2020-238-T
- Let date
- Friday, April 29, 2022
- Contract
- 62N07 · job page
- District
- District 1
- County
- Cook, Dupage, Lake
- Highway
- Limits
- This is a drainage improvement on various State maintained routes within the Cities of Elmhurst and Waukegan and the Villages of Glendale Heights, Lemont, and Mount Prospect in Cook, DuPage and Lake Counties. The routes are Kensington Road, IL 137, I-290, IL 64, and McCarthy Road / 123rd Street.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martam Construction Incorporated Low bidder | $1,608,899 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martam Construc… |
|---|---|---|---|---|---|---|
| 1 | X0323265 | REMOVE EXIST RIPRAP | 7 | SQ YD | $122.00 | |
| 2 | X0325207 | TV INSPECT OF SEWER | 2,074 | FOOT | $7.00 | |
| 3 | X0327649 | SOIL RETENTION SYSTEM | 458 | SQ FT | $68.00 | |
| 4 | X1200328 | STORM SEW LINING 36 | 60 | FOOT | $322.00 | |
| 5 | X2020110 | GRADING & SHAP SHLDRS | 5.3 | UNIT | $660.00 | |
| 6 | X4400501 | COMB C&G REMOV REPL < = 10FT | 16 | FOOT | $275.00 | |
| 7 | X4406620 | PART DEP REM T4 2 | 165 | SQ YD | $12.00 | |
| 8 | X4420819 | CL D PATCH T3 14 SPL | 17 | SQ YD | $375.00 | |
| 9 | X4421000 | PARTIAL DEPTH PATCH | 19 | TON | $390.00 | |
| 10 | X4421839 | CL D PATCH T2 16 SPL | 10 | SQ YD | $675.00 | |
| 11 | X4421851 | CL D PATCH T2 17 SPL | 17 | SQ YD | $685.00 | |
| 12 | X4428187 | CL D PATCH T3 13 SPL | 24 | SQ YD | $365.00 | |
| 13 | X4428189 | CL D PATCH T4 13 SPL | 100 | SQ YD | $265.00 | |
| 14 | X5537600 | SS CLEANED 8 | 40 | FOOT | $6.00 | |
| 15 | X5537700 | SS CLEANED 10 | 64 | FOOT | $6.00 | |
| 16 | X5537800 | SS CLEANED 12 | 1,335 | FOOT | $1.00 | |
| 17 | X5537900 | SS CLEANED 15 | 432 | FOOT | $1.00 | |
| 18 | X5538000 | SS CLEANED 18 | 578 | FOOT | $8.00 | |
| 19 | X5538200 | SS CLEANED 24 | 318 | FOOT | $8.00 | |
| 20 | X5538700 | SS CLEANED 42 | 219 | FOOT | $50.00 | |
| 21 | X5538800 | SS CLEANED 48 | 231 | FOOT | $100.00 | |
| 22 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $2,800.00 | |
| 23 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $144,000.00 | |
| 24 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $152,000.00 | |
| 25 | X7830050 | RAISD REF PM REFL REM | 53 | EACH | $10.00 | |
| 26 | Z0004562 | COMB C C&G REM & REPL | 24 | FOOT | $275.00 | |
| 27 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,000.00 | |
| 28 | Z0018500 | DRAINAGE STR CLEANED | 45 | EACH | $500.00 | |
| 29 | Z0030850 | TEMP INFO SIGNING | 205.6 | SQ FT | $15.00 | |
| 30 | Z0064600 | SELECTIVE CLEARING | 0.85 | ACRE | $25,000.00 | |
| 31 | Z0073510 | TEMP TR SIGNAL TIMING | 1 | EACH | $1,000.00 | |
| 32 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | |
| 33 | 20100110 | TREE REMOV 6-15 | 220 | UNIT | $40.00 | |
| 34 | 20100210 | TREE REMOV OVER 15 | 18 | UNIT | $60.00 | |
| 35 | 20101000 | TEMPORARY FENCE | 232 | FOOT | $10.00 | |
| 36 | 20101200 | TREE ROOT PRUNING | 11 | EACH | $130.00 | |
| 37 | 20101700 | SUPPLE WATERING | 2 | UNIT | $100.00 | |
| 38 | 20200100 | EARTH EXCAVATION | 427 | CU YD | $85.00 | |
| 39 | 20201200 | REM & DISP UNS MATL | 21 | CU YD | $88.00 | |
| 40 | 20400800 | FURNISHED EXCAVATION | 111 | CU YD | $65.00 | |
| 41 | 20800150 | TRENCH BACKFILL | 92 | CU YD | $122.00 | |
| 42 | 21101505 | TOPSOIL EXC & PLAC | 624 | CU YD | $22.00 | |
| 43 | 21101615 | TOPSOIL F & P 4 | 3,488 | SQ YD | $8.00 | |
| 44 | 21400100 | GRADING & SHAP DITCH | 217 | FOOT | $85.00 | |
| 45 | 25000210 | SEEDING CL 2A | 0.89 | ACRE | $6,000.00 | |
| 46 | 25000400 | NITROGEN FERT NUTR | 81 | POUND | $4.00 | |
| 47 | 25000500 | PHOSPHORUS FERT NUTR | 81 | POUND | $4.00 | |
| 48 | 25000600 | POTASSIUM FERT NUTR | 81 | POUND | $4.00 | |
| 49 | 25100630 | EROSION CONTR BLANKET | 4,313 | SQ YD | $1.50 | |
| 50 | 28000250 | TEMP EROS CONTR SEED | 89 | POUND | $10.00 | |
| 51 | 28000305 | TEMP DITCH CHECKS | 360 | FOOT | $10.00 | |
| 52 | 28000400 | PERIMETER EROS BAR | 969 | FOOT | $5.00 | |
| 53 | 28000510 | INLET FILTERS | 3 | EACH | $200.00 | |
| 54 | 28100105 | STONE RIPRAP CL A3 | 13 | SQ YD | $165.00 | |
| 55 | 31101400 | SUB GRAN MAT B 6 | 17 | SQ YD | $85.00 | |
| 56 | 40600290 | BIT MATLS TACK CT | 62 | POUND | $8.00 | |
| 57 | 40600982 | HMA SURF REM BUTT JT | 3 | SQ YD | $750.00 | |
| 58 | 40604062 | HMA SC IL-9.5 D N70 | 16 | TON | $355.00 | |
| 59 | 42001300 | PROTECTIVE COAT | 25 | SQ YD | $30.00 | |
| 60 | 42400200 | PC CONC SIDEWALK 5 | 50 | SQ FT | $60.00 | |
| 61 | 44000157 | HMA SURF REM 2 | 137 | SQ YD | $28.00 | |
| 62 | 44000600 | SIDEWALK REM | 50 | SQ FT | $16.00 | |
| 63 | 44003100 | MEDIAN REMOVAL | 62 | SQ FT | $36.00 | |
| 64 | 44004250 | PAVED SHLD REMOVAL | 167 | SQ YD | $45.00 | |
| 65 | 48102100 | AGG WEDGE SHLD TYPE B | 13.3 | TON | $115.00 | |
| 66 | 48203045 | HMA SHOULDERS 12 | 167 | SQ YD | $145.00 | |
| 67 | 542A5473 | P CUL CL A 1 EQRS 18 | 40 | FOOT | $345.00 | |
| 68 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $1,400.00 | |
| 69 | 54214713 | PRCF END S EL EQRS 18 | 2 | EACH | $2,200.00 | |
| 70 | 550A0050 | STORM SEW CL A 1 12 | 68.4 | FOOT | $132.00 | |
| 71 | 550A0340 | STORM SEW CL A 2 12 | 402.6 | FOOT | $136.00 | |
| 72 | 550A0660 | STORM SEW CL A 3 15 | 8 | FOOT | $598.00 | |
| 73 | 55100400 | STORM SEWER REM 10 | 10 | FOOT | $50.00 | |
| 74 | 55100500 | STORM SEWER REM 12 | 10 | FOOT | $50.00 | |
| 75 | 55100700 | STORM SEWER REM 15 | 8 | FOOT | $60.00 | |
| 76 | 55101600 | STORM SEWER REM 36 | 5 | FOOT | $90.00 | |
| 77 | 60200105 | CB TA 4 DIA T1F OL | 1 | EACH | $6,800.00 | |
| 78 | 60200805 | CB TA 4 DIA T8G | 3 | EACH | $6,500.00 | |
| 79 | 60201340 | CB TA 4 DIA T24F&G | 1 | EACH | $6,800.00 | |
| 80 | 60208230 | CB TC T23F&G | 1 | EACH | $4,200.00 | |
| 81 | 60223800 | MAN TA 6 DIA T1F CL | 1 | EACH | $12,600.00 | |
| 82 | 60237470 | INLETS TA T24F&G | 1 | EACH | $3,200.00 | |
| 83 | 60251740 | CB ADJ NEW T24F&G | 1 | EACH | $1,250.00 | |
| 84 | 60252800 | CB RECONST | 1 | EACH | $1,600.00 | |
| 85 | 60255500 | MAN ADJUST | 2 | EACH | $800.00 | |
| 86 | 60500050 | REMOV CATCH BAS | 1 | EACH | $600.00 | |
| 87 | 60620000 | CONC MED TSB6.24 | 62 | SQ FT | $60.00 | |
| 88 | 60905305 | BOX CUL TO BE CLEANED | 881 | FOOT | $330.00 | |
| 89 | 60920015 | PIPE CULV CLEANED 15 | 42 | FOOT | $40.00 | |
| 90 | 63000001 | SPBGR TY A 6FT POSTS | 75 | FOOT | $50.00 | |
| 91 | 63100089 | TRAF BAR TERM T6B | 1 | EACH | $4,800.00 | |
| 92 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $4,400.00 | |
| 93 | 63200310 | GUARDRAIL REMOV | 163 | FOOT | $20.00 | |
| 94 | 66900200 | NON SPL WASTE DISPOSL | 1,308 | CU YD | $88.00 | |
| 95 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,650.00 | |
| 96 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $4,000.00 | |
| 97 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $600.00 | |
| 98 | 66901006 | REG SUB MON | 8 | CAL DA | $900.00 | |
| 99 | 67100100 | MOBILIZATION | 1 | L SUM | $96,000.00 | |
| 100 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $1.00 | |
| 101 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $4,000.00 | |
| 102 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $4,000.00 | |
| 103 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | |
| 104 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | |
| 105 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | |
| 106 | 70107004 | PAVT MK BLKOUT TAPE 4 | 1,692 | FOOT | $2.00 | |
| 107 | 70107012 | PAVT MK BLKOUT TPE 12 | 20 | FOOT | $6.00 | |
| 108 | 70107024 | PAVT MK BLKOUT TPE 24 | 13 | FOOT | $12.00 | |
| 109 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $9,000.00 | |
| 110 | 70300150 | SHRT TRM PAVT MK REM | 1,998 | SQ FT | $0.5000 | |
| 111 | 70307120 | TEMP PVT MK L4 T4 TAPE | 2,208 | FOOT | $1.20 | |
| 112 | 70307130 | TEMP PVT MK L6 T4 TAPE | 1,250 | FOOT | $1.80 | |
| 113 | 70307210 | TEMP PVT MK L24 T4 TAPE | 13 | FOOT | $10.00 | |
| 114 | 70400100 | TEMP CONC BARRIER | 1,250 | FOOT | $30.00 | |
| 115 | 70400125 | PIN TEMP CONC BARRIER | 294 | EACH | $25.00 | |
| 116 | 70600250 | IMP ATTN TEMP NRD TL3 | 1 | EACH | $4,000.00 | |
| 117 | 72501000 | TERMINAL MARKER - DA | 1 | EACH | $50.00 | |
| 118 | 78000200 | THPL PVT MK LINE 4 | 86 | FOOT | $15.00 | |
| 119 | 78000300 | THPL PVT MK LINE 5 | 10 | FOOT | $17.00 | |
| 120 | 78000500 | THPL PVT MK LINE 8 | 620 | FOOT | $20.00 | |
| 121 | 78000600 | THPL PVT MK LINE 12 | 113 | FOOT | $100.00 | |
| 122 | 78000650 | THPL PVT MK LINE 24 | 5 | FOOT | $160.00 | |
| 123 | 78009008 | MOD URETH PM LINE 8 | 190 | FOOT | $50.00 | |
| 124 | 78100100 | RAISED REFL PAVT MKR | 4 | EACH | $700.00 | |
| 125 | 78100300 | REPLACEMENT REFLECTOR | 53 | EACH | $90.00 | |
| 126 | 78200005 | GRDRAIL REF TYPE A | 4 | EACH | $15.00 | |
| 127 | 78200011 | BARR WALL REF TYPE C | 100 | EACH | $10.00 | |
| 128 | 78300200 | RAISED REF PVT MK REM | 2 | EACH | $100.00 | |
| 129 | 88600600 | DET LOOP REPL | 100 | FOOT | $30.00 |