train platform shelter on Prospect Avenue, from Burlington Avenue to Ann Street in Clarendon Hills. | — | Executed | John Burns Construction Company $1,216,667 · | ||
| Nov 6, 2020 | 61G12 | DuPageDistrict 1 | Intersection Widening, milling and resurfacing, and the upgrade of existing signalized intersection on 31st Street from Meyers Road to York Road in Oak Brook. | — | Executed | K-Five Construction Corporation $6,239,378 · | ||
| Nov 6, 2020 | 61G54 | DuPageDistrict 1 | Replace a pedestrian bridge at the intersection of Eastern Avenue and Harris Avenue over Flagg Creek in Clarendon Hills. | — | Executed | Alliance Contractors, Inc. $136,011 · | ||
| Nov 6, 2020 | 62M67 | CookDuPageDistrict 1 | Installation of ramp speed advisory radar signs and curve warning signs, at various locations in Cook and DuPage counties. | — | Executed | Western Remac, Inc. $144,928 · | ||
| Nov 6, 2020 | 62N00 | DuPageDistrict 1 | Cleaning (sweeping) various arterial highways in District One throughout DuPage County. | — | Rejected | Illinois Central Sweeping LLC $599,170 · | ||
| Jan 15, 2021 | 61G19 | DuPageDistrict 1 | Pavement widening and reconstruction, sidewalks, multi-use path, storm sewer, traffic signals, lighting and pavement markings on North Aurora Road from Frontenanc Road to Fairwy Drive in Naperville. | — | Executed | Berger Excavating Contractors, Inc. $10,132,406 · | ||
| Jan 15, 2021 | 61G26 | DuPageDistrict 1 | Resurfacing, curb and gutter replacement, sidewalk replacement, and pavement markings on Prince Crossing Road from Geneva Road to IL 164 in West Chicago. | — | Executed | K-Five Construction Corporation $814,444 · | ||
| Jan 15, 2021 | 61G59 | DuPageDistrict 1 | Resurfacing Clarendon Hjills Road between 91st Street and 79th Street within Downers Grove Township in Dupage County. | — | Executed | K-Five Construction Corporation $552,568 · | ||
| Jan 15, 2021 | 61G66 | DuPageDistrict 1 | Resurfacing Abbeywood Drive and Green Trails Drive from Naper Boulevard to College Road in the Village of Lisle. | — | Executed | K-Five Construction Corporation $806,290 · | ||
| Jan 15, 2021 | 62K96 | DuPageDistrict 1 | Bridge Deck Overlay, Approach Slab Overlay, Joint Repairs and Substructure Repairs The improvement on 1-55 over Madison Street consist of Bridge Deck Overlay, Approach Slab Overlay, Joint Repairs and Substructure Repairs. Located in the Village of Burr Ridge in DuPage County. LT=392 FT(0.10-Mile) | — | Executed | Martam Construction Incorporated $1,919,305 · | ||
| Jan 15, 2021 | 62L47 | CookDuPageDistrict 1 | Cleaning and sealing cracks and joints in the existing concrete pavement, new pavement marking in the village (2.80-Mile) Improvement on 1-290 from Grand Ave to Cook County Line Rd consists of cleaning and sealing cracks and joints in the existing concrete pavement, new pavement marking in the village of Elmhurst, York and Addison Townships. | — | Executed | Freehill Asphalt, Inc. $206,128 · | ||
| Jan 15, 2021 | 62L77 | DuPageDistrict 1 | (3.157-Mile) Crack and joint sealing project on IL 64 (North Avenue) from IL 53 (Rohlwing Road) to Villa Ave. within the Villages of Lombard, Addison and Villa Ave. within the Villages of Lombard, Addison and Villa Park in DuPage County. | — | Executed | Freehill Asphalt, Inc. $261,467 · | ||
| Jan 15, 2021 | 62M60 | DuPageDistrict 1 | Interconnecting various traffic signals in order to mitigate congestion and improve traffic flow along various Work consists of interconnecting various traffic signals in order to mitigate congestion and improve traffic flow along various arterial routes. | — | Executed | H & H Electric Co. $911,409 · | ||
| Mar 5, 2021 | 62L23 | DuPageDistrict 1 | (2.3-Mile) SMART resurfacing and ADA improvements on IL 83 from north of I-290 to IL 19 within the Villages of Addison and Bensenville and Cities of Elmhurst and Wooddale. | — | Executed | K-Five Construction Corporation $3,619,222 · | ||
| Apr 23, 2021 | 61G97 | DuPageDistrict 1 | Resurfacing Eola Road from Oakhurst Drive to US 34 in Aurora. | — | Executed | K-Five Construction Corporation $1,046,723 · | ||
| Apr 23, 2021 | 61H02 | DuPageDistrict 1 | Resurfacing, curb and gutter, traffic signals, sidewalks and pavement markings on Grand Avenue, from US 20 to County Line Road in Elmhurst and Bensenville. | — | Executed | K-Five Construction Corporation $3,916,382 · | ||
| Apr 23, 2021 | 62L82 | DuPageDistrict 1 | (3.9-Mile) Crack and joint sealing on US 20 (Lake Street) from I-355 to IL 83 (Kingery Highway) within the Village of Addison. | — | Executed | Freehill Asphalt, Inc. $335,213 · | ||
| Apr 23, 2021 | 62M36 | DuPageDistrict 1 | A full and partial depth deck and approach slab repairs, bridge deck scarification, a new latex concrete overl This project is located on IL.83 over the Salt Creek within the Village of Villa Park in DuPage County. This work consists of a full and partial depth deck and approach slab repairs, bridge deck scarification, a new latex concrete overlay, deck drain adjustments and pavement marking. | — | Executed | Martam Construction Incorporated $741,297 · | ||
| Apr 23, 2021 | 62N92 | CookDuPageDistrict 1 | Litter/Debris removal from edge of pavement to the Pedestrian Barrier on I-55 - Stevenson expressway from IL 4 (150-Mile) Improvement consists of Litter/Debris removal from edge of pavement to the Pedestrian Barrier on I-55 - Stevenson expressway from IL 43 (Harlem Ave.) to I-355. | — | Executed | Western Remac, Inc. $207,720 · | ||
| Jun 11, 2021 | 46574 | DuPageMcHenryDistrict 1 | Applying water borne, lead free, white and yellow paint marking lines of 4, 6, and 8 inches in width This work shall consist of applying water borne, lead free, white and yellow paint marking lines of 4, 6, and 8 inches in width. | — | Executed | STF, LLC d/b/a Traffic Control Company $423,000 · | ||
| Jun 11, 2021 | 61G38 | DuPageDistrict 1 | Resurfacing, sidewalk, curb and gutter replacement on Chicago Avenue from IL 83 to Garfield Street and on 3rd. Street from Grant Street to Washington Street in Hinsdale. | — | Executed | Builders Paving, LLC $812,000 · | ||
| Jun 11, 2021 | 61H05 | DuPageDistrict 1 | Replace the culverts carrying Brickvale Drive over Willow Creek with precast concrete box culvert, 0.10 mile south of Devon Ave. in Elk Grove Village. | — | Executed | Alliance Contractors, Inc. $1,229,833 · | ||
| Jun 11, 2021 | 62G39 | DuPageDistrict 1 | (990.33-Ft) Removal of existing bridge along 1-55 over Lemont Road and replacement with a 4-span 200'-00" long, 197'-10" out-to-out wide bridge; roadway reconstruction and resurfacing; safety, drainage, lighting, signing, pavement marking and landscaping improvements in the City of Darien. | — | Executed | IHC Construction Companies, L.L.C. $17,018,663 · | ||
| Jun 11, 2021 | 62M69 | DuPageDistrict 1 | Removal of existing single cell box culvert and with proposed triple cell box culvert, ditch regrading and con The improvement consists of removal of existing single cell box culvert and with proposed triple cell box culvert, ditch regrading and constructing a new retaining wall located on ll 83 over Drainage Ditch in DuPage County, IL. | — | Executed | D. Construction, Inc. $3,570,071 · | ||
| Jul 30, 2021 | 62J25 | DuPageDistrict 1 | (636-Ft) Removal of the existing retaining wall and replacement with new soldier piles wall with lagging. Location: West side of IL 59, from Glen Ave to Forest Ave in the City of West Chicago in DuPage County. | — | Executed | Herlihy Mid-Continent Company $938,401 · | ||
| Nov 5, 2021 | 61H22 | DuPageDistrict 1 | Traffic signal improvements at various locations in DuPage County | — | Executed | Home Towne Electric, Inc. $5,849,810 · | ||
| Nov 5, 2021 | 62H97 | DuPageDistrict 1 | (1.826-Mile) Designed overlay and ADA improvements on I-55 N. Frontage Rd. from IL 83 to Elm St., located in the Villages of Willowbrook and Burr Ridge. | — | Executed | K-Five Construction Corporation $1,359,555 · | ||
| Nov 5, 2021 | 62M34 | DuPageDistrict 1 | (1555-Ft) Bridge deck overlay, expansion joint replacement and drainage scuppers repair located on a bridge carrying II 56 over 1-355 in the Village of Downers Grove. | — | Executed | Martam Construction Incorporated $1,989,293 · | ||
| Nov 5, 2021 | 62M35 | DuPageDistrict 1 | (1556-Ft) Bridge deck overlay and expansion joint replacement located on a bridge carrying 1164 over 1-355 in the Village of Lombard in DuPage County, IL. | — | Executed | Martam Construction Incorporated $2,304,407 · | ||
| Jan 21, 2022 | 61E87 | DuPageDistrict 1 | Pavement widening, resurfacing, storm sewer, curb and gutter, Sidewalks, traffic Signals, lighting and pavment Reconstruct the intersection of 87th Street and Woodrige Avenue in Woodridge. Work consists of Pavement widening, resurfacing, storm sewer, curb and gutter, Sidewalks, traffic Signals, lighting and pavment Markings. | — | Executed | Alliance Contractors, Inc. $4,371,729 · | ||
| Jan 21, 2022 | 61F88 | DuPageDistrict 1 | Sidewalk improvement on IL 53 from Hobson Road to Mulligan Drive in the Village of Woodridge. , Sidewalk removal and replacement, curb and gutter replacement, installation of pedestrian traffic signals and pavement markings on IL 53 from Hobson Road to Mulligan Drive in Woodridge. | — | Executed | Triggi Construction, Inc. $307,164 · | ||
| Jan 21, 2022 | 61H19 | DuPageDistrict 1 | Construction of a bike path along the North Central DuPage Regional Trail, from the Illinois Prairie Path to Forest Preserve Drive, in the Villages of Wayne and Bartlett. | — | Executed | Martam Construction Incorporated $1,145,132 · | ||
| Jan 21, 2022 | 61H29 | DuPageDistrict 1 | Geometric improvements and traffic signal modernizations at four intersections along 75th Street at Millbrook Drive, Modoff Road, Olympus Drive and Green Road in Naperville. | — | Executed | Alliance Contractors, Inc. $4,524,977 · | ||
| Jan 21, 2022 | 61H36 | DuPageDistrict 1 | Pavement reconstruction and resurfacing on Garfield Street from Hindsdale Avenue to 55th Street in Hinsdale. | — | Executed | J. Nardulli Concrete, Inc. $2,083,485 · | ||
| Jan 21, 2022 | 61H37 | DuPageDistrict 1 | Resurfacing Foster Avenue from Central Avenue to Spruce Avenue in Wood Dale | — | Executed | Arrow Road Construction Co. $316,707 · | ||
| Jan 21, 2022 | 62K99 | DuPageDistrict 1 | (1,562-Ft) Intersection improvement and signal installation project including HMA surface removal, pavement widening, pavement resurfacing, and traffic signal installation in the City of West Chicago. | — | Executed | A Lamp Concrete Contractors, Inc. $909,680 · | ||
| Jan 21, 2022 | 62P88 | DuPageDistrict 1 | Cleaning(sweeping) various arterial highways in District One throughout DuPage County The improvement consists of cleaning(sweeping) various arterial highways in District One throughout DuPage County. | — | Executed | Elgin Sweeping Services, Inc. $1,314,896 · | ||
| Mar 11, 2022 | 61H39 | DuPageDistrict 1 | Resurfacing Fairview Avenue from Ogden Avenue to 55th Street in Downers Grove. | — | Executed | K-Five Construction Corporation $838,974 · | ||
| Mar 11, 2022 | 61H46 | DuPageDistrict 1 | Pavement reconstruction, storm sewer, pipe culverts, curb and gutter, sidewalk, and pavement markings on Bloomingdale Road from Rohlwing Road to Irving Park Road in Itasca. | — | Executed | R. W. Dunteman Company $2,985,000 · | ||
| Mar 11, 2022 | 61H61 | DuPageDistrict 1 | Traffic signal modernization at the intersection of 63rd Street and Main Street in Downers Grove. | — | Executed | Home Towne Electric, Inc. $512,865 · | ||
| Mar 11, 2022 | 62M64 | DuPageDistrict 1 | (1000-Ft) Bridge deck overlay and joint replacement and beam repairs with fiber wrap located on a bridge carrying Clarendon Hills Road over 1-55 in unincorporated DuPage County. | — | Executed | Lorig Construction Company $862,370 · | ||
| Mar 11, 2022 | 62R36 | CookDuPageDistrict 1 | (185.6-Mile) Litter/ Debris Removal from edge of pavement to the Pedestrian Barrier on I-290 expressway from IL 83 (Kingery Hwy) to Austin Blvd. | — | Executed | MYS, Incorporated $208,772 · | ||
| Mar 11, 2022 | 62R37 | CookDuPageDistrict 1 | (209-Mile) Litter/ Debris Removal from edge of pavement to the Pedestrian Barrier on I-290 expressway from Lake Cook Rd to IL 83 (Kingery Hwy). | — | Executed | MYS, Incorporated $219,241 · | ||
| Apr 29, 2022 | 61G89 | DuPageDistrict 1 | Constructon of PCC Sidewalk, curb and gutter replacement, storm sewer, Segmental concrete block wall, traffic signal improvements and pavement markings on Hobson Road from Woodside Drive to Janes Avenue in Woodridge and unincorporated DuPage County in Lisle Township. | — | Executed | Acura Inc. $1,696,019 · | ||
| Apr 29, 2022 | 61H18 | DuPageDistrict 1 | Trailhead improvements including new sidewalk, landscaping, signing and construction of a restroom building and shelter. Project is located at the south corner of IL 56 at Batavia Road in Warrenville. | — | Executed | Landmark Contractors, Inc. $1,001,551 · | ||
| Apr 29, 2022 | 62N07 | CookDuPageLakeDistrict 1 | This is a drainage improvement on various State maintained routes within the Cities of Elmhurst and Waukegan and the Villages of Glendale Heights, Lemont, and Mount Prospect in Cook, DuPage and Lake Counties. The routes are Kensington Road, IL 137, I-290, IL 64, and McCarthy Road / 123rd Street. | — | Executed | Martam Construction Incorporated $1,608,899 · | ||
| Apr 29, 2022 | 62P82 | CookDuPageDistrict 1 | Cleaning and painting existing steel structures at 4 locations Improvement consists of cleaning and painting existing steel structures at 4 locations. Location 1 is at I-290 at IL 58 (SN 016-0980) in Rolling Meadows and Scahumburg. Location 2 is at 25th Ave at IHB RR (SN 016-1011) in Melrose Park and Franklin Park. Location 3 is at 1-290 and 1-355 (SN 022-0092) in Addison. Location 4 is at I-290 ramp to I-355 (SN022-0094) in Addison. | — | Executed | Eagle Painting & Maintenance Company, Inc. $1,176,437 · | ||
| Apr 29, 2022 | 62R45 | CookDuPageDistrict 1 | Litter/ Debris Removal from edge of pavement to the Pedestrian Barrier on 1-55 expressway from 1-355 to IL 43 (180-Mile) Improvement consists of Litter/ Debris Removal from edge of pavement to the Pedestrian Barrier on 1-55 expressway from 1-355 to IL 43 (Harlem Ave). | — | Executed | Winston's Image LLC $186,480 · | ||
| Jun 17, 2022 | 46594 | DuPageDistrict 1 | Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p This work shall consist of removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised pavement marker castings within the limits shown. | — | Executed | Superior Road Striping, Inc. $1,443,259 · | ||
| Jun 17, 2022 | 61H51 | DuPageDistrict 1 | Construction of a bike path along the west side of Kuhn Road from Army Trail Road to 0.10 mile south of Lies Road in Carol Stream. | — | Executed | R. W. Dunteman Company $521,372 · | ||
| Jun 17, 2022 | 62P58 | DuPageDistrict 1 | (1.40-Mile) Bridge joint repairs and approach slab replacements at the structures earring 1-290 EB over IL 83 and Wooddale Road located in the City of Elmhurst and Village of Addison in DuPage County. | — | Executed | Alliance Contractors, Inc. $2,248,890 · | ||
| Jun 17, 2022 | 62P72 | CookDuPageDistrict 1 | Trombone Mast Arm Replacement at various locations in District 1. | — | Executed | H & H Electric Co. $993,648 · | ||
| Jul 15, 2022 | 62R64 | DuPageDistrict 1 | Reconstructing the bridge wing wall, structure excavation, removal and replacement of curb and gutter in the c (230-Ft) Bridge wing wall repair and the work consist of reconstructing the bridge wing wall, structure excavation, removal and replacement of curb and gutter in the city of Elmhurst, DuPage County. | — | Executed | Herlihy Mid-Continent Company $362,100 · | ||
| Aug 5, 2022 | 61H86 | DuPageDistrict 1 | Resurfacing Devon Avenue/Ontarioville Road from 0.5 mile west of Church Road to US 20 (Lake Street) in Hanover Park.. | — | Executed | J. A. Johnson Paving Company $527,500 · | ||
| Sep 23, 2022 | 61H96 | DuPageDistrict 1 | Installation of conduit, handholes and fiber optic interconnet cable to connect existing traffic signal controllers to the existing DuPage County Central System Network. Includes installation of new PTZ cameras, Layer II (Data Link) switches, Layer III (Network) switches, new traffic signal controllers and cabinets. Project is located in various locations in Dupage County. | — | Executed | Thorne Electric, Inc. $6,484,160 · | ||
| Sep 23, 2022 | 62P22 | DuPageDistrict 1 | (4.18-Mile) Traffic signal modernization and intersection improvements of IL 59 at Joliet St/Edgewood Walk and at James Ave, pavement removal, HMA resurfacing, curb and gutter removal and replacement, median removal, traffic signal removal and replacement, adjustment of drainage structures, and pavement markings. Located in the City of West Chicago and Winfield Township. | — | Executed | Geneva Construction Company $1,558,813 · | ||
| Nov 18, 2022 | 61G82 | DuPageDistrict 1 | Removal of existing structure and construciton of two span post-tensioned cast-in-place concrete superstructure bridge on cast-in-place concrete substructure, with HMA removal and replacement, PCC sidewalk with ADA improvements, class D patching, curb and gutter, storm sewer, street scaping, and traffic signals on Washington Street over west branch of DuPage River in Naperville. | — | Executed | Dunnet Bay Construction Company $9,822,305 · | ||
| Nov 18, 2022 | 61H52 | DuPageDistrict 1 | Construction of HMA bike path, grading, and seeding along Lies Road from Gary Avenue to Schmale Road in Carol Stream. | — | Executed | A Lamp Concrete Contractors, Inc. $837,086 · | ||
| Jan 20, 2023 | 61H91 | DuPageDistrict 1 | HMA surface removal and replacement along North York Street from Crestview Avenue to Grand Avenue, with widening and traffic signal modernization at the Belden Avenue/Idustrial Drive intersection. Work includes raised medians, ADA improvements, Curb and Gutter removal and reconstruction, storm sewers, landscaping, and pavement markings all in the city of Elmhurst. | — | Executed | Builders Paving, LLC $3,125,808 · | ||
| Jan 20, 2023 | 61J11 | DuPageDistrict 1 | Resurface Montgomery Road from Frontenac Street to IL 59 in Aurora | — | Executed | K-Five Construction Corporation $831,305 · | ||
| Jan 20, 2023 | 61J12 | DuPageDistrict 1 | Widening and resurfacing the intersection of Devon Avenue and Park Boulevard and the intersection of Park Boulevard and Pierce Road in Itasca. | — | Executed | A Lamp Concrete Contractors, Inc. $1,996,347 · | ||
| Jan 20, 2023 | 61J13 | DuPageDistrict 1 | Resurfacing Liberty Street from Commons Drive to IL 59 in Aurora. | — | Executed | K-Five Construction Corporation $977,658 · | ||
| Jan 20, 2023 | 62K77 | DuPageDistrict 1 | (1,254-Ft) Deck replacement, replacement of exterior beams, structural repairs to existing beams and substructure, guardrail replacement, and resurfacing from Woodland Ave. and Meadow Lane. The project includes a flush 5 ft sidewalk on both sides and traffic signal interconnect fiber will be replaced from St Charles Road to IL 64 (North Ave.) | — | Executed | Herlihy Mid-Continent Company $3,360,385 · | ||
| Jan 20, 2023 | 62M43 | DuPageWillDistrict 1 | (4,199-Ft) Designed Overlay, New Shoulders on Joliet Rd from I-55 to Sherman Road. The project also includes Diamond Grooving on I-55 NB off ramp to I-355. This Project is in the Villages of Romeoville, Bollingbrook and Woodridge. | — | Executed | P. T. Ferro Construction Co. $2,288,051 · | ||
| Jan 20, 2023 | 62T96 | DuPageDistrict 1 | Bridge deck patching and bridge joint reconstruction on FAI 290 (WB) ramp to SB 1-355 located in the Village o (2546-Ft) Improvement consists of Bridge deck patching and bridge joint reconstruction on FAI 290 (WB) ramp to SB 1-355 located in the Village of Addison and Medinah in DuPage County. | — | Executed | Alliance Contractors, Inc. $915,316 · | ||
| Mar 10, 2023 | 61J31 | DuPageDistrict 1 | HMA removal and resurfacing, Sidewalk ADA ramp upgrades, curb and gutter, and pavement markings algon various routes in Lisle. | — | Executed | Schroeder Asphalt Services, Inc. $695,387 · | ||
| Mar 10, 2023 | 61J32 | DuPageDistrict 1 | HMA resurfacing, pavement markings, sidewalk ADA ramps, curb and gutter along Technology Boulevard in West Chicago. | — | Executed | Plote Construction, Inc. $758,000 · | ||
| Mar 10, 2023 | 62U60 | CookDuPageDistrict 1 | Debris and litter cleaning along I-290 and I-290 Extension from IL-83 (Kingery Hwy) to Austin Blvd This contract consists of debris and litter cleaning along I-290 and I-290 Extension from IL-83 (Kingery Hwy) to Austin Blvd. | — | Executed | MYS, Incorporated $163,621 · | ||
| Mar 10, 2023 | 62U67 | CookDuPageDistrict 1 | Debris and litter cleaning along I-290/IL-53 from Lake Cook Road to IL-83 This contract consists of debris and litter cleaning along I-290/IL-53 from Lake Cook Road to IL-83. | — | Executed | The Final Connection, Inc. $248,640 · | ||
| Apr 28, 2023 | 61J22 | DuPageDistrict 1 | Resurfacing Harger Road from Spring Road to the Westbound I-88 Ramp in Oak Brook. | — | Executed | Plote Construction, Inc. $865,726 · | ||
| Apr 28, 2023 | 61J27 | DuPageDistrict 1 | Resurfacing Covington Drive from Schick Road to Brighton Drive; Brighton Drive from Covington Drive to Army Trail Road; Comden Drive from Covington Drive to Gazy Avenue; Fox Court from Covington Drive to Gary Avenue; all in Bloomingdale. | — | Executed | Plote Construction, Inc. $945,090 · | ||
| Apr 28, 2023 | 61J33 | DuPageDistrict 1 | Resurfacing Batavia Road from east of the CN Railroad tracks to IL 159 in Warrenville. | — | Executed | Plote Construction, Inc. $706,756 · | ||
| Apr 28, 2023 | 61J37 | DuPageDistrict 1 | Resurfacing, patching, sidewalks and sod restoration along 71st Street from the west coporate limits to Dunham road in Downers Grove. | — | Executed | K-Five Construction Corporation $493,000 · | ||
| Apr 28, 2023 | 61J41 | DuPageDistrict 1 | Resurfacing Woodwar Avenue from the south village limits to 63rd Street in Downers Grove. | — | Executed | K-Five Construction Corporation $509,199 · | ||
| Apr 28, 2023 | 61J56 | DuPageDistrict 1 | Resurfacing Burlington Avenue from the west village limit to Prospect Avenue in Clarendon Hills | — | Executed | R. W. Dunteman Company $793,000 · | ||
| Apr 28, 2023 | 62U55 | CookDuPageDistrict 1 | Debris and litter cleaning along I-55 from I-355 to IL-43 (Harlem Ave) This contract consists of debris and litter cleaning along I-55 from I-355 to IL-43 (Harlem Ave). | — | Executed | The Final Connection, Inc. $152,640 · | ||
| Jun 16, 2023 | 46622 | DuPageMcHenryDistrict 1 | Application of water borne, lead free, white and yellow paint pavement marking lines of 4, 6 and 8 inches at various locations. The work will be on various State-maintained highways in McHenry and DuPage Counties. | — | Executed | Precision Pavement Markings Inc. $787,650 · | ||
| Jun 16, 2023 | 62K04 | DuPageDistrict 1 | (3847-Ft) Channelization and traffic signal modernization project on US 20 at Gary Avenue within the Village of Hanover Park, the Village of Roselle, and Bloomingdale Township in DuPage County. | — | Executed | R. W. Dunteman Company $5,675,641 · | ||
| Jun 16, 2023 | 62T16 | DuPageDistrict 1 | (700-Ft) This is a bridge preservation project and scope of work includes deck scarification, latex concrete overlay, joint sealing and replacement and approach slab repair on IL Route 38 over Winfield Creek in the City of Wheaton in DuPage County. | — | Executed | MYS, Incorporated $945,438 · | ||
| Jun 16, 2023 | 62T53 | CookDuPageDistrict 1 | Installation of new fiber optic cable, network switches, PTZ cameras, at 77 signalized intersections. This project located in Cook and DuPage Counties. | — | Executed | H & H Electric Co. $3,706,914 · | ||
| Jun 16, 2023 | 62T70 | CookDuPageDistrict 1 | (5.6-Mile) Crack and Joint Sealing project along IL Route 38, from East of Edson Ave to East of I-294 in the Villages of Elmhurst, Hillside, Lombard, Oakbrook Terrace and Villa Park in DuPage and Cook Counties. | — | Executed | Denler, Inc. $329,908 · | ||
| Aug 4, 2023 | 61J40 | DuPageDistrict 1 | HMA Resurfacing with Utility and structure adjustments, curb and gutter, sidewalk improvements, sodding, aggregate shoulders, and pavement markings on Crestwood Boulevard, from Park Right-of-Way to the east corporate limits of Glen Ellyn. | — | Executed | K-Five Construction Corporation $1,620,838 · | ||
| Aug 4, 2023 | 61J52 | DuPageDistrict 1 | Construction of a Shared-Use path along Wildwood Avenue and Monterey Avenue to provide connection between the Great Western Trail, the Illinois Prarie Path and Salt Creek Greenway Trail in Villa Park. | — | Executed | A Lamp Concrete Contractors, Inc. $738,989 · | ||
| Aug 4, 2023 | 62P03 | DuPageDistrict 1 | Culvert repair of IL 83 (Kingery Hwy) over drainage ditch, 0 (900-Ft) The proposed improvement consists of culvert repair of IL 83 (Kingery Hwy) over drainage ditch, 0.6 miles south of 91st Street in the Village of Burr Ridge in DuPage County. | — | Executed | D. Construction, Inc. $324,577 · | ||
| Sep 22, 2023 | 61J66 | DuPageDistrict 1 | Construction of a Shared-Use Path on 22nd Street from Finley Road to Meyers Road in Lombard. | — | Executed | Triggi Construction, Inc. $1,298,699 · | ||
| Sep 22, 2023 | 61J75 | DuPageDistrict 1 | Resurfacing Conde Street from Joliet Street to IL 59 in West Chicago. | — | Executed | A Lamp Concrete Contractors, Inc. $679,999 · | ||
| Sep 22, 2023 | 61J76 | DuPageDistrict 1 | Resurfacing Lorraine Road from Hill Avenue to IL 38 in Wheaton. | — | Executed | A Lamp Concrete Contractors, Inc. $384,568 · | ||
| Nov 17, 2023 | 61J77 | DuPageDistrict 1 | Resurfacing Edgewater Drive from Bloomingdale Road to Glen Ellyn Road, and Lakeview Lane from Edgewater Drive to South Circle Avenue in Bloomingdale. | — | Executed | Builders Paving, LLC $1,498,000 · | ||
| Nov 17, 2023 | 61J85 | DuPageDistrict 1 | Resurfacing Fullerton Avenue from Schmale Road to Bloomingdale Road in Glendale Heights. | — | Executed | K-Five Construction Corporation $1,717,494 · | ||
| Nov 17, 2023 | 62T12 | DuPageDistrict 1 | Bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Townshi The proposed improvement consists of bridge deck overlay and joint replacement of IL 83 over BNSF RR (S of Bluff Road) in the Downers Grove Township, DuPage County. Total gross length and net length= 5442.65 FT (1.031 Ml), and 4811.44FT (0.911 Ml) | — | Executed | Lorig Construction Company $1,355,097 · | ||
| Nov 17, 2023 | 62T65 | DuPageDistrict 1 | (2.09-Mile) SMART Overlay and pedestrian ramps (ADA) project. The scope included pavement patching, HMA surface removal and resurfacing, pedestrian ramp improvements, drainage structure adjustments, cleaning and placement of permanent pavement markings. This project begins on Beaumont Dr./ Shandrew Dr. at Ogden Ave. (US 34) and extends southwest of Aurora Rd. and is located within the City of Naperville in DuPage County. | — | Executed | Plote Construction, Inc. $1,874,899 · | ||
| Jan 19, 2024 | 61J95 | DuPageDistrict 1 | Resurfacing Central Avenue from Thomdale Avenue to Foster Avenue in Wood Dale. | — | Executed | Builders Paving, LLC $726,808 · | ||
| Jan 19, 2024 | 61K02 | DuPageDistrict 1 | Roadway reconstruction on Janes Avenue from 7th Street to Spring Street in Woodridge. | — | Executed | K-Five Construction Corporation $2,045,192 · | ||
| Jan 19, 2024 | 62R40 | DuPageDistrict 1 | Earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and ful (803-Ft) Curve correction project consists of earth excavation, removal and construction of a pipe culvert and drainages structure, pavement removal and full-depth HMA pavement, located along I-55 North Frontage Road at Cass Avenue in the City of Darien in DuPage County. | — | Executed | Martam Construction Incorporated $673,990 · | ||
| Jan 19, 2024 | 62W19 | DuPageDistrict 1 | Arterial road sweeping in DuPage County This contract consists of arterial road sweeping in DuPage County. | — | Rejected | Central Sweeping of Illinois, LLC $1,601,000 · | ||
| Mar 8, 2024 | 61J30 | DuPageDistrict 1 | Replacement of existing structure with a single span steel beam structure with concrete deck and HMA approach roadways, retaining walls, curb and gutter, shared-use path, drainage improvements, pavement markings and landscaping on Geneva Road over the the west branch of the DuPage River. | — | Executed | Herlihy Mid-Continent Company $7,867,988 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.