Contact information
- vince@corpaving.com
- Phone
- (979) 836-1105
- Address
- 4059 QUAIL RUN RD, BRENHAM, TX 77833
- TxDOT prequalification
- Construction qualified
304BidsOct 8, 2013 to Jul 2, 2026
97Wins (low bidder)
31.9%Win rate
$127,952,374Total won
Competitor scorecard
Last 5 years in Texas34.3%Win rate49 of 143 bids
+1.4%Average bid vs estimate
-5.3%Winning bids vs estimate
+14.4%Over the low bid when they loseAverage field: 4.6 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| TEXAS MATERIALS GROUP, INC. | 108 | 73 | 35 | 68% |
| KNIFE RIVER CORPORATION - SOUTH | 44 | 28 | 16 | 64% |
| BIG CREEK CONSTRUCTION, LTD. | 37 | 18 | 19 | 49% |
| VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC | 31 | 19 | 12 | 61% |
| DURWOOD GREENE CONSTRUCTION CO. | 26 | 12 | 14 | 46% |
| HUNTER INDUSTRIES, LTD. | 23 | 10 | 13 | 43% |
| FORDE CONSTRUCTION COMPANY, INC. | 23 | 20 | 3 | 87% |
| BRAZOS PAVING, INC. | 22 | 18 | 4 | 82% |
| CK NEWBERRY, LLC | 17 | 9 | 8 | 53% |
| ELITE KINGS CONSTRUCTION, LLC | 15 | 7 | 8 | 47% |
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Jul 2, 2026 | 0508-02-140 | IH 10 WB FR(SH 99-FM 565)REPAIR & OVERLAChambers · Beaumont | 2 of 3 | $3,335,495 | $3,332,075DURWOOD GREENE CONSTRUCTION… | +0.1% |
| Jul 2, 2026 | 6503-27-001 | FY26 - Huntsville AO Mill & Inlay - 07Walker · Bryan | 3 of 4 | $1,586,975 | $1,433,238BIG CREEK CONSTRUCTION, LTD. | +10.7% |
| Jul 1, 2026 | 6503-24-001 | FY27 - Brenham AO Mill & Inlay - 07Washington · Bryan | 4 of 5 | $1,219,563 | $1,091,717BRAZOS PAVING, INC. | +11.7% |
| Jun 23, 2026 | 6499-85-001 | IH 10 EB FR Base Repair and OverlayChambers · Beaumont | 2 of 2 | $595,155 | $570,461TEXAS MATERIALS GROUP, INC. | +4.3% |
| Jun 10, 2026 | 6499-84-001 | FM 2090 Base Repair and OverlayLiberty · Beaumont | 1 of 3 | $726,406 | $726,406 | Won |
| Jun 3, 2026 | 1683-01-040 | FM 1640: SS 529 to W of FM 2218Fort Bend · Houston | 2 of 5 | $3,397,769 | $3,065,936DURWOOD GREENE CONSTRUCTION… | +10.8% |
| Jun 2, 2026 | 0315-03-070 | SH 90 at FM 244 - Turn Lane FY 26Grimes · Bryan | 4 of 7 | $1,335,711 | $1,241,183LARRY YOUNG PAVING, INC. | +7.6% |
| Jun 2, 2026 | 0050-12-002 | BU 290-L, Fry Rd. to US 290 OverlayHarris · Houston | 1 of 4 | $733,755 | $733,755 | Won |
| Jun 2, 2026 | 6498-37-001 | FY26 Brazoria Flexpave/Asphalt RepairBrazoria · Houston | 1 of 4 | $1,369,590 | $1,369,590 | Won |
| Mar 5, 2026 | 0932-02-059 | BMT_FM0365_1 (2022 HSIP) PAVED SHOULDERSJefferson · Beaumont | 1 of 3 | $1,134,406 | $1,134,406 | Won |
| Mar 5, 2026 | 6491-05-001 | FY26 - Robertson SH 6 Mill & InlayRobertson · Bryan | 3 of 7 | $2,413,153 | $2,329,117TEXAS MATERIALS GROUP, INC. | +3.6% |
| Mar 4, 2026 | 0978-02-084 | FM 517, SH 146 to FM 646Galveston · Houston | 3 of 7 | $3,484,454 | $3,316,075ELITE KINGS CONSTRUCTION, L… | +5.1% |
| Mar 4, 2026 | 0419-01-019 | RER | 2401 |SH 171 |N Second - LimestoneHill · Waco | 3 of 3 | $4,420,114 | $3,387,033BIG CREEK CONSTRUCTION, LTD. | +30.5% |
| Feb 5, 2026 | 0338-12-011 | SH 105-(US 59-SH 321) FDBR, OVERLAYLiberty · Beaumont | 1 of 5 | $2,780,143 | $2,780,143 | Won |
| Feb 5, 2026 | 0057-05-033 | US 84 at FM 489 - Turn Lanes FY 26Freestone · Bryan | 2 of 5 | $1,798,042 | $1,716,130BIG CREEK CONSTRUCTION, LTD. | +4.8% |
| Feb 4, 2026 | 3047-02-012 | FM 529, Brazos River to FM 362Waller · Houston | 2 of 7 | $3,720,352 | $3,274,774DURWOOD GREENE CONSTRUCTION… | +13.6% |
| Feb 4, 2026 | 0920-03-080 | Village Creek Park Resurfacing (PR 74)Hardin · Beaumont | 2 of 2 | $258,152 | $190,948TEXAS MATERIALS GROUP, INC. | +35.2% |
| Feb 4, 2026 | 0913-19-032 | PW STATE PARK IMPROVEMENTS 2019Calhoun · Yoakum | 10 of 11 | $609,781 | $342,250GARRET SHIELDS INFRASTRUCTU… | +78.2% |
| Jan 7, 2026 | 0177-03-109 | US 59 NB FR(SL 573[S]-DUDLEY ST) OVERLAYLiberty · Beaumont | 1 of 4 | $859,788 | $859,788 | Won |
| Jan 6, 2026 | 1259-02-022 | FM 1097, SH 75 to Walker C/LMontgomery · Houston | 3 of 7 | $5,483,663 | $4,872,185DURWOOD GREENE CONSTRUCTION… | +12.6% |
| Dec 2, 2025 | 0912-70-098 | VA, Resurface PR 138 in Sheldon Lake SPHarris · Houston | 1 of 5 | $1,740,088 | $1,740,088 | Won |
| Dec 2, 2025 | 0244-09-014 | FM 2799(FM 777-US 96)MILL,OV,SAFETY UPGRJasper · Beaumont | 2 of 2 | $1,612,922 | $1,374,926TEXAS MATERIALS GROUP, INC. | +17.3% |
| Nov 6, 2025 | 0028-04-083 | US 90(TRINITY RVR BR-E /SH 146)MILL & OVLiberty · Beaumont | 1 of 4 | $4,088,177 | $4,088,177 | Won |
| Nov 6, 2025 | 0117-05-063 | SH 21 E of IH 45 - TWLT FY 26Madison · Bryan | 3 of 8 | $2,399,584 | $2,014,433BIG CREEK CONSTRUCTION, LTD. | +19.1% |
| Nov 5, 2025 | 0028-06-091 | US 90 EB -(FM 365-4mi EAST)FULL D REPAIRJefferson · Beaumont | 2 of 5 | $3,207,458 | $3,143,022TEXAS MATERIALS GROUP, INC. | +2.1% |
| Oct 9, 2025 | 0508-03-111 | IH 10 WBFR(FM 1406-0.361 MI EAST)OVERLAYChambers · Beaumont | 1 of 3 | $822,842 | $822,842 | Won |
| Oct 8, 2025 | 0192-02-064 | SH 6, 2nd Street to BS 35CBrazoria · Houston | 1 of 3 | $1,826,598 | $1,826,598 | Won |
| Sep 5, 2025 | 6486-15-001 | FM 1442 InlayOrange · Beaumont | 2 of 2 | $1,230,789 | $1,190,491TEXAS MATERIALS GROUP, INC. | +3.4% |
| Sep 4, 2025 | 6477-48-001 | On Call Pavement Repairs FY 26Gonzales · Yoakum | 4 of 4 | $3,898,146 | $2,922,697HUNTER INDUSTRIES, LTD. | +33.4% |
| Aug 7, 2025 | 0540-03-037 | FM 974 at SH 6 FR - TWLT FY 25Brazos · Bryan | 4 of 5 | $3,466,663 | $2,808,685LARRY YOUNG PAVING, INC. | +23.4% |
| Jul 2, 2025 | 0703-03-029 | BMT_FM0256_2(2021 HSIP)STFO,RES,PVD SHLRTyler · Beaumont | 1 of 5 | $5,598,867 | $5,598,867 | Won |
| Jul 1, 2025 | 0166-07-068 | SH 75 at IH 45 Vertical Curve - FY 25Madison · Bryan | 1 of 5 | $820,741 | $820,741 | Won |
| Jul 1, 2025 | 3171-01-012 | FM 3084 REHABILITATE ROADWAY HSIP 2605Calhoun · Yoakum | 6 of 7 | $5,470,799 | $4,398,168CLARK CONSTRUCTION OF TEXAS… | +24.4% |
| Jun 12, 2025 | 6484-97-001 | FY26 - Grimes Spot Base RepairGrimes · Bryan | 1 of 4 | $362,890 | $362,890 | Won |
| Jun 11, 2025 | 6484-98-001 | FY26 - Washington Spot Base RepairWashington · Bryan | 1 of 5 | $230,840 | $230,840 | Won |
| Jun 10, 2025 | 6483-00-001 | FY26 - Bryan AO Spot MillBrazos · Bryan | 2 of 5 | $852,721 | $814,128KNIFE RIVER CORPORATION - S… | +4.7% |
| Jun 10, 2025 | 6484-02-001 | FY26 - Freestone Spot Base RepairFreestone · Bryan | 2 of 6 | $549,346 | $403,575KNIFE RIVER CORPORATION - S… | +36.1% |
| Jun 5, 2025 | 6475-41-001 | FY 26 US 59 FR BASE REPAI AND OVERLAYLiberty · Beaumont | 1 of 3 | $1,763,446 | $1,763,446 | Won |
| Jun 5, 2025 | 0586-01-069 | SH 332, FM 523 to End of MaintenanceBrazoria · Houston | 4 of 5 | $2,298,863 | $2,104,777DURWOOD GREENE CONSTRUCTION… | +9.2% |
| Jun 5, 2025 | 0274-01-040 | US 183 0.7 MI SOUTH SH 16 to Lampasas CLMills · Brownwood | 4 of 11 | $5,249,983 | $4,457,730BIG CREEK CONSTRUCTION, LTD. | +17.8% |
| Jun 4, 2025 | 0508-01-399 | IH 10 FR WB, SL 8 to Monmouth RdHarris · Houston | 2 of 5 | $3,734,804 | $3,413,667TEXAS MATERIALS GROUP, INC. | +9.4% |
| Jun 4, 2025 | 6479-33-001 | US 96 Mill & OverlayJasper · Beaumont | 1 of 2 | $2,469,559 | $2,469,559 | Won |
| Jun 4, 2025 | 6477-39-001 | FY25 - Madison IH-45 NBMadison · Bryan | 3 of 5 | $4,240,098 | $3,461,710BIG CREEK CONSTRUCTION, LTD. | +22.5% |
| Jun 4, 2025 | 0667-01-128 | SH 347(HOGABOOM RD-SH 73 FR) MILL & OVJefferson · Beaumont | 2 of 5 | $2,516,553 | $2,363,295ISI CONTRACTING, INC. | +6.5% |
| May 29, 2025 | 6484-96-001 | Asphaltic Concrete Pavement RepairsLavaca · Yoakum | 2 of 3 | $889,836 | $791,562HUNTER INDUSTRIES, LTD. | +12.4% |
| May 6, 2025 | 6482-99-001 | FY26 - Brenham AO Spot MillWashington · Bryan | 1 of 4 | $733,533 | $733,533 | Won |
| May 2, 2025 | 6483-01-001 | FY26 - Huntsville AO Spot MillWalker · Bryan | 1 of 5 | $1,349,975 | $1,349,975 | Won |
| May 2, 2025 | 0187-02-073 | REHABILITATE ROADWAY 2701-2Austin · Yoakum | 2 of 5 | $6,889,361 | $6,157,668TEXAS MATERIALS GROUP, INC. | +11.9% |
| May 2, 2025 | 0920-00-171 | TRUCK PARKING (FY 25)Jefferson · Beaumont | 1 of 3 | $1,999,855 | $1,999,855 | Won |
| May 2, 2025 | 0580-01-039 | SH 316 REHABILITATE ROADWAY HSIP 2505Calhoun · Yoakum | 3 of 4 | $3,779,627 | $3,141,248LCR TOTAL TRANSPORT LLC | +20.3% |
| May 2, 2025 | 0114-09-099 | US 290 R-Cuts West Washington - FY 25Washington · Bryan | 1 of 7 | $965,907 | $965,907 | Won |
| May 1, 2025 | 2887-01-013 | BMT_FM2830_1(2021 HSIP)INCREASE SUPERELELiberty · Beaumont | 1 of 4 | $484,908 | $484,908 | Won |
| Apr 22, 2025 | 6476-06-001 | 6476-06-001 Base Rep,Seal Coat,Pav MrkHarris · Houston | 2 of 3 | $505,913 | $487,049ELITE KINGS CONSTRUCTION, L… | +3.9% |
| Apr 15, 2025 | 6465-08-001 | RMC 6465-08-001 Program Call - FM 3083Montgomery · Houston | 3 of 4 | $269,747 | $160,976ELITE KINGS CONSTRUCTION, L… | +67.6% |
| Apr 4, 2025 | 0187-03-078 | REHABILITATE ROADWAY 2701Austin · Yoakum | 2 of 7 | $4,366,512 | $4,364,003TEXAS MATERIALS GROUP, INC. | +0.1% |
| Apr 4, 2025 | 0540-05-054 | FM 159 F:S FM2154 T:SH105 - Rehab 11PESBrazos · Bryan | 3 of 5 | $7,523,366 | $6,280,471BRAZOS PAVING, INC. | +19.8% |
| Apr 4, 2025 | 1284-01-085 | FM 1130-(FM 1136 E-4.24 MI)PAVED SHLDRSOrange · Beaumont | 2 of 5 | $4,226,290 | $3,916,262TEXAS MATERIALS GROUP, INC. | +7.9% |
| Apr 3, 2025 | 1004-01-064 | FM 524, UPRR to FM 521Brazoria · Houston | 5 of 6 | $1,813,469 | $1,714,183VULCAN MATERIALS ASPHALT AN… | +5.8% |
| Apr 3, 2025 | 0205-05-051 | US 79 F: SH 75 T:FM 1848 - TWLTL FY 25Leon · Bryan | 2 of 6 | $3,299,950 | $2,870,625LARRY YOUNG PAVING, INC. | +15.0% |
| Apr 3, 2025 | 2523-02-077 | FM 2004, SH 288 to SH 332Brazoria · Houston | 3 of 6 | $2,335,631 | $2,192,873ELITE KINGS CONSTRUCTION, L… | +6.5% |
| Mar 5, 2025 | 0515-04-034 | FM 530 SURFACING RESTORATION 2303Lavaca · Yoakum | 5 of 8 | $7,200,801 | $5,948,468HUNTER INDUSTRIES, LTD. | +21.1% |
| Mar 5, 2025 | 0720-05-007 | Spur 149, FM 1488 to FM 149Montgomery · Houston | 3 of 6 | $1,210,855 | $1,063,539VULCAN MATERIALS ASPHALT AN… | +13.9% |
| Mar 5, 2025 | 6477-41-001 | FY25 - Washington US 290Washington · Bryan | 1 of 9 | $1,299,406 | $1,299,406 | Won |
| Mar 4, 2025 | 1412-01-022 | FM 1301 SURFACING RESTORATION 2304Matagorda · Yoakum | 2 of 6 | $7,152,851 | $7,126,058CLARK CONSTRUCTION OF TEXAS… | +0.4% |
| Feb 7, 2025 | 3223-01-010 | FM 3155: Richmond State School to UA 90Fort Bend · Houston | 5 of 7 | $701,285 | $585,949DURWOOD GREENE CONSTRUCTION… | +19.7% |
| Feb 7, 2025 | 0739-02-183 | IH 10FR(HAMSHIRE RD-N. FORK TAYLOR BAYOUJefferson · Beaumont | 2 of 6 | $3,358,647 | $3,084,194TEXAS MATERIALS GROUP, INC. | +8.9% |
| Feb 7, 2025 | 0210-02-029 | US 77 at FM 1712 - Turn Lane FY 24Milam · Bryan | 5 of 7 | $1,558,504 | $1,382,358LARRY YOUNG PAVING, INC. | +12.7% |
| Feb 6, 2025 | 1685-03-105 | FM 1960, FM 2100 to Liberty C/LHarris · Houston | 1 of 7 | $1,835,597 | $1,835,597 | Won |
| Feb 6, 2025 | 0205-01-046 | US 79 at FM 2549 - Intersection FY 25Robertson · Bryan | 1 of 7 | $897,290 | $897,290 | Won |
| Jan 8, 2025 | 2633-01-014 | FM 526; North of US 90 to BU 90Harris · Houston | 2 of 6 | $1,169,016 | $1,067,872DURWOOD GREENE CONSTRUCTION… | +9.5% |
| Jan 8, 2025 | 6477-42-001 | FY25 - Brazos FM 2154Brazos · Bryan | 1 of 5 | $898,734 | $898,734 | Won |
| Jan 8, 2025 | 0089-15-018 | BU 59-S SURFACING RESTORATION 2022Wharton · Yoakum | 1 of 5 | $6,366,588 | $6,366,588 | Won |
| Jan 8, 2025 | 0114-04-078 | US 290 from SH 95 to FM 696 OverlayBastrop · Austin | 5 of 6 | $4,824,203 | $4,270,055TEXAS MATERIALS GROUP, INC. | +13.0% |
| Jan 7, 2025 | 1062-03-053 | FM 1485, Old Houston to Kidd Cemetery RdMontgomery · Houston | 3 of 5 | $9,194,576 | $8,172,669VULCAN MATERIALS ASPHALT AN… | +12.5% |
| Aug 1, 2024 | 0601-04-013 | SURFACING/ROADWAY RESTORATIONLiberty · Beaumont | 2 of 5 | $3,736,503 | $3,702,742VULCAN MATERIALS ASPHALT AN… | +0.9% |
| Jun 6, 2024 | 0049-08-078 | INTERSECTION IMPROVEMENTRobertson · Bryan | 4 of 4 | $1,429,497 | $1,275,457BRAZOS PAVING, INC. | +12.1% |
| Jun 5, 2024 | 2952-01-009 | WIDEN ROAD - ADD SHOULDERSHardin · Beaumont | 2 of 3 | $8,541,945 | $8,441,473TEXAS MATERIALS GROUP, INC. | +1.2% |
| Jun 5, 2024 | 0578-03-051 | HIGHWAY IMPROVEMENTWalker · Bryan | 2 of 4 | $634,108 | $611,096KNIFE RIVER CORPORATION - S… | +3.8% |
| Jun 5, 2024 | 6463-97-001 | ACP OVERLAYChambers · Beaumont | 2 of 3 | $939,372 | $918,473TEXAS MATERIALS GROUP, INC. | +2.3% |
| May 2, 2024 | 0049-08-076 | WIDEN ROAD - ADD SHOULDERSRobertson · Bryan | 2 of 5 | $2,710,999 | $2,487,591BIG CREEK CONSTRUCTION, LTD. | +9.0% |
| May 2, 2024 | 6397-27-001 | BASE REPAIR WITH SEAL COAT AND/OR OVERLAYLiberty · Beaumont | 1 of 3 | $933,874 | $933,874 | Won |
| May 2, 2024 | 6427-17-001 | REHABILITATION OF EXISTING ROADWAYJefferson · Beaumont | 1 of 2 | $2,952,947 | $2,952,947 | Won |
| May 2, 2024 | 6463-62-001 | ACP OVERLAYChambers · Beaumont | 2 of 3 | $1,483,569 | $1,417,123VULCAN MATERIALS ASPHALT AN… | +4.7% |
| May 2, 2024 | 6451-57-001 | MILL AND INLAYBrazos · Bryan | 2 of 6 | $4,597,602 | $4,330,955KNIFE RIVER CORPORATION - S… | +6.2% |
| May 2, 2024 | 6401-54-001 | ASPHALT PAVEMENT REPAIRColorado · Yoakum | 2 of 5 | $528,664 | $468,903HUNTER INDUSTRIES, LTD. | +12.7% |
| Apr 5, 2024 | 1133-02-030 | SURFACING/ROADWAY RESTORATIONGonzales · Yoakum | 8 of 11 | $5,500,663 | $4,879,726BIG CREEK CONSTRUCTION, LTD. | +12.7% |
| Apr 5, 2024 | 0787-02-022 | HAZARD ELIMINATION & SAFETYLiberty · Beaumont | 3 of 4 | $4,417,627 | $3,983,906TEXAS MATERIALS GROUP, INC. | +10.9% |
| Apr 5, 2024 | 0578-03-055 | INTERSECTION IMPROVEMENTS W/ TURN LANESWalker · Bryan | 3 of 5 | $1,679,146 | $1,514,151LARRY YOUNG PAVING, INC. | +10.9% |
| Mar 6, 2024 | 0952-01-062 | SURFACING/ROADWAY RESTORATIONLiberty · Beaumont | 2 of 4 | $2,395,426 | $2,261,890TEXAS MATERIALS GROUP, INC. | +5.9% |
| Mar 6, 2024 | 0527-05-012 | SURFACING/ROADWAY RESTORATIONFort Bend · Houston | 4 of 5 | $1,623,471 | $1,497,972DURWOOD GREENE CONSTRUCTION… | +8.4% |
| Mar 6, 2024 | 0910-08-064 | STATE PARK IMPROVEMENTSAnderson · Tyler | 2 of 3 | $182,639 | $170,874REYNOLDS & KAY, LTD. | +6.9% |
| Feb 2, 2024 | 0213-01-048 | INTERSECTION IMPROVEMENTS WITH LEFT TURN LANEWalker · Bryan | 4 of 8 | $1,131,822 | $1,036,981KNIFE RIVER CORPORATION - S… | +9.1% |
| Feb 1, 2024 | 0515-03-055 | REHABILITATE EXISTING ROADWAYCalhoun · Yoakum | 1 of 3 | $1,007,462 | $1,007,462 | Won |
| Feb 1, 2024 | 6422-12-001 | ASPHALT PAVEMENT REPAIRDe Witt · Yoakum | 2 of 5 | $1,935,766 | $1,882,668HUNTER INDUSTRIES, LTD. | +2.8% |
| Jan 5, 2024 | 0523-02-051 | BASE REPAIR, 1.5" PLANING, 1.5" ACP OVERLAYWaller · Houston | 4 of 5 | $4,210,290 | $4,087,472DURWOOD GREENE CONSTRUCTION… | +3.0% |
| Jan 4, 2024 | 0508-02-129 | REHABILITATE EXISTING ROADWAYChambers · Beaumont | 1 of 3 | $2,423,890 | $2,423,890 | Won |
| Jan 4, 2024 | 6422-27-001 | ACP OVERLAYWaller · Houston | 1 of 7 | $598,559 | $598,559 | Won |
| Nov 2, 2023 | 0339-04-040 | SURFACING/ROADWAY RESTORATIONHardin · Beaumont | 2 of 3 | $1,638,683 | $1,536,305TEXAS MATERIALS GROUP, INC. | +6.7% |
| Nov 2, 2023 | 6442-45-001 | ACP OVERLAYLiberty · Beaumont | 3 of 3 | $1,623,583 | $1,435,988TEXAS MATERIALS GROUP, INC. | +13.1% |
| Aug 3, 2023 | 0932-02-044 | ADD SHOULDERS AND OVERLAYJefferson · Beaumont | 1 of 2 | $7,997,541 | $7,997,541 | Won |
| Aug 2, 2023 | 1706-02-008 | SURFACING/ROADWAY RESTORATIONMontgomery · Houston | 3 of 8 | $1,118,423 | $1,006,889TEXAS MATERIALS GROUP, INC. | +11.1% |
| Jun 28, 2023 | 6420-79-001 | ASPHALT PAVEMENT WIDENINGChambers · Beaumont | 2 of 4 | $1,398,773 | $1,219,732TEXAS MATERIALS GROUP, INC. | +14.7% |
| Jun 27, 2023 | 6413-57-001 | REHABILITATION OF EXISTING ROADWAYChambers · Beaumont | 2 of 3 | $1,656,641 | $1,218,369TEXAS MATERIALS GROUP, INC. | +36.0% |
| May 5, 2023 | 0388-02-069 | SURFACING/ROADWAY RESTORATIONLiberty · Beaumont | 3 of 3 | $3,622,522 | $3,497,274VULCAN MATERIALS ASPHALT AN… | +3.6% |
| May 5, 2023 | 6429-62-001 | ACP OVERLAYTyler · Beaumont | 2 of 2 | $909,475 | $883,996TEXAS MATERIALS GROUP, INC. | +2.9% |
| May 5, 2023 | 6439-22-001 | MILL AND INLAYWalker · Bryan | 1 of 2 | $1,747,300 | $1,747,300 | Won |
| May 5, 2023 | 6439-32-001 | SPOT BASE REPAIRBrazos · Bryan | 1 of 4 | $1,557,750 | $1,557,750 | Won |
| May 4, 2023 | 0420-03-018 | HAZARD ELIMINATION & SAFETYCalhoun · Yoakum | 2 of 4 | $2,695,590 | $2,118,839BRANNAN PAVING CO., LTD. | +27.2% |
| May 4, 2023 | 0951-01-068 | SURFACING/ROADWAY RESTORATIONLiberty · Beaumont | 3 of 3 | $2,197,969 | $1,980,516TEXAS MATERIALS GROUP, INC. | +11.0% |
| May 4, 2023 | 6390-36-001 | ASPHALTJefferson · Beaumont | 1 of 2 | $905,299 | $905,299 | Won |
| May 4, 2023 | 6427-11-001 | ACP OVERLAYJefferson · Beaumont | 1 of 2 | $1,074,625 | $1,074,625 | Won |
| May 4, 2023 | 6439-20-001 | MILL AND INLAYBrazos · Bryan | 2 of 4 | $1,294,674 | $1,293,480BRAZOS PAVING, INC. | +0.1% |
| May 4, 2023 | 6439-30-001 | SPOT BASE REPAIRWashington · Bryan | 1 of 4 | $1,067,638 | $1,067,638 | Won |
| Mar 7, 2023 | 6432-20-001 | BASE FAILURE PAVEMENT REPAIRLimestone · Waco | 4 of 5 | $1,381,780 | $1,015,395BIG CREEK CONSTRUCTION, LTD. | +36.1% |
| Mar 7, 2023 | 6432-16-001 | BASE FAILURE PAVEMENT REPAIRFalls · Waco | 4 of 4 | $915,294 | $597,313BIG CREEK CONSTRUCTION, LTD. | +53.2% |
| Feb 1, 2023 | 1812-02-026 | REHABILITATE EXISTING ROADWAYChambers · Beaumont | 1 of 3 | $1,093,301 | $1,093,301 | Won |
| Jan 6, 2023 | 6428-74-001 | SPOT BASE REPAIRGonzales · Yoakum | 1 of 4 | $985,800 | $985,800 | Won |
| Jan 6, 2023 | 6416-47-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRGonzales · Yoakum | 1 of 6 | $3,081,398 | $3,081,398 | Won |
| Jan 5, 2023 | 0913-19-037 | SEAL COATCalhoun · Yoakum | 4 of 4 | $458,243 | $329,594LCR TOTAL TRANSPORT LLC | +39.0% |
| Oct 7, 2022 | 0089-10-026 | SURFACING/ROADWAY RESTORATIONWharton · Yoakum | 2 of 5 | $2,127,069 | $1,891,288JAMES CONSTRUCTION GROUP, L… | +12.5% |
| Sep 8, 2022 | 0807-01-032 | RESURFACE ROADWAYBastrop · Austin | 4 of 5 | $1,854,947 | $1,577,805HUNTER INDUSTRIES, LTD. | +17.6% |
| Sep 7, 2022 | 6390-39-001 | MILL AND INLAYJefferson · Beaumont | 1 of 2 | $1,547,222 | $1,547,222 | Won |
| Aug 4, 2022 | 0049-09-089 | WIDEN ROAD - ADD LANESBrazos · Bryan | 1 of 5 | $5,909,647 | $5,909,647 | Won |
| Aug 4, 2022 | 0420-02-051 | HAZARD ELIMINATION & SAFETYJackson · Yoakum | 4 of 5 | $3,749,670 | $2,881,196BRANNAN PAVING CO., LTD. | +30.1% |
| Aug 4, 2022 | 6403-74-001 | ACP OVERLAYOrange · Beaumont | 2 of 2 | $1,427,716 | $1,387,550TEXAS MATERIALS GROUP, INC. | +2.9% |
| Aug 3, 2022 | 0122-03-033 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TFreestone · Bryan | 2 of 3 | $2,140,930 | $2,078,845BIG CREEK CONSTRUCTION, LTD. | +3.0% |
| Aug 3, 2022 | 0028-03-109 | HAZARD ELIMINATION & SAFETYLiberty · Beaumont | 3 of 4 | $2,246,688 | $1,615,491VULCAN MATERIALS ASPHALT AN… | +39.1% |
| Aug 3, 2022 | 0931-04-034 | HAZARD ELIMINATION & SAFETYTrinity · Lufkin | 1 of 4 | $1,648,548 | $1,648,548 | Won |
| Aug 3, 2022 | 6404-33-001 | ASPHALT PAVEMENT REPAIRGalveston · Houston | 2 of 3 | $917,675 | $695,675MAIN LANE INDUSTRIES LTD. | +31.9% |
| May 4, 2022 | 6400-51-001 | MILL AND INLAYWalker · Bryan | 1 of 4 | $1,656,940 | $1,656,940 | Won |
| May 4, 2022 | 6400-70-001 | SPOT BASE REPAIRBrazos · Bryan | 1 of 3 | $898,532 | $898,532 | Won |
| Mar 4, 2022 | 0446-04-014 | SURFACING/ROADWAY RESTORATIONColorado · Yoakum | 2 of 7 | $6,779,605 | $5,576,114GLENN FUQUA, INC. | +21.6% |
| Mar 4, 2022 | 0523-02-050 | BASE REPAIR, PLANING, SEAL COAT, 1.5" PFC OLWaller · Houston | 4 of 6 | $3,687,199 | $3,607,335DURWOOD GREENE CONSTRUCTION… | +2.2% |
| Mar 3, 2022 | 0910-34-035 | STATE PARK IMPROVEMENTSHenderson · Tyler | 1 of 4 | $110,625 | $110,625 | Won |
| Mar 3, 2022 | 6394-33-001 | ASPHALT PAVEMENT REPAIRAustin · Yoakum | 1 of 2 | $1,117,948 | $1,117,948 | Won |
| Mar 3, 2022 | 6394-32-001 | ASPHALT PAVEMENT REPAIRGonzales · Yoakum | 2 of 5 | $709,055 | $704,757HUNTER INDUSTRIES, LTD. | +0.6% |
| Feb 15, 2022 | 6396-32-001 | CULVERT REPLACEMENTWashington · Bryan | 6 of 9 | $321,141 | $234,239KNIFE RIVER CORPORATION - S… | +37.1% |
| Feb 4, 2022 | 0920-38-253 | STATE PARK IMPROVEMENTSJefferson · Beaumont | 2 of 2 | $156,334 | $151,736TEXAS MATERIALS GROUP, INC. | +3.0% |
| Feb 3, 2022 | 3158-01-044 | HAZARD ELIMINATION & SAFETYMontgomery · Houston | 2 of 4 | $1,732,571 | $1,594,936MAIN LANE INDUSTRIES LTD. | +8.6% |
| Feb 3, 2022 | 0920-39-021 | STATE PARK IMPROVEMENTSChambers · Beaumont | 1 of 3 | $46,390 | $46,390 | Won |
| Jan 6, 2022 | 0515-01-071 | SURFACING/ROADWAY RESTORATIONJackson · Yoakum | 6 of 6 | $4,270,150 | $3,684,182BRANNAN PAVING CO., LTD. | +15.9% |
| Jan 6, 2022 | 0530-01-008 | REHABILITATE EXISTING ROADWAYBastrop · Austin | 2 of 3 | $574,038 | $547,399LONE STAR PAVING COMPANY | +4.9% |
| Jan 6, 2022 | 0914-33-067 | STATE PARK IMPROVEMENTSHays · Austin | 1 of 2 | $345,406 | $345,406 | Won |
| Oct 8, 2021 | 6382-92-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRJefferson · Beaumont | 1 of 3 | $904,019 | $904,019 | Won |
| Oct 7, 2021 | 6387-64-001 | MILL AND INLAYOrange · Beaumont | 2 of 4 | $686,194 | $623,184PTSS INVESTMENTS, LLC | +10.1% |
| Sep 2, 2021 | 2447-01-032 | INTERSECTION IMPROVEMENTWashington · Bryan | 1 of 5 | $576,065 | $576,065 | Won |
| Sep 1, 2021 | 6382-90-001 | MILL AND INLAYJefferson · Beaumont | 3 of 4 | $618,720 | $581,453PTSS INVESTMENTS, LLC | +6.4% |
| Aug 24, 2021 | 6381-03-001 | HOT MIXBrazoria · Houston | 1 of 3 | $228,110 | $228,110 | Won |
| Jul 1, 2021 | 6373-94-001 | HMA MILL & INLAYBrazos · Bryan | 1 of 4 | $708,467 | $708,467 | Won |
| Jul 1, 2021 | 6376-13-001 | SPOT BASE REPAIRWashington · Bryan | 1 of 4 | $638,324 | $638,324 | Won |
| Jul 1, 2021 | 6380-32-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIROrange · Beaumont | 1 of 3 | $802,871 | $802,871 | Won |
| Jul 1, 2021 | 0110-01-049 | INTERSECTION IMPROVEMENTS WITH TURN LANESWalker · Bryan | 1 of 5 | $946,422 | $946,422 | Won |
| Jun 3, 2021 | 6373-97-001 | SPOT BASE REPAIRBrazos · Bryan | 2 of 6 | $754,524 | $654,818BIG CREEK CONSTRUCTION, LTD. | +15.2% |
| Jun 3, 2021 | 6373-95-001 | HMA MILL AND INLAYWalker · Bryan | 2 of 4 | $1,320,972 | $1,225,720BIG CREEK CONSTRUCTION, LTD. | +7.8% |
| May 5, 2021 | 2524-01-011 | WIDEN ROADWAY AND INSTALL CENTERLINE RUMBLE STRIPSMatagorda · Yoakum | 1 of 6 | $2,706,169 | $2,706,169 | Won |
| May 5, 2021 | 1464-01-018 | HAZARD ELIMINATION & SAFETYChambers · Beaumont | 1 of 3 | $736,394 | $736,394 | Won |
| May 5, 2021 | 6379-46-001 | BASE FAILURE PAVEMENT REPAIRFalls · Waco | 4 of 4 | $282,704 | $157,745TEXAS MATERIALS GROUP, INC. | +79.2% |
| May 5, 2021 | 6379-64-001 | BASE FAILURE PAVEMENT REPAIRHill · Waco | 5 of 6 | $877,196 | $631,827NORTHEASTERN PAVERS, LLC | +38.8% |
| Apr 8, 2021 | 1096-01-065 | HAZARD ELIMINATION & SAFETYHardin · Beaumont | 2 of 5 | $2,289,954 | $2,206,602TEXAS MATERIALS GROUP, INC. | +3.8% |
| Apr 8, 2021 | 6369-57-001 | ON CALL SPOT REPAIRSGonzales · Yoakum | 1 of 7 | $756,100 | $756,100 | Won |
| Apr 7, 2021 | 0912-31-286 | SURFACING/ROADWAY RESTORATIONBrazoria · Houston | 1 of 3 | $481,707 | $481,707 | Won |
| Apr 7, 2021 | 0368-03-037 | CONSTRUCT NEW ROADWAY LANESJefferson · Beaumont | 2 of 4 | $429,544 | $362,017TEXAS MATERIALS GROUP, INC. | +18.7% |
| Apr 7, 2021 | 0388-03-081 | HAZARD ELIMINATION & SAFETYLiberty · Beaumont | 3 of 6 | $426,798 | $352,845TEXAS MATERIALS GROUP, INC. | +21.0% |
| Apr 7, 2021 | 6376-14-001 | SPOT BASE REPAIRWalker · Bryan | 3 of 5 | $968,425 | $828,385BIG CREEK CONSTRUCTION, LTD. | +16.9% |
| Apr 7, 2021 | 6373-96-001 | HMA MILL AND INLAYWashington · Bryan | 1 of 4 | $986,327 | $986,327 | Won |
| Mar 9, 2021 | 6374-34-001 | PAV REPAIR, SEAL COAT AND ACP OVERLAYBrazoria · Houston | 1 of 3 | $125,690 | $125,690 | Won |
| Mar 5, 2021 | 0920-12-044 | STATE PARK IMPROVEMENTSJasper · Beaumont | 4 of 4 | $1,598,474 | $1,434,467DREWERY CONSTRUCTION COMPAN… | +11.4% |
| Mar 5, 2021 | 3422-01-012 | STATE PARK IMPROVEMENTSFort Bend · Houston | 1 of 4 | $386,914 | $386,914 | Won |
| Mar 4, 2021 | 6369-58-001 | ON CALL PAVEMENT REPAIRSGonzales · Yoakum | 5 of 7 | $3,756,860 | $3,203,924HUNTER INDUSTRIES, LTD. | +17.3% |
| Feb 5, 2021 | 2850-01-018 | INTERSECTION IMPROVEMENTS, RT & LT TURN LANESWalker · Bryan | 3 of 10 | $2,205,700 | $2,117,590VULCAN CONSTRUCTION | +4.2% |
| Feb 5, 2021 | 6296-80-001 | MILL & IN-LAYJasper · Beaumont | 1 of 5 | $577,252 | $577,252 | Won |
| Feb 4, 2021 | 0111-01-095 | RESTORATION OF ROADWAYHarris · Houston | 3 of 4 | $1,290,679 | $969,114DURWOOD GREENE CONSTRUCTION… | +33.2% |
| Feb 4, 2021 | 0179-02-085 | PLANING, PAVEMENT REPAIR, SEAL COAT AND 1.5" HMABrazoria · Houston | 3 of 6 | $887,758 | $858,674DURWOOD GREENE CONSTRUCTION… | +3.4% |
| Feb 4, 2021 | 6367-33-001 | BASE REPAIR MILL-OVERLAYLiberty · Beaumont | 1 of 5 | $573,577 | $573,577 | Won |
| Dec 17, 2020 | 6370-13-001 | SCOUR REPAIRBrazos · Bryan | 9 of 16 | $343,284 | $204,920EVERYTHING IRRIGATION LLC | +67.5% |
| Dec 3, 2020 | 6348-62-001 | OVERLAYNewton · Beaumont | 3 of 3 | $392,495 | $337,382PTSS INVESTMENTS, LLC | +16.3% |
| Dec 3, 2020 | 6363-89-001 | OVERLAY ROADWAYHardin · Beaumont | 3 of 3 | $1,046,797 | $893,785VULCAN CONSTRUCTION | +17.1% |
| Dec 3, 2020 | 6363-88-001 | OVERLAYJefferson · Beaumont | 2 of 2 | $849,732 | $797,913TEXAS MATERIALS GROUP, INC. | +6.5% |
| Nov 5, 2020 | 6365-63-001 | BASE REPAIR & OVERLAYChambers · Beaumont | 1 of 5 | $235,487 | $235,487 | Won |
| Nov 5, 2020 | 6348-60-001 | OVERLAYNewton · Beaumont | 1 of 3 | $878,621 | $878,621 | Won |
| Nov 5, 2020 | 6366-19-001 | MILLING AND OVERLAYHarris · Houston | 3 of 4 | $859,964 | $783,388ANGEL BROTHERS HOLDINGS COR… | +9.8% |
| Oct 2, 2020 | 0420-09-024 | RESTORE ROADWAYJackson · Yoakum | 6 of 6 | $3,060,513 | $2,486,470BRANNAN PAVING CO., LTD. | +23.1% |
| Oct 2, 2020 | 3312-02-017 | HIGHWAY IMPROVEMENTGalveston · Houston | 3 of 5 | $572,656 | $476,344ANGEL BROTHERS HOLDINGS COR… | +20.2% |
| Oct 2, 2020 | 6364-11-001 | FULL DEPTH FLEXIBLE PAVEMENT REPAIRChambers · Beaumont | 1 of 8 | $462,140 | $462,140 | Won |
| Sep 3, 2020 | 1413-01-018 | SURFACING/ROADWAY RESTORATIONBrazoria · Houston | 4 of 5 | $1,581,218 | $1,468,982ANGEL BROTHERS HOLDINGS COR… | +7.6% |
| Aug 5, 2020 | 0269-04-039 | ADD LEFT TURN LANESLavaca · Yoakum | 4 of 6 | $1,290,913 | $1,216,445HUNTER INDUSTRIES, LTD. | +6.1% |
| Jul 9, 2020 | 6361-72-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRJefferson · Beaumont | 3 of 5 | $1,016,077 | $902,312PTSS INVESTMENTS, LLC | +12.6% |
| Jul 8, 2020 | 6364-93-001 | PAVEMENT REPAIRKerr · San Antonio | 3 of 7 | $1,096,057 | $959,228TEXAS MATERIALS GROUP, INC. | +14.3% |
| May 8, 2020 | 6355-77-001 | BASE FAILURE PAVEMENT REPAIRLimestone · Waco | 4 of 5 | $952,739 | $434,031BIG CREEK CONSTRUCTION, LTD. | +119.5% |
| May 8, 2020 | 6355-79-001 | BASE FAILURE PAVEMENT REPAIRSMcLennan · Waco | 4 of 4 | $1,260,222 | $827,444TEXAS MATERIALS GROUP, INC. | +52.3% |
| May 7, 2020 | 6349-21-001 | MILL AND OVERLAYChambers · Beaumont | 3 of 4 | $578,493 | $495,428ANGEL BROTHERS HOLDINGS COR… | +16.8% |
| May 7, 2020 | 6355-78-001 | BASE FAILURE PAVEMENT REPAIRFalls · Waco | 4 of 5 | $623,749 | $435,115TEXAS MATERIALS GROUP, INC. | +43.4% |
| May 7, 2020 | 6355-81-001 | BASE FAILURE PAVEMENT REPAIRHill · Waco | 5 of 6 | $1,308,123 | $812,252KNIFE RIVER CORPORATION - S… | +61.0% |
| Apr 9, 2020 | 6354-37-001 | ACP OVERLAYBrazoria · Houston | 1 of 4 | $781,875 | $781,875 | Won |
| Feb 7, 2020 | 0543-01-065 | PLANING, SEAL COAT, ACP OVERLAY AND TEXTURINGWaller · Houston | 5 of 5 | $2,097,321 | $1,597,357ANGEL BROTHERS HOLDINGS COR… | +31.3% |
| Feb 6, 2020 | 0271-09-023 | ADD 5 FT SHLDR, PLANING, LEVEL-UP AND 1.5 IN PFCWaller · Houston | 5 of 5 | $2,045,739 | $1,784,542JAMES CONSTRUCTION GROUP, L… | +14.6% |
| Dec 4, 2019 | 2940-02-011 | SEAL COAT, ACP OVERLAY, SIGNING & PVMT MARKFort Bend · Houston | 4 of 5 | $1,371,650 | $1,038,126DURWOOD GREENE CONSTRUCTION… | +32.1% |
| Oct 2, 2019 | 6345-32-001 | FULL DEPTH FLEXIBLE PAVEMENT REPChambers · Beaumont | 2 of 4 | $671,368 | $641,296MAIN LANE INDUSTRIES LTD. | +4.7% |
| Sep 6, 2019 | 6344-64-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRHardin · Beaumont | 2 of 3 | $742,891 | $607,253TEXAS MATERIALS GROUP, INC. | +22.3% |
| Jun 5, 2019 | 6340-58-001 | SPOT BASE REPAIRBrazos · Bryan | 1 of 3 | $713,352 | $713,352 | Won |
| Jun 5, 2019 | 6341-26-001 | HMA MILL AND INLAYBrazos · Bryan | 2 of 3 | $568,089 | $546,196KNIFE RIVER CORPORATION - S… | +4.0% |
| Jun 5, 2019 | 6340-59-001 | SPOT BASE REPAIRWalker · Bryan | 1 of 3 | $1,020,358 | $1,020,358 | Won |
| Jun 5, 2019 | 6341-27-001 | HMA MILL AND INLAYWalker · Bryan | 1 of 3 | $1,137,392 | $1,137,392 | Won |
| Jun 5, 2019 | 6340-60-001 | SPOT BASE REPAIRWashington · Bryan | 1 of 3 | $769,528 | $769,528 | Won |
| Jun 5, 2019 | 6341-28-001 | HMA MILL AND INLAYWashington · Bryan | 1 of 3 | $885,498 | $885,498 | Won |
| Apr 3, 2019 | 6343-65-001 | CALL OUT ASPHALTIC CONCRETE PAVEMENT OVERLAYDe Witt · Yoakum | 4 of 5 | $3,671,153 | $3,029,377HUNTER INDUSTRIES, LTD. | +21.2% |
| Apr 2, 2019 | 2825-01-009 | WIDEN RDWY, EDGLN, CTRLN PROFL MRKBurleson · Bryan | 3 of 5 | $1,418,827 | $1,323,982KNIFE RIVER CORPORATION - S… | +7.2% |
| Feb 26, 2019 | 6333-82-001 | STRUCTURAL AND EROSION REPAIRSAustin · Yoakum | 3 of 3 | $390,812 | $312,421CHAMPION INFRASTRUCTURE, LLC | +25.1% |
| Feb 5, 2019 | 6333-79-001 | OVERLAY AND PAVEMENT REPAIRLiberty · Beaumont | 2 of 6 | $826,628 | $780,012ANGEL BROTHERS HOLDINGS COR… | +6.0% |
| Feb 5, 2019 | 6320-47-001 | SCOUR REPAIRWashington · Bryan | 3 of 7 | $549,855 | $510,520SJ&J CONSTRUCTION, LLC | +7.7% |
| Feb 5, 2019 | 6340-25-001 | ON CALL SPOT REPAIRSGonzales · Yoakum | 1 of 5 | $876,200 | $876,200 | Won |
| Jan 9, 2019 | 6337-35-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRHardin · Beaumont | 1 of 6 | $768,059 | $768,059 | Won |
| Jan 9, 2019 | 6335-54-001 | MILL & INLAYJasper · Beaumont | 1 of 2 | $570,205 | $570,205 | Won |
| Jan 9, 2019 | 1418-01-012 | BASE REPAIR,ACP OVERLAY AND PAVEMENT MARKINGSWaller · Houston | 3 of 4 | $1,725,356 | $1,597,058ANGEL BROTHERS HOLDINGS COR… | +8.0% |
| Jan 8, 2019 | 6293-71-001 | PLANE AND OVERLAYChambers · Beaumont | 4 of 5 | $394,400 | $380,487FORDE CONSTRUCTION COMPANY,… | +3.7% |
| Dec 6, 2018 | 0210-03-025 | WIDEN ROADWAY, EDGLN & CTRLN PROFL MRKMilam · Bryan | 3 of 5 | $1,385,068 | $1,262,198KNIFE RIVER CORPORATION - S… | +9.7% |
| Dec 6, 2018 | 1302-03-010 | RESTORATION OF EXISTING ROADWAYWharton · Yoakum | 3 of 6 | $3,140,709 | $2,932,384REXCO CONSTRUCTION SERVICES… | +7.1% |
| Dec 5, 2018 | 1061-01-032 | CONSTRUCT PAVED SHLDRS,MILLED RUMBLE STRIPSLiberty · Beaumont | 1 of 4 | $1,711,111 | $1,711,111 | Won |
| Nov 7, 2018 | 0120-05-025 | INCREASE SUPERELEVATIONHamilton · Waco | 3 of 4 | $698,908 | $571,907BIG CREEK CONSTRUCTION, LTD. | +22.2% |
| Nov 6, 2018 | 6331-77-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRJasper · Beaumont | 2 of 6 | $1,109,834 | $897,768OLDCASTLE MATERIALS TEXAS, … | +23.6% |
| Sep 7, 2018 | 0587-01-063 | MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGSBrazoria · Houston | 1 of 4 | $1,335,804 | $1,335,804 | Won |
| Aug 14, 2018 | 6331-34-001 | REPAIR OF FLEXIBLE PAVEMENTBrazoria · Houston | 3 of 3 | $337,852 | $236,830MAIN LANE INDUSTRIES LTD. | +42.7% |
| Aug 8, 2018 | 1349-03-013 | PROVIDE ADDITIONAL PAVED SURFACEBurnet · Austin | 1 of 6 | $6,179,469 | $6,179,469 | Won |
| Aug 8, 2018 | 0523-08-014 | BASE REPAIR, OCST, LEVEL UP, OVMontgomery · Houston | 2 of 6 | $3,273,871 | $3,164,973ANGEL BROTHERS HOLDINGS COR… | +3.4% |
| Aug 7, 2018 | 0025-05-021 | SAFETY TREAT FIXED OBJECTSGonzales · Yoakum | 2 of 5 | $2,396,349 | $2,179,041MPB, INC. | +10.0% |
| Aug 7, 2018 | 0540-05-048 | REHABILITATE EXISTING ROADBrazos · Bryan | 2 of 8 | $2,889,237 | $2,816,988GLENN FUQUA, INC. | +2.6% |
| Jul 11, 2018 | 0114-08-035 | SAFETY TREAT FIXED OBJECTSFayette · Yoakum | 1 of 4 | $2,098,141 | $2,098,141 | Won |
| Jul 11, 2018 | 1986-01-063 | BASE REPAIR, OCST, LEVEL UP, OVERLAYMontgomery · Houston | 4 of 4 | $1,994,121 | $1,738,187SMITH & COMPANY | +14.7% |
| Jul 11, 2018 | 0533-01-020 | LEVEL-UP AND SEAL COATBurnet · Austin | 3 of 7 | $1,995,866 | $1,963,010LONE STAR PAVING COMPANY | +1.7% |
| Jul 10, 2018 | 3005-02-006 | PROVIDE ADDITIONAL PAVED SURFACEBurnet · Austin | 2 of 6 | $3,083,197 | $2,692,129AARON CONCRETE CONTRACTORS,… | +14.5% |
| Jul 10, 2018 | 0089-18-003 | BASE REPAIR, PLANING, ACP OL, SIGNING & PVMT MARKFort Bend · Houston | 4 of 5 | $1,828,545 | $1,518,767DURWOOD GREENE CONSTRUCTION… | +20.4% |
| Jul 10, 2018 | 0269-02-065 | SAFETY TREAT FIXED OBJECTSLavaca · Yoakum | 4 of 4 | $1,985,133 | $1,147,696CONSTAR CONSTRUCTION | +73.0% |
| Jun 6, 2018 | 6328-21-001 | HMA MILL AND INLAYBrazos · Bryan | 2 of 4 | $666,104 | $629,253KNIFE RIVER CORPORATION - S… | +5.9% |
| Jun 6, 2018 | 6328-22-001 | HMA MILL AND INLAYWalker · Bryan | 1 of 4 | $642,696 | $642,696 | Won |
| Jun 6, 2018 | 6328-23-001 | HMA MILL AND INLAYWashington · Bryan | 1 of 5 | $616,781 | $616,781 | Won |
| Jun 5, 2018 | 6328-29-001 | SPOT BASE REPAIRBrazos · Bryan | 3 of 5 | $857,953 | $802,085GLENN FUQUA, INC. | +7.0% |
| Jun 5, 2018 | 6328-30-001 | SPOT BASE REPAIRWalker · Bryan | 3 of 6 | $858,128 | $799,315KNIFE RIVER CORPORATION - S… | +7.4% |
| Jun 5, 2018 | 6328-31-001 | SPOT BASE REPAIRWashington · Bryan | 3 of 5 | $845,038 | $766,590KNIFE RIVER CORPORATION - S… | +10.2% |
| Jun 5, 2018 | 6332-10-001 | MILL AND INLAYBrazos · Bryan | 3 of 4 | $3,797,664 | $2,477,766KNIFE RIVER CORPORATION - S… | +53.3% |
| May 2, 2018 | 0334-05-032 | REPAIR, LEVEL-UP & SEAL COATLee · Austin | 5 of 8 | $1,598,601 | $1,244,148LONE STAR PAVING COMPANY | +28.5% |
| May 1, 2018 | 6322-30-001 | OVERLAY AND PAVEMENT REPAIRLiberty · Beaumont | 4 of 5 | $861,076 | $797,673SMITH & COMPANY | +7.9% |
| Apr 4, 2018 | 1420-02-012 | PROVIDE ADDITIONAL SURFACE_WIDTHChambers · Beaumont | 1 of 4 | $328,472 | $328,472 | Won |
| Apr 3, 2018 | 0204-01-070 | LENGTHEN LEFT TURN LANEWilliamson · Austin | 6 of 6 | $179,994 | $110,818COX COMMERCIAL CONSTRUCTION… | +62.4% |
| Apr 3, 2018 | 6316-23-001 | ADD LEFT TURN LANEMcLennan · Waco | 5 of 5 | $559,255 | $342,755KNIFE RIVER CORPORATION - S… | +63.2% |
| Mar 7, 2018 | 6322-21-001 | OVERLAYChambers · Beaumont | 4 of 4 | $966,692 | $839,543ANGEL BROTHERS HOLDINGS COR… | +15.1% |
| Mar 6, 2018 | 0593-01-123 | LEVEL-UP/OVERLAYLiberty · Beaumont | 3 of 5 | $912,063 | $845,385SMITH & COMPANY | +7.9% |
| Mar 6, 2018 | 6326-62-001 | MILL AND OVERLAYMontgomery · Houston | 1 of 7 | $551,281 | $551,281 | Won |
| Mar 6, 2018 | 6326-56-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRSJefferson · Beaumont | 1 of 4 | $537,909 | $537,909 | Won |
| Mar 6, 2018 | 3043-01-011 | PROVIDE ADDITIONAL PAVED SURFACE WIDTHTyler · Beaumont | 2 of 7 | $532,126 | $509,224OLDCASTLE MATERIALS TEXAS, … | +4.5% |
| Feb 2, 2018 | 1200-01-027 | ONE COURSE SURFACE TREATMENTWilliamson · Austin | 3 of 6 | $1,668,961 | $1,408,398HUNTER INDUSTRIES, LTD. | +18.5% |
| Feb 2, 2018 | 6322-91-001 | OVERLAY ROADWAYOrange · Beaumont | 2 of 5 | $1,079,344 | $999,987OLDCASTLE MATERIALS TEXAS, … | +7.9% |
| Feb 1, 2018 | 1062-02-026 | INST TN LNS,SHLDR WDEN ,MILL OL&PVHarris · Houston | 1 of 3 | $234,041 | $234,041 | Won |
| Feb 1, 2018 | 0593-01-120 | INSTALL TURN LANE, PASSING LANES & RUMBLE STRIPSLiberty · Beaumont | 3 of 4 | $5,787,237 | $5,234,742ANGEL BROTHERS HOLDINGS COR… | +10.6% |
| Feb 1, 2018 | 6324-58-001 | US 190 ETC FLEX PAVE STRUCTURE REPJasper · Beaumont | 2 of 5 | $565,293 | $562,947A. L. HELMCAMP, INC. | +0.4% |
| Feb 1, 2018 | 6320-56-001 | MILL AND OVERLAYLiberty · Beaumont | 2 of 5 | $1,066,641 | $1,042,371ANGEL BROTHERS HOLDINGS COR… | +2.3% |
| Nov 3, 2017 | 6320-14-001 | ON CALL PAVEMENT REPAIRSGonzales · Yoakum | 4 of 9 | $3,298,349 | $2,619,289RAY FARIS, INC. | +25.9% |
| Nov 2, 2017 | 6320-65-001 | ON CALL SPOT REPAIRSGonzales · Yoakum | 1 of 7 | $792,950 | $792,950 | Won |
| Oct 4, 2017 | 1414-05-014 | BASE REPAIR AND OVERLAYFort Bend · Houston | 3 of 6 | $887,885 | $851,224JAMES CONSTRUCTION GROUP, L… | +4.3% |
| Oct 3, 2017 | 6320-83-001 | SEAL COATMcLennan · Waco | 3 of 3 | $1,283,019 | $993,658F. N. PLOCH CONSTRUCTION CO… | +29.1% |
| Oct 3, 2017 | 6319-04-001 | SEAL COAT AND HMA OVERLAYBurleson · Bryan | 4 of 4 | $1,367,383 | $1,023,190BIG CREEK CONSTRUCTION, LTD. | +33.6% |
| Sep 12, 2017 | 6321-09-001 | HAULING ROADWAY MATERIALJefferson · Beaumont | 1 of 3 | $189,150 | $189,150 | Won |
| Sep 7, 2017 | 0858-02-021 | REHABILITATE EXISTING ROADMilam · Bryan | 1 of 12 | $1,428,674 | $1,428,674 | Won |
| Sep 7, 2017 | 6320-46-001 | OVERLAY, PLANING, MBGF, BRIDGE RAILLeon · Bryan | 3 of 4 | $2,443,167 | $2,153,410BIG CREEK CONSTRUCTION, LTD. | +13.5% |
| Aug 9, 2017 | 0110-04-129 | WIDEN 2 LANES TO 4 LANES UNDIVIDEDMontgomery · Houston | 2 of 3 | $1,167,908 | $1,126,256SMITH & COMPANY | +3.7% |
| Aug 9, 2017 | 0051-02-100 | ADD RIGHT TURN LANESHarris · Houston | 2 of 4 | $382,637 | $345,346MAIN LANE INDUSTRIES LTD. | +10.8% |
| Aug 9, 2017 | 0573-04-015 | SAFETY TREAT FIXED OBJECTSGonzales · Yoakum | 6 of 8 | $4,762,189 | $4,044,139HUNTER INDUSTRIES, LTD. | +17.8% |
| Aug 9, 2017 | 6317-40-001 | SPOT BASE REPAIRBrazos · Bryan | 6 of 8 | $1,066,015 | $816,110KNIFE RIVER CORPORATION - S… | +30.6% |
| Aug 9, 2017 | 6317-19-001 | OVERLAYLiberty · Beaumont | 2 of 5 | $648,663 | $605,867SMITH & COMPANY | +7.1% |
| Aug 8, 2017 | 0315-03-059 | OVERLAYGrimes · Bryan | 4 of 6 | $2,353,011 | $2,078,725ANGEL BROTHERS HOLDINGS COR… | +13.2% |
| Aug 8, 2017 | 6316-12-001 | ASPHALT PAVEMENT REPAIRWaller · Houston | 2 of 2 | $914,900 | $521,960MAIN LANE INDUSTRIES LTD. | +75.3% |
| Aug 8, 2017 | 6315-28-001 | HMA MILL AND INLAYWashington · Bryan | 2 of 4 | $698,763 | $648,765BIG CREEK CONSTRUCTION, LTD. | +7.7% |
| Jul 12, 2017 | 6315-29-001 | HMA MILL AND INLAYBrazos · Bryan | 2 of 5 | $705,415 | $687,930BIG CREEK CONSTRUCTION, LTD. | +2.5% |
| Jul 12, 2017 | 6315-30-001 | HMA MILL AND INLAYWalker · Bryan | 1 of 5 | $672,700 | $672,700 | Won |
| Jul 12, 2017 | 6317-39-001 | SPOT BASE REPAIRWashington · Bryan | 3 of 5 | $867,690 | $850,911KNIFE RIVER CORPORATION - S… | +2.0% |
| Jul 11, 2017 | 1411-02-011 | RESTORE ROADWAYAustin · Yoakum | 5 of 7 | $4,673,832 | $4,469,342GLENN FUQUA, INC. | +4.6% |
| Jul 11, 2017 | 1109-01-021 | PROVIDE ADDITIONAL PAVED SURFACE WIDTHJasper · Beaumont | 2 of 6 | $509,602 | $499,478DREWERY CONSTRUCTION COMPAN… | +2.0% |
| Jul 11, 2017 | 6317-38-001 | SPOT BASE REPAIRWalker · Bryan | 3 of 4 | $933,464 | $878,328KNIFE RIVER CORPORATION - S… | +6.3% |
| Jun 7, 2017 | 0593-01-114 | OVERLAY EXISTING ROADWAYLiberty · Beaumont | 1 of 4 | $1,050,837 | $1,050,837 | Won |
| Jun 7, 2017 | 6315-72-001 | BASE FAILURE PAVEMENT REPAIRCoryell · Waco | 4 of 6 | $370,242 | $305,221BIG CREEK CONSTRUCTION, LTD. | +21.3% |
| Jun 6, 2017 | 6315-73-001 | BASE FAILURE PAVEMENT REPAIRHamilton · Waco | 5 of 8 | $713,902 | $510,942BIG CREEK CONSTRUCTION, LTD. | +39.7% |
| Apr 5, 2017 | 6313-71-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRTyler · Beaumont | 3 of 5 | $639,996 | $532,283OLDCASTLE MATERIALS TEXAS, … | +20.2% |
| Mar 8, 2017 | 6314-08-001 | SPOT BASE REPAIRRobertson · Bryan | 5 of 6 | $873,525 | $657,725KNIFE RIVER CORPORATION - S… | +32.8% |
| Mar 7, 2017 | 0273-02-024 | CONVERT 4 LANE UNDIVIDED TO SUPER 2 WITH SHOULDERSBurnet · Austin | 3 of 4 | $1,680,062 | $1,383,923CLARK CONSTRUCTION OF TEXAS… | +21.4% |
| Mar 7, 2017 | 6313-74-001 | MILL AND INLAYWalker · Bryan | 3 of 3 | $561,737 | $477,154BIG CREEK CONSTRUCTION, LTD. | +17.7% |
| Jan 5, 2017 | 0114-11-076 | TRAFFIC SAFETY IMPROVEMENT, CLOSE CROSSOVERWaller · Houston | 2 of 2 | $187,587 | $181,057MAIN LANE INDUSTRIES LTD. | +3.6% |
| Jan 5, 2017 | 6310-81-001 | HMA MILL AND INLAYWalker · Bryan | 1 of 4 | $616,698 | $616,698 | Won |
| Jan 5, 2017 | 6310-82-001 | HMA MILL AND INLAYWashington · Bryan | 1 of 4 | $633,250 | $633,250 | Won |
| Jan 5, 2017 | 6310-83-001 | SPOT BASE REPAIRLeon · Bryan | 3 of 5 | $743,850 | $692,725A. L. HELMCAMP, INC. | +7.4% |
| Jan 5, 2017 | 6310-84-001 | SPOT BASE REPAIRGrimes · Bryan | 5 of 6 | $813,975 | $694,650ANGEL BROTHERS HOLDINGS COR… | +17.2% |
| Jan 5, 2017 | 6301-96-001 | FLEXIBLE PAVEMENT REPAIRSHardin · Beaumont | 1 of 8 | $1,166,410 | $1,166,410 | Won |
| Jan 4, 2017 | 6307-43-001 | MILL AND INLAYMilam · Bryan | 4 of 5 | $1,443,780 | $1,068,368KNIFE RIVER CORPORATION - S… | +35.1% |
| Dec 6, 2016 | 6307-58-001 | OVERLAY OF EXISTING ROADWAYLiberty · Beaumont | 1 of 2 | $192,805 | $192,805 | Won |
| Dec 1, 2016 | 0026-03-042 | WIDEN BRIDGE AND APPROACHESFayette · Yoakum | 7 of 8 | $1,354,184 | $831,842HUNTER INDUSTRIES, LTD. | +62.8% |
| Dec 1, 2016 | 2098-02-008 | WIDEN, REPAIR AND SEAL COATLee · Austin | 3 of 6 | $2,905,802 | $2,468,925HUNTER INDUSTRIES, LTD. | +17.7% |
| Dec 1, 2016 | 6305-93-001 | SOIL STABILIZATION AND RIPRAPFayette · Yoakum | 7 of 9 | $1,033,116 | $781,891AUSTIN FILTER SYSTEMS, INC. | +32.1% |
| Dec 1, 2016 | 6286-32-001 | ROADWAY RESTORATIONMadison · Bryan | 4 of 5 | $1,533,032 | $1,331,517GLENN FUQUA, INC. | +15.1% |
| Nov 4, 2016 | 6306-42-001 | SPOT BASE REPAIRMadison · Bryan | 3 of 6 | $778,725 | $749,475GLENN FUQUA, INC. | +3.9% |
| Nov 4, 2016 | 6302-43-001 | PLANE AND OVERLAYChambers · Beaumont | 5 of 5 | $771,128 | $637,844FORDE CONSTRUCTION COMPANY,… | +20.9% |
| Nov 3, 2016 | 6306-63-001 | ON-CALL SPOT REPAIRDe Witt · Yoakum | 4 of 6 | $1,160,500 | $985,500LONE STAR PAVING COMPANY | +17.8% |
| Nov 3, 2016 | 6305-47-001 | SLOPE REPAIRBrazos · Bryan | 10 of 10 | $1,753,191 | $1,149,333ANGEL BROTHERS HOLDINGS COR… | +52.5% |
Active prime contracts 11
| CCSJ | Where | Work | Contract | Complete | Report |
|---|---|---|---|---|---|
| 0338-12-011Let Feb 5, 2026 | LibertyBeaumont · SH 105 | OVERLAY | $2,780,143 | 101% | |
| 0177-03-109Let Jan 7, 2026 | LibertyBeaumont · US 59 | OVERLAY | $861,829 | 87% | |
| 0912-70-098Let Dec 2, 2025 | HarrisHouston · PR 138 | REHABILITATION OF EXISTING ROAD | $1,793,089 | 51% | |
| 0028-04-083Let Nov 6, 2025 | LibertyBeaumont · US 90 | OVERLAY | $4,088,177 | 95% | |
| 0508-03-111Let Oct 9, 2025 | ChambersBeaumont · IH 10 | OVERLAY | $822,842 | 104% | |
| 0192-02-064Let Oct 8, 2025 | BrazoriaHouston · SH 6 | OVERLAY | $1,854,324 | 85% | |
| 0703-03-029Let Jul 2, 2025 | TylerBeaumont · FM 256 | WIDEN NON-FREEWAY | $5,649,262 | 95% | |
| 6475-41-001Let Jun 5, 2025 | LibertyBeaumont · US0059 | MAINTENANCE | $1,617,547 | 84% | |
| 0920-00-171Let May 2, 2025 | JeffersonBeaumont · Various | MISCELLANEOUS CONSTRUCTION | $2,091,217 | 24% | |
| 0089-15-018Let Jan 8, 2025 | WhartonYoakum · BU 59S | OVERLAY | $6,736,491 | 98% | |
| 0049-09-089Let Aug 4, 2022 | BrazosBryan · US 190 | HAZARD ELIMINATION & SAFETY | $12,464,056 | 85% |
Subcontracts on active jobs 2
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 6395-34-001Let Mar 3, 2022 | ROY JORGENSEN ASSOCIATES, INC. | WalkerBryan | MAINTENANCE | 0% | $0 |
| 0716-02-045Let Feb 4, 2022 | (INACTIVE)MAIN LANE INDUSTRIES LTD. | ColoradoYoakum | BRIDGE REPLACEMENT | 10.3% | $728,315 |