19-00114-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $838,974 | ||
| 2 | R. W. Dunteman Company | $868,000 | +3.5% | |
| 3 | A Lamp Concrete Contractors, Inc. | $904,057 | +7.8% | |
| 4 | Geneva Construction Company | $916,596 | +9.3% | |
| 5 | J. A. Johnson Paving Company | $920,031 | +9.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 R. W. Dunteman … | #3 A Lamp Concrete… | #4 Geneva Construc… | #5 J. A. Johnson P… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $6,500.00 | $5,500.00 | $6,500.00 | $3,851.00 | $5,500.00 | |
| 2 | X2070304 | POROUS GRAN EMB SPEC | 50 | CU YD | $100.00 | $94.03 | $10.00 | $90.00 | $1.00 | |
| 3 | X2800510 | INLET FILTER CLEANING | 80 | EACH | $50.00 | $25.00 | $10.00 | $25.00 | $1.00 | |
| 4 | X4240430 | PC CONC SIDEWALK 5 SP | 4,600 | SQ FT | $10.50 | $6.75 | $6.25 | $8.35 | $9.25 | |
| 5 | X4400500 | COMB C&G REMOV SPL | 1,500 | FOOT | $13.25 | $6.59 | $6.40 | $8.65 | $6.50 | |
| 6 | X4404700 | SIDEWALK REM SPL | 4,600 | SQ FT | $4.25 | $3.32 | $1.40 | $1.40 | $2.80 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 24 | EACH | $800.00 | $924.00 | $880.00 | $916.00 | $800.00 | |
| 8 | X6061005 | CONC CURB TB SPL | 150 | FOOT | $22.00 | $25.00 | $35.00 | $33.25 | $24.00 | |
| 9 | X6064200 | COMB CC&G TB6.12 SPL | 1,500 | FOOT | $34.00 | $28.65 | $26.00 | $33.47 | $41.00 | |
| 10 | Z0004510 | HMA DRIVEWAY PAVT 3 | 160 | SQ YD | $68.00 | $31.00 | $30.00 | $41.00 | $45.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 180 | SQ FT | $15.00 | $15.00 | $22.00 | $15.00 | $15.00 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 14 | 20101100 | TREE TRUNK PROTECTION | 10 | EACH | $95.00 | $200.00 | $50.00 | $100.00 | $25.00 | |
| 15 | 20101200 | TREE ROOT PRUNING | 10 | EACH | $105.00 | $200.00 | $50.00 | $150.00 | $50.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 50 | CU YD | $105.00 | $59.22 | $52.00 | $56.00 | $80.00 | |
| 17 | 21001000 | GEOTECH FAB F/GR STAB | 150 | SQ YD | $2.00 | $4.13 | $2.00 | $2.15 | $0.0100 | |
| 18 | 21101615 | TOPSOIL F & P 4 | 700 | SQ YD | $0.0100 | $6.00 | $7.70 | $5.25 | $1.00 | |
| 19 | 25200100 | SODDING | 700 | SQ YD | $0.0100 | $12.00 | $10.00 | $18.50 | $20.00 | |
| 20 | 25200200 | SUPPLE WATERING | 10 | UNIT | $65.00 | $65.00 | $0.0100 | $0.0100 | $50.00 | |
| 21 | 28000510 | INLET FILTERS | 80 | EACH | $225.00 | $150.00 | $15.00 | $200.00 | $150.00 | |
| 22 | 35101600 | AGG BASE CSE B 4 | 520 | SQ YD | $7.00 | $9.09 | $4.20 | $3.85 | $9.00 | |
| 23 | 40600290 | BIT MATLS TACK CT | 18,400 | POUND | $0.0100 | $0.0100 | $0.4600 | $0.0100 | $0.0100 | |
| 24 | 40600400 | MIX CR JTS FLANGEWYS | 50 | TON | $50.00 | $80.00 | $100.00 | $175.00 | $85.00 | |
| 25 | 40600982 | HMA SURF REM BUTT JT | 715 | SQ YD | $0.0100 | $19.44 | $10.00 | $7.76 | $3.00 | |
| 26 | 40603200 | P HMA BC IL-4.75 N50 | 1,150 | TON | $105.00 | $99.00 | $120.00 | $120.00 | $108.00 | |
| 27 | 40604062 | HMA SC IL-9.5 D N70 | 2,300 | TON | $88.00 | $90.70 | $94.00 | $96.00 | $86.00 | |
| 28 | 42300200 | PCC DRIVEWAY PAVT 6 | 50 | SQ YD | $54.00 | $59.00 | $75.00 | $83.00 | $72.00 | |
| 29 | 42300400 | PCC DRIVEWAY PAVT 8 | 50 | SQ YD | $63.00 | $69.00 | $85.00 | $93.00 | $87.00 | |
| 30 | 42400800 | DETECTABLE WARNINGS | 500 | SQ FT | $32.00 | $33.00 | $25.00 | $30.00 | $32.00 | |
| 31 | 44000157 | HMA SURF REM 2 | 26,500 | SQ YD | $2.75 | $3.13 | $2.20 | $2.40 | $3.00 | |
| 32 | 44000200 | DRIVE PAVEMENT REM | 260 | SQ YD | $18.00 | $17.67 | $10.75 | $9.00 | $0.0100 | |
| 33 | 44201773 | CL D PATCH T1 11 | 300 | SQ YD | $24.00 | $24.00 | $60.00 | $85.00 | $10.00 | |
| 34 | 44201777 | CL D PATCH T2 11 | 300 | SQ YD | $24.00 | $24.00 | $60.00 | $80.00 | $10.00 | |
| 35 | 44201781 | CL D PATCH T3 11 | 300 | SQ YD | $24.00 | $24.00 | $60.00 | $75.00 | $10.00 | |
| 36 | 44201783 | CL D PATCH T4 11 | 300 | SQ YD | $24.00 | $24.00 | $60.00 | $75.00 | $10.00 | |
| 37 | 60265700 | VV ADJUST | 13 | EACH | $490.00 | $490.00 | $540.00 | $545.00 | $400.00 | |
| 38 | 60266600 | VALVE BOX ADJ | 11 | EACH | $425.00 | $425.00 | $470.00 | $360.00 | $295.00 | |
| 39 | 60300305 | FR & LIDS ADJUST | 24 | EACH | $490.00 | $614.00 | $540.00 | $450.00 | $475.00 | |
| 40 | 60406000 | FR & LIDS T1 OL | 1 | EACH | $450.00 | $450.00 | $495.00 | $450.00 | $380.00 | |
| 41 | 60406100 | FR & LIDS T1 CL | 1 | EACH | $450.00 | $450.00 | $495.00 | $450.00 | $380.00 | |
| 42 | 66900200 | NON SPL WASTE DISPOSL | 50 | CU YD | $50.00 | $96.00 | $50.00 | $120.00 | $140.00 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,600.00 | $1,600.00 | $2,150.00 | $1,850.00 | $1,400.00 | |
| 44 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,500.00 | $3,500.00 | $3,250.00 | $2,300.00 | $2,600.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $500.00 | $1,000.00 | $2,100.00 | $2,000.00 | |
| 46 | 66901006 | REG SUB MON | 5 | CAL DA | $675.00 | $675.00 | $750.00 | $930.00 | $450.00 | |
| 47 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $51,750.00 | $50,000.00 | $53,000.00 | $55,221.68 | |
| 48 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $48,109.11 | $14,300.00 | $1.00 | $131,000.00 | |
| 49 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $17,700.00 | $7,350.00 | $57,000.50 | $7,350.00 | $1.00 | |
| 50 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $250.00 | $250.00 | $1.00 | $250.00 | $1.00 | |
| 51 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $3,300.00 | $1.00 | $1.00 | |
| 52 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.29 | $1.00 | $1.00 | $1.00 | |
| 53 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $3,850.00 | $1.00 | $1.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 4,500 | FOOT | $1.00 | $0.7200 | $0.0100 | $0.0100 | $0.0100 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 1,850 | SQ FT | $2.00 | $1.15 | $0.0100 | $0.0100 | $0.0100 | |
| 56 | 70306100 | TEMP PVT MK LTR & SYM T3 TAPE | 350 | SQ FT | $3.50 | $3.30 | $1.10 | $3.30 | $0.0100 | |
| 57 | 78000100 | THPL PVT MK LTR & SYM | 1,310 | SQ FT | $4.00 | $4.00 | $5.50 | $6.00 | $4.00 | |
| 58 | 78000200 | THPL PVT MK LINE 4 | 13,140 | FOOT | $0.5500 | $0.5500 | $0.6100 | $0.8500 | $0.5500 | |
| 59 | 78000400 | THPL PVT MK LINE 6 | 3,150 | FOOT | $0.7500 | $0.7500 | $1.35 | $1.30 | $0.7500 | |
| 60 | 78000600 | THPL PVT MK LINE 12 | 400 | FOOT | $1.50 | $1.50 | $2.20 | $3.00 | $1.50 | |
| 61 | 78000650 | THPL PVT MK LINE 24 | 820 | FOOT | $4.00 | $4.00 | $5.50 | $6.00 | $4.00 | |
| 62 | 88600600 | DET LOOP REPL | 1,600 | FOOT | $16.00 | $15.40 | $18.00 | $16.00 | $16.00 |