Bid tab 140264

Let Aug 21, 2014 · Division 4 · Grant Sign up free

‹ Aug 2014 results

GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (EW-09): OVER SAND CREEK, 0.40 MILES EAST OF SH -132. PROJECT LENGTH = 0.655 MILES

Let date
Thursday, August 21, 2014
Contract
140264
J/P numbers
28418(04)
District
Division 4
County
Grant
Highway
Limits
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (EW-09): OVER SAND CREEK, 0.40 MILES EAST OF SH -132. PROJECT LENGTH = 0.655 MILES
Project number
CIRB-127C(186)RB

Bidders 10

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,259,483
1 SEWELL BROS., INC. Low bidder $1,374,704 +9.1%
2 Bridges, Inc. DBA Scudder Bridge Co. $1,393,459 +10.6% +1.4%
3 L & M Contractors, Inc. $1,448,030 +15.0% +5.3%
4 BRIDGECO CONTRACTORS, INC. $1,454,357 +15.5% +5.8%
5 B & B BRIDGE COMPANY, LLC $1,464,066 +16.2% +6.5%
6 MERIDIAN CONTRACTING, INC. $1,489,858 +18.3% +8.4%
7 RRY SERVICES LLC $1,525,803 +21.1% +11.0%
8 Reece Construction Co, Inc. $1,545,501 +22.7% +12.4%
9 OBC, INC. $1,563,641 +24.1% +13.7%
10 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES $1,608,879 +27.7% +17.0%

Bid tab: unit prices 52 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SEWELL BROS., I…#2 Bridges, Inc. D…#3 L & M Contracto…#4 BRIDGECO CONTRA…#5 B & B BRIDGE CO…#6 MERIDIAN CONTRA…#7 RRY SERVICES LLC#8 Reece Construct…
1202(H) 0185 EARTHWORK1LSUM $55,000.00 $117,000.00 $105,500.00 $115,000.00 $132,300.00 $137,515.68 $140,000.00 $125,000.00 $137,515.68
2221(C) 2801 TEMPORARY SILT FENCE1,180LF $1.75 $1.33 $2.00 $1.60 $1.27 $1.21 $1.75 $1.35 $1.60
3221(F) 0100 TEMPORARY SILT DIKE644LF $8.50 $5.87 $7.00 $8.00 $5.61 $5.34 $8.50 $6.00 $8.00
4230(A) 2806 SOLID SLAB SODDING21,328SY $1.80 $1.53 $1.34 $1.30 $1.41 $1.34 $1.40 $1.50 $1.30
5233(A) 2817 VEGETATIVE MULCHING4.41AC $400.00 $420.00 $418.00 $200.00 $438.90 $418.00 $250.00 $450.00 $200.00
6307(A) 4200 FLY ASH409TON $75.00 $80.00 $80.00 $80.00 $84.00 $80.00 $90.00 $85.00 $80.00
7307(E) 4240 CEMENTITIOUS STABILIZED SUBGRADE8,973SY $3.25 $3.50 $3.75 $3.75 $3.94 $3.75 $3.00 $4.00 $3.75
8402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E601TON $45.00 $38.00 $43.00 $44.00 $41.34 $40.00 $40.00 $46.43 $42.00
9407(B) 0250 TACK COAT429GAL $6.25 $6.50 $6.00 $6.00 $6.30 $6.00 $7.50 $6.00 $6.00
10408 5774 PRIME COAT3,142GAL $6.50 $6.50 $6.00 $6.00 $6.30 $6.00 $1.50 $6.00 $6.00
11411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)1,971TON $98.00 $117.50 $102.00 $102.00 $107.10 $102.00 $116.00 $103.00 $102.00
12411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)945TON $108.00 $141.00 $118.00 $118.00 $123.90 $118.00 $134.00 $120.00 $118.00
13501(A) 0313 STRUCTURAL EXCAVATION UNCLASSIFIED16CY $15.00 $50.00 $18.00 $50.00 $21.00 $60.00 $49.00 $25.00 $10.00
14509(A) 0319 CLASS AA CONCRETE65CY $525.00 $475.00 $550.00 $635.00 $684.97 $565.00 $560.00 $675.00 $721.00
15509(D) 0325 CLASS C CONCRETE20CY $300.00 $300.00 $350.00 $225.00 $494.14 $450.00 $160.00 $260.00 $380.00
16511(A) 0332 REINFORCING STEEL8,697LB $1.00 $0.9000 $1.10 $1.20 $1.39 $2.00 $1.00 $1.00 $0.8000
17613(B) 0692 36" CORR. GALV. STEEL PIPE170LF $52.00 $40.00 $32.00 $35.00 $32.94 $30.00 $75.00 $80.00 $43.00
18613(M) 7189 TYPE D4 CULVERT END TREATMENT4EA $2,500.00 $1,050.00 $2,000.00 $3,000.00 $1,951.56 $2,150.00 $1,500.00 $2,000.00 $1,810.00
19619(B) 0291 REMOVAL OF HEADWALL2EA $2,000.00 $1,000.00 $1,500.00 $1,000.00 $525.00 $1,500.00 $1,800.00 $600.00 $750.00
20619(B) 4728 REMOVAL OF ASPHALT PAVEMENT7,649SY $4.25 $5.00 $3.25 $5.00 $4.20 $5.00 $2.00 $5.00 $2.50
21619(C) 0924 SAWING PAVEMENT50LF $3.75 $5.00 $5.00 $10.00 $5.25 $10.00 $6.50 $5.00 $5.00
22856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)2,656LF $0.7500 $2.50 $1.79 $2.00 $1.88 $1.79 $2.50 $2.25 $1.79
23501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON190CY $14.50 $15.00 $18.00 $25.00 $12.96 $30.00 $24.00 $25.00 $30.00
24501(G) 6309 CLSM BACKFILL76CY $158.00 $122.00 $210.00 $185.00 $144.69 $160.00 $135.00 $160.00 $198.00
25503(A) 1311 PRESTRESSED CONCRETE BEAMS (TYPE II)537LF $205.00 $184.00 $260.00 $200.00 $171.55 $200.00 $195.00 $200.00 $203.00
26504(B) 1305 SAW-CUT GROOVING445SY $6.25 $7.05 $8.00 $9.50 $6.91 $6.40 $8.00 $7.00 $6.40
27504(C) 6250 SEALED EXPANSION JOINT66.12LF $270.00 $242.00 $325.00 $425.00 $243.26 $265.00 $200.00 $270.00 $312.00
28504(D) 6239 CONCRETE RAIL (TR3)428.2LF $71.00 $65.00 $68.00 $85.00 $73.81 $70.00 $65.00 $75.00 $103.00
29506(A) 1322 STRUCTURAL STEEL1,000LB $3.45 $2.50 $5.00 $4.00 $2.88 $2.75 $2.40 $2.75 $2.00
30507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY9EA $625.00 $1,200.00 $650.00 $500.00 $901.58 $850.00 $450.00 $1,000.00 $931.00
31507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY9EA $625.00 $1,200.00 $650.00 $500.00 $901.58 $850.00 $450.00 $1,000.00 $931.00
32509(A) 1326 CLASS AA CONCRETE141.4CY $565.00 $600.00 $550.00 $660.00 $542.54 $625.00 $940.00 $700.00 $809.00
33509(B) 1328 CLASS A CONCRETE114.6CY $615.00 $600.00 $675.00 $660.00 $534.54 $625.00 $700.00 $725.00 $777.00
34511(A) 1332 REINFORCING STEEL63,542LB $0.9000 $0.9000 $1.10 $0.9500 $1.22 $0.8500 $1.00 $1.05 $0.8000
35514(A) 6010 PILES, FURNISHED (HP 10X42)100LF $30.00 $30.00 $55.00 $65.00 $46.18 $30.00 $104.00 $38.00 $46.00
36514(A) 6011 PILES, FURNISHED (HP 12X53)220LF $38.00 $38.00 $70.00 $70.00 $54.45 $41.50 $104.00 $49.00 $66.00
37514(B) 6292 PILES, DRIVEN (HP 10X42)100LF $16.00 $15.00 $15.00 $10.00 $10.80 $31.50 $44.00 $16.00 $13.00
38514(B) 6294 PILES, DRIVEN (HP 12X53)220LF $12.00 $17.00 $15.00 $9.00 $10.80 $32.00 $44.00 $17.00 $13.00
39514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
40516(A) 6094 DRILLED SHAFTS 48" DIAMETER46LF $695.00 $700.00 $875.00 $1,150.00 $1,182.22 $950.00 $850.00 $1,000.00 $996.00
41601(B) 1353 TYPE I-A PLAIN RIPRAP1,458TON $48.00 $44.00 $48.00 $48.00 $51.54 $52.00 $50.00 $60.00 $54.00
42601(C) 1355 TYPE I-A FILTER BLANKET486TON $40.00 $39.00 $43.00 $43.00 $43.60 $40.00 $44.50 $50.00 $41.00
43613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND60LF $32.00 $20.00 $28.00 $35.00 $28.71 $35.00 $30.00 $20.00 $14.00
44613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.30LF $28.00 $20.00 $30.00 $35.00 $28.71 $35.00 $30.00 $20.00 $14.00
45619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $20,000.00 $15,000.00 $26,000.00 $16,000.00 $10,800.00 $8,435.25 $23,500.00 $30,000.00 $8,435.25
46623(A) 1418 BEAM GUARDRAIL W-BEAM SINGLE100LF $19.00 $17.50 $16.00 $18.00 $17.28 $16.00 $19.00 $18.00 $16.00
47623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,650.00 $1,840.00 $1,670.00 $1,800.00 $1,803.60 $1,670.00 $1,800.00 $1,600.00 $1,670.00
48623(G) 8571 GUARDRAIL END TREATMENT (GET)4EA $2,300.00 $1,965.00 $1,785.00 $1,900.00 $1,927.80 $1,785.00 $1,800.00 $2,300.00 $1,785.00
49880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $3,000.00 $3,355.00 $3,050.00 $3,500.00 $3,294.00 $3,050.00 $4,000.00 $3,300.00 $3,050.00
50642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $12,000.00 $15,000.00 $13,400.00 $16,000.00 $31,763.63 $20,000.00 $12,000.00 $21,000.00 $6,900.00
51220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $4,000.00 $2,000.00 $5,000.00 $4,000.00 $4,792.50 $4,000.00 $1,000.00 $3,000.00 $5,000.00
52641 1399 MOBILIZATION1LSUM $50,000.00 $60,000.00 $48,000.00 $84,000.00 $89,030.53 $119,200.00 $74,480.80 $98,000.00 $166,400.00

Showing the first 8 bidders. The Excel and CSV downloads include all 10.