Bid tab 160322

Let Sep 15, 2016 · Division 3 · Mcclain Sign up free

‹ Sep 2016 results

BRIDGE REHABILITATION SH -74: OVER I-35, 1.1 MILES SOUTH OF SH-39 IN PURCELL. PROJECT LENGTH = 0.133 MILE

Let date
Thursday, September 15, 2016
Contract
160322
J/P numbers
29572(04)
District
Division 3
County
Mcclain
Highway
Limits
BRIDGE REHABILITATION SH -74: OVER I-35, 1.1 MILES SOUTH OF SH-39 IN PURCELL. PROJECT LENGTH = 0.133 MILE
Project number
NHPPI-244N(029)SS

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,723,288
1 MANHATTAN ROAD & BRIDGE COMPANY, LLC Low bidder $2,368,083 -13.0%
2 Frontier Bridge, Inc. $2,435,332 -10.6% +2.8%
3 M.J. HUGHES CONSTRUCTION, INC. $2,742,613 +0.7% +15.8%
4 C3 Construction, Inc. $2,762,573 +1.4% +16.7%
5 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES $3,488,599 +28.1% +47.3%
6 K & R BUILDERS, INC. $3,546,682 +30.2% +49.8%

Bid tab: unit prices 101 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MANHATTAN ROAD …#2 Frontier Bridge…#3 M.J. HUGHES CON…#4 C3 Construction…#5 WILDCAT CONSTRU…#6 K & R BUILDERS,…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $20,000.00 $5,400.00 $5,000.00 $2,897.34 $1,500.00 $9,500.00
2202(A) 0183 UNCLASSIFIED EXCAVATION123CY $25.00 $35.00 $27.00 $17.00 $15.94 $75.00 $62.75
3202(D) 0184 UNCLASSIFIED BORROW37CY $35.00 $85.00 $27.00 $52.00 $21.73 $100.00 $90.50
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $5,000.00 $10,000.00 $4,860.00 $10,000.00 $4,056.27 $3,000.00 $11,500.00
5221(C) 2801 TEMPORARY SILT FENCE900LF $3.00 $3.00 $3.24 $4.00 $4.33 $2.99 $2.80
6221(D) 2803 TEMPORARY SEDIMENT FILTER4EA $500.00 $150.00 $540.00 $6.00 $346.23 $239.00 $360.00
7230(A) 2806 SOLID SLAB SODDING2,300SY $4.00 $4.05 $4.32 $6.50 $7.17 $4.95 $3.85
8233(A) 2817 VEGETATIVE MULCHING1AC $550.00 $2,025.00 $2,160.00 $250.00 $282.50 $195.00 $200.00
9241 2832 MOWING1AC $170.00 $205.00 $216.00 $400.00 $427.36 $295.00 $200.00
10307(K) 4300 STABILIZED SUBGRADE1,121SY $10.00 $15.00 $11.88 $14.00 $15.94 $5.75 $12.10
11407(B) 0250 TACK COAT597GAL $5.00 $2.10 $3.24 $4.00 $5.79 $4.00 $4.40
12408 5774 PRIME COAT494GAL $10.00 $4.05 $4.32 $5.00 $4.35 $3.00 $3.50
13411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)567TON $105.00 $70.00 $74.95 $90.00 $100.54 $69.40 $80.00
14411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)662TON $105.00 $85.00 $118.80 $145.00 $159.35 $110.00 $140.00
15412 5267 COLD MILLING PAVEMENT3,711SY $10.00 $4.00 $7.29 $9.00 $9.78 $6.75 $12.00
16414(A) 0210 P.C.CONCRETE PAVEMENT(PLACEMENT)223SY $50.00 $65.00 $75.60 $52.00 $60.84 $120.00 $84.00
17414(G) 5275 P.C. CONCRETE FOR PAVEMENT56CY $155.00 $155.00 $209.52 $130.00 $179.63 $220.00 $165.00
18609(B) 1500 1'-8" COMB. CURB & GUTTER (4" MNTBLE)969LF $35.00 $45.00 $35.24 $30.00 $30.42 $58.00 $37.00
19611(G) 6000 INLET (SMD-TYPE 1)1EA $3,000.00 $3,500.00 $3,796.31 $2,500.00 $3,331.94 $10,000.00 $3,300.00
20613(B) 0689 18" CORR. GALV. STEEL PIPE207LF $40.00 $40.00 $34.31 $35.00 $52.15 $75.00 $26.00
21619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $5,000.00 $8,500.00 $3,780.00 $5,000.00 $1,738.40 $2,000.00 $10,500.00
22619(B) 4726 REMOVAL OF CURB AND GUTTER1,144LF $8.00 $4.50 $5.40 $19.00 $9.42 $15.00 $5.70
23619(B) 4728 REMOVAL OF ASPHALT PAVEMENT1,295SY $10.00 $8.00 $5.40 $11.00 $8.69 $30.00 $12.00
24619(B) 4780 REMOVAL OF GUARDRAIL929LF $5.00 $5.00 $4.32 $12.00 $5.48 $3.78 $6.00
25619(C) 0924 SAWING PAVEMENT1,902LF $5.00 $3.00 $6.48 $6.00 $7.25 $6.00 $3.50
26623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE362.5LF $25.00 $17.00 $17.28 $22.00 $23.18 $16.00 $19.00
27623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,500.00 $2,200.00 $2,435.40 $2,800.00 $2,890.09 $1,995.00 $2,500.00
28623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")6EA $2,000.00 $3,000.00 $1,679.40 $1,900.00 $2,701.77 $18,665.00 $1,815.00
29805(A) 8724 (PL)REMOVAL OF EXISTING SIGNS8EA $65.00 $55.00 $54.00 $195.00 $72.43 $50.00 $250.00
30850(A) 8110 SHEET ALUMINUM SIGNS42.1SF $25.00 $30.00 $31.32 $32.00 $42.01 $29.00 $25.00
31851(C) 8324 2" SQUARE TUBE POST88LF $10.00 $8.30 $8.64 $13.00 $11.59 $8.00 $15.00
32202(A) 1301 UNCLASSIFIED EXCAVATION310CY $15.00 $35.00 $22.00 $21.00 $11.59 $50.00 $22.50
33501(G) 6309 CLSM BACKFILL105CY $200.00 $160.00 $172.43 $150.00 $246.27 $240.00 $205.00
34502 1000 TEMPORARY EARTH RETAINAGE1LSUM $5,000.00 $35,000.00 $7,150.00 $20,000.00 $4,346.00 $25,000.00 $75,000.00
35504(A) 1304 APPROACH SLAB306.6SY $210.00 $180.00 $253.17 $200.00 $277.78 $270.00 $260.00
36504(B) 1305 SAW-CUT GROOVING1,265SY $5.00 $4.10 $4.46 $5.00 $5.87 $4.05 $4.50
37504(C) 6250 SEALED EXPANSION JOINT98.6LF $350.00 $220.00 $277.86 $250.00 $383.90 $300.00 $315.00
38504(D) 6245 CONCRETE RAIL (TR4)598.9LF $95.00 $90.00 $130.83 $80.00 $105.75 $130.00 $105.00
39506(A) 1322 STRUCTURAL STEEL5,310LB $6.00 $6.75 $6.53 $7.00 $7.16 $4.94 $6.00
40509 6152 SPECIAL CONCRETE FINISH91SY $50.00 $65.00 $44.00 $13.00 $66.64 $67.00 $60.00
41509(A) 1326 CLASS AA CONCRETE401.2CY $850.00 $850.00 $672.90 $1,000.00 $796.77 $1,300.00 $1,340.00
42509(D) 1331 CLASS C CONCRETE10CY $600.00 $650.00 $402.51 $700.00 $434.60 $2,200.00 $695.00
43510(C) 6137 SLOPE WALL (4")120SY $150.00 $225.00 $163.44 $150.00 $89.82 $130.00 $160.00
44511(B) 6010 EPOXY COATED REINFORCING STEEL98,090LB $1.25 $1.10 $1.19 $1.00 $1.36 $1.00 $1.13
45512(A) 1323 PAINTING EXISTING STRUCTURES1LSUM $50,000.00 $35,000.00 $43,915.30 $52,000.00 $5,783.17 $39,923.00 $45,000.00
46512(B) 6303 COLLECTION AND HANDLING OF WASTE1LSUM $25,000.00 $5,000.00 $2,191.20 $2,600.00 $2,885.75 $1,992.00 $3,800.00
47515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)399SY $5.00 $3.65 $3.85 $5.00 $5.50 $3.50 $5.00
48520(A) 6058 PREPARATION OF CRACKS, ABOVE WATER50LF $40.00 $32.00 $22.00 $26.00 $28.97 $20.00 $22.00
49520(C) 6060 EPOXY RESIN, ABOVE WATER5GAL $80.00 $105.00 $55.00 $65.00 $72.43 $50.00 $110.00
50521(A) 6210 PNEUMATICALLY PLACED MORTAR15SY $900.00 $665.00 $693.00 $800.00 $912.66 $630.00 $750.00
51523(A) 6550 SEALER CRACK PREPARATION99.6LF $5.00 $5.25 $4.40 $5.00 $5.79 $4.00 $4.40
52523(B) 6560 SEALER RESIN2GAL $120.00 $155.00 $165.00 $195.00 $217.30 $150.00 $165.00
53525(A) 0100 (SP)NEST PREVENTION - NETTING1LSUM $10,000.00 $500.00 $2,750.00 $17,000.00 $10,140.67 $10,000.00 $8,000.00
54540 4515 (PL)REPAIR BRIDGE ITEM (TYPE A)10EA $500.00 $1,500.00 $1,126.38 $750.00 $1,231.37 $500.00 $3,200.00
55540 4525 (PL)REPAIR BRIDGE ITEM (TYPE B)20EA $1,000.00 $750.00 $1,100.00 $2,600.00 $1,158.93 $1,000.00 $1,600.00
56545 4815 (PL)REPLACE BRIDGE ITEM (TYPE A)7EA $2,500.00 $2,000.00 $2,426.60 $2,200.00 $2,471.43 $1,706.00 $2,100.00
57619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $150,000.00 $80,000.00 $112,200.00 $85,000.00 $123,136.73 $215,000.00 $200,000.00
58202(A) 1301 UNCLASSIFIED EXCAVATION320CY $15.00 $35.00 $22.00 $21.00 $11.59 $50.00 $22.50
59501(G) 6309 CLSM BACKFILL105CY $200.00 $160.00 $172.43 $150.00 $246.27 $240.00 $205.00
60502 1000 TEMPORARY EARTH RETAINAGE1LSUM $5,000.00 $35,000.00 $7,150.00 $20,000.00 $4,346.00 $25,000.00 $75,000.00
61504(A) 1304 APPROACH SLAB306.6SY $210.00 $180.00 $253.17 $190.00 $293.72 $270.00 $260.00
62504(B) 1305 SAW-CUT GROOVING1,265SY $5.00 $4.10 $4.46 $5.00 $5.87 $4.05 $4.50
63504(C) 6250 SEALED EXPANSION JOINT98.6LF $350.00 $220.00 $332.86 $250.00 $383.90 $300.00 $315.00
64504(D) 6245 CONCRETE RAIL (TR4)598.9LF $95.00 $90.00 $130.83 $80.00 $105.75 $130.00 $105.00
65506(A) 1322 STRUCTURAL STEEL5,310LB $6.00 $6.75 $5.43 $7.00 $7.16 $4.94 $6.00
66509 6152 SPECIAL CONCRETE FINISH91SY $50.00 $65.00 $33.00 $13.00 $66.64 $67.00 $60.00
67509(A) 1326 CLASS AA CONCRETE403.6CY $850.00 $750.00 $672.90 $1,000.00 $796.77 $1,300.00 $1,340.00
68509(D) 1331 CLASS C CONCRETE10CY $600.00 $650.00 $347.51 $700.00 $434.60 $2,200.00 $695.00
69510(C) 6137 SLOPE WALL (4")120SY $150.00 $225.00 $163.44 $150.00 $89.82 $130.00 $160.00
70511(B) 6010 EPOXY COATED REINFORCING STEEL98,220LB $1.25 $1.00 $1.30 $1.00 $1.36 $1.00 $1.13
71512(A) 1323 PAINTING EXISTING STRUCTURES1LSUM $50,000.00 $25,000.00 $45,589.50 $52,000.00 $60,040.04 $41,445.00 $47,000.00
72512(B) 6303 COLLECTION AND HANDLING OF WASTE1LSUM $25,000.00 $5,000.00 $2,191.20 $2,600.00 $2,885.75 $1,992.00 $3,800.00
73515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)399SY $5.00 $3.65 $3.85 $5.00 $5.50 $3.50 $5.00
74520(A) 6058 PREPARATION OF CRACKS, ABOVE WATER50LF $40.00 $32.00 $22.00 $26.00 $72.43 $20.00 $22.00
75520(C) 6060 EPOXY RESIN, ABOVE WATER5GAL $80.00 $105.00 $55.00 $65.00 $115.89 $50.00 $110.00
76521(A) 6210 PNEUMATICALLY PLACED MORTAR15SY $90.00 $665.00 $693.00 $800.00 $912.66 $630.00 $750.00
77523(A) 6550 SEALER CRACK PREPARATION99.6LF $5.00 $5.25 $4.40 $5.00 $5.79 $4.00 $4.40
78523(B) 6560 SEALER RESIN2GAL $120.00 $155.00 $165.00 $195.00 $217.30 $150.00 $165.00
79525(A) 0100 (SP)NEST PREVENTION - NETTING1LSUM $10,000.00 $5,000.00 $4,400.00 $17,000.00 $10,140.67 $10,000.00 $8,000.00
80540 4515 (PL)REPAIR BRIDGE ITEM (TYPE A)10EA $500.00 $1,500.00 $1,126.38 $750.00 $1,231.37 $500.00 $3,200.00
81540 4525 (PL)REPAIR BRIDGE ITEM (TYPE B)20EA $1,000.00 $750.00 $1,100.00 $2,600.00 $1,158.93 $1,000.00 $1,600.00
82545 4815 (PL)REPLACE BRIDGE ITEM (TYPE A)11EA $2,500.00 $2,000.00 $2,426.60 $2,200.00 $2,471.43 $1,706.00 $2,100.00
83619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $150,000.00 $67,000.00 $112,200.00 $85,000.00 $123,136.75 $215,000.00 $200,000.00
84805(D) 8744 (PL)REMOVE & RESET LIGHT POLE2EA $5,000.00 $13,000.00 $13,528.31 $16,500.00 $21,730.02 $15,000.00 $14,500.00
85856(A) 8535 TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE)6,038LF $1.00 $1.05 $0.9600 $1.20 $1.45 $1.00 $1.00
86856(B) 8860 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS)8EA $150.00 $365.00 $133.75 $160.00 $507.03 $350.00 $150.00
87857(C) 8851 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)10,584LF $2.00 $1.30 $0.9600 $1.20 $1.81 $1.25 $1.10
88857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)1,464LF $1.00 $1.35 $1.07 $1.30 $1.88 $1.30 $1.20
89871(B) 8705 (SP)CONST.ZONE IMPACT ATTEN.420SD $15.00 $6.50 $5.35 $6.50 $8.69 $6.00 $6.25
90877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER700LF $40.00 $45.00 $21.40 $39.00 $58.24 $40.20 $142.00
91880(A) 8812 ARROW DISPLAY(TYPE C)420SD $5.00 $1.05 $1.07 $1.30 $1.45 $1.00 $2.00
92880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF8,400SD $0.5000 $0.0600 $0.1600 $0.2000 $0.0700 $0.0500 $0.2000
93880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF8,400SD $1.00 $0.0600 $2.68 $3.50 $0.0700 $0.0500 $4.00
94880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF13,860SD $1.00 $0.0600 $0.2700 $0.4000 $0.0700 $0.0500 $0.3000
95880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)5,880SD $1.00 $5.20 $3.75 $4.50 $7.24 $5.00 $4.00
96880(C) 8848 WING BARRICADES1,680SD $1.00 $0.1100 $0.2700 $0.4000 $1.45 $0.1000 $0.4000
97880(E) 8860 WARNING LIGHTS(TYPE A)19,530SD $0.2500 $0.5200 $0.5400 $0.6500 $0.7200 $0.5000 $0.6000
98880(F) 8878 DRUMS43,260SD $0.2000 $0.0600 $0.1100 $0.1500 $0.0700 $0.0500 $0.1200
99882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN1,260SD $20.00 $6.25 $5.35 $6.50 $8.69 $6.00 $6.00
100642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $30,000.00 $9,489.00 $9,951.00 $20,000.00 $13,472.61 $14,000.00 $15,000.00
101641 1399 MOBILIZATION1LSUM $159,100.00 $143,000.00 $142,019.30 $155,000.00 $166,596.78 $290,000.00 $190,000.00