Bid tab 140365

Let Nov 20, 2014 · Division 1 · Muskogee Sign up free

‹ Nov 2014 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-83.5): OVER GRAND RIVER, 0.5 MILES NORTH AND 0.6 MILES WEST OF FORT GIBSON . PROJECT LENGTH = 0.529 MILE

Let date
Thursday, November 20, 2014
Contract
140365
J/P numbers
25419(04)
District
Division 1
County
Muskogee
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-83.5): OVER GRAND RIVER, 0.5 MILES NORTH AND 0.6 MILES WEST OF FORT GIBSON . PROJECT LENGTH = 0.529 MILE
Project number
CIRB-151C(181)RB

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$5,789,265
1 C-GAWF CONSTRUCTION, INC. Low bidder $6,155,742 +6.3%
2 JENSEN CONSTRUCTION COMPANY $6,485,182 +12.0% +5.4%

Bid tab: unit prices 78 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 C-GAWF CONSTRUC…#2 JENSEN CONSTRUC…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $30,000.00 $42,250.00 $67,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION3,857CY $7.50 $10.05 $8.90
3202(D) 0184 UNCLASSIFIED BORROW51,576CY $10.00 $12.55 $11.90
4202(I) 5100 SELECTIVE SUBGRADE TOPPING1LSUM $32,000.00 $45,000.00 $86,200.00
5205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $20,000.00 $37,500.00 $50,500.00
6210 0121 OBLITERATING ABANDONED ROAD1,000LF $6.06 $24.00 $14.20
7221(C) 2801 TEMPORARY SILT FENCE2,500LF $1.78 $2.15 $0.9500
8221(F) 0100 TEMPORARY SILT DIKE200LF $7.58 $9.90 $7.95
9221(G) 0150 TEMPORARY ROCK FILTER DAM TYPE 110CY $100.00 $400.00 $100.00
10230(A) 2806 SOLID SLAB SODDING30,520SY $1.50 $2.16 $1.05
11232(B) 2814 SEEDING METHOD B6AC $478.93 $555.00 $249.00
12233(A) 2817 VEGETATIVE MULCHING6AC $577.64 $825.00 $295.00
13234(A) 2824 FERTILIZING (10-20-10)1.54TON $602.80 $1,150.00 $595.00
14303(A) 2100 AGGREGATE BASE TYPE A3,407CY $50.00 $53.11 $62.00
15325 5271 SEPARATOR FABRIC9,847SY $1.20 $2.50 $2.25
16326(B) 0100 GEOGRID REINFORCEMENT4,000SY $2.00 $4.50 $4.25
17402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E400TON $30.00 $27.00 $35.00
18407(B) 0250 TACK COAT621GAL $3.43 $5.32 $3.00
19408 5774 PRIME COAT5,904GAL $4.95 $7.90 $3.00
20411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,797TON $80.00 $109.00 $77.77
21411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)1,017TON $90.00 $116.00 $88.11
22509(A) 0319 CLASS AA CONCRETE147.3CY $500.00 $450.00 $400.00
23509(D) 0325 CLASS C CONCRETE10CY $350.00 $350.00 $300.00
24511(A) 0332 REINFORCING STEEL19,200LB $1.25 $1.16 $1.00
25613(B) 0689 18" CORR. GALV. STEEL PIPE25LF $29.20 $27.65 $50.00
26613(B) 0690 24" CORR. GALV. STEEL PIPE80LF $33.87 $33.88 $60.00
27613(H) 0450 6" PERFORATED PIPE UNDERDRAIN ROUND175LF $16.36 $19.75 $30.00
28613(I) 1096 6" NON-PERF.PIPE UNDERDRAIN RND.25LF $20.97 $19.75 $30.00
29613(L) 5726 18" PREFAB. CULVERT END SECTION, ROUND2EA $472.13 $1,000.00 $225.00
30613(L) 5730 24" PREFAB. CULVERT END SECTION, ROUND4EA $744.53 $1,250.00 $300.00
31619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $12,000.00 $11,500.00 $21,200.00
32619(B) 4728 REMOVAL OF ASPHALT PAVEMENT2,835SY $4.00 $2.04 $3.50
33623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE150LF $18.52 $20.22 $18.00
34623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,484.39 $2,533.00 $1,675.00
35623(G) 8571 GUARDRAIL END TREATMENT (GET)4EA $2,268.53 $1,974.00 $2,200.00
36501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON240CY $30.00 $25.00 $20.00
37501(G) 6309 CLSM BACKFILL148CY $200.00 $170.00 $230.00
38503(A) 6290 PRESTRESSED CONCRETE BEAMS (TYPE J BT)3,472LF $320.00 $434.70 $375.00
39504(A) 1304 APPROACH SLAB169.8SY $200.00 $155.00 $250.00
40504(B) 1305 SAW-CUT GROOVING3,257.2SY $5.00 $4.47 $4.30
41504(C) 6250 SEALED EXPANSION JOINT70.4LF $300.00 $245.00 $250.00
42504(D) 6239 CONCRETE RAIL (TR3)1,817.2LF $80.00 $62.55 $90.00
43506(A) 1322 STRUCTURAL STEEL6,140LB $4.00 $4.10 $2.00
44507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY16EA $1,500.00 $899.00 $3,000.00
45507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY32EA $1,500.00 $899.00 $3,000.00
46509(A) 1326 CLASS AA CONCRETE914.6CY $800.00 $650.00 $800.00
47509(B) 1328 CLASS A CONCRETE321.5CY $800.00 $610.00 $800.00
48511(A) 1332 REINFORCING STEEL232,550LB $1.00 $1.05 $1.30
49514(A) 6010 PILES, FURNISHED (HP 10X42)144LF $30.00 $36.19 $25.00
50514(A) 6011 PILES, FURNISHED (HP 12X53)545LF $40.00 $35.55 $32.00
51514(B) 6292 PILES, DRIVEN (HP 10X42)144LF $15.00 $22.50 $11.00
52514(B) 6294 PILES, DRIVEN (HP 12X53)545LF $20.00 $22.50 $14.00
53514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00
54516(A) 6096 DRILLED SHAFTS 60" DIAMETER312LF $4,000.00 $3,425.00 $4,000.00
55516(C) 6200 CROSSHOLE SONIC LOGGING2EA $3,000.00 $4,250.00 $1,500.00
56601(B) 1353 TYPE I-A PLAIN RIPRAP1,853TON $50.00 $37.67 $35.00
57601(C) 1355 TYPE I-A FILTER BLANKET155TON $40.00 $30.37 $30.00
58601(H) 1390 TYPE IV GROUTED RIPRAP135SY $65.00 $164.00 $100.00
59613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND64LF $25.00 $40.00 $20.00
60613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.56LF $25.00 $25.00 $20.00
61850(D) 8121 SPECIAL SIGNS4EA $100.00 $505.00 $100.00
62104 0955 (SP) RAILROAD FLAGGING(NON-BIDDABLE)10DAY $400.00 $400.00 $400.00
63850(A) 8110 SHEET ALUMINUM SIGNS52.32SF $18.76 $16.20 $15.00
64851(C) 8324 2" SQUARE TUBE POST76LF $12.28 $13.50 $12.00
65853 9033 DELINEATORS(TYPE 2, CODE 1)19EA $16.03 $33.00 $20.00
66853 9039 DELINEATORS(TYPE 2, CODE 3)2EA $20.00 $30.06 $20.00
67853 9069 GUARDRAIL DELINEATORS(TYPE 2, CODE 1)18EA $15.49 $30.18 $20.00
68854(A) 8800 TRAFFIC STRIPE(PAINT)(4" WIDE)5,000LF $0.2900 $0.4600 $0.1000
69856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)13,440LF $0.6900 $1.01 $0.6500
70856(B) 8870 TRAFFIC STRIPE(MULTI-POLY.)(SYMBOLS)2EA $117.91 $240.00 $200.00
71871(B) 8705 (SP)CONST.ZONE IMPACT ATTEN.300SD $9.15 $2.00 $1.00
72877(A) 8483 PORTABLE LONGITUDINAL BARRIER50LF $50.00 $68.00 $175.00
73877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER800LF $25.59 $63.00 $30.00
74880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $8,254.48 $6,155.00 $5,000.00
75882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN600SD $10.03 $5.50 $5.00
76642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $50,000.00 $42,500.00 $150,000.00
77220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $18,343.00 $5,000.00
78641 1552 MOBILIZATION1LSUM $275,000.00 $307,000.00 $315,000.00