| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$50,000.00 |
$6,500.00 |
$20,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 1,862 | CY |
$7.50 |
$20.00 |
$8.50 |
$18.00 |
| 3 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$8,000.00 |
$8,500.00 |
$7,392.00 |
$18,000.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,129 | LF |
$2.00 |
$2.99 |
$2.99 |
$3.50 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 98 | LF |
$8.00 |
$14.95 |
$14.95 |
$16.00 |
| 6 | 221(G) 0152 |
TEMPORARY ROCK FILTER DAM TYPE 3 | 200 | CY |
$80.00 |
$35.00 |
$150.00 |
$62.00 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 2,019 | SY |
$1.50 |
$9.95 |
$9.95 |
$11.20 |
| 8 | 232(B) 2814 |
SEEDING METHOD B | 3.32 | AC |
$500.00 |
$6,750.00 |
$6,750.00 |
$7,538.00 |
| 9 | 233(A) 2817 |
VEGETATIVE MULCHING | 3.32 | AC |
$200.00 |
$6,750.00 |
$6,750.00 |
$7,538.00 |
| 10 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 1,234 | CY |
$50.00 |
$46.24 |
$35.00 |
$55.00 |
| 11 | 307(K) 4300 |
STABILIZED SUBGRADE | 5,853 | SY |
$8.00 |
$7.75 |
$5.95 |
$5.75 |
| 12 | 325 5271 |
SEPARATOR FABRIC | 5,853 | SY |
$1.50 |
$1.62 |
$1.11 |
$1.50 |
| 13 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 313 | TON |
$35.00 |
$34.12 |
$20.00 |
$30.50 |
| 14 | 408 5774 |
PRIME COAT | 3,483 | GAL |
$5.50 |
$4.00 |
$5.00 |
$5.00 |
| 15 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 1,691 | TON |
$85.00 |
$81.77 |
$64.00 |
$82.54 |
| 16 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 556 | TON |
$90.00 |
$93.48 |
$78.00 |
$110.00 |
| 17 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$250.00 |
$200.00 |
$300.00 |
$400.00 |
| 18 | 613(B) 0689 |
18" CORR. GALV. STEEL PIPE | 67 | LF |
$35.00 |
$42.00 |
$25.50 |
$50.00 |
| 19 | 613(M) 7196 |
TYPE A6 CULVERT END TREATMENT | 2 | EA |
$1,215.00 |
$1,500.00 |
$1,500.00 |
$1,700.00 |
| 20 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$8,000.00 |
$7,500.00 |
$4,500.00 |
$6,200.00 |
| 21 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 4,140 | SY |
$6.00 |
$6.00 |
$4.00 |
$8.00 |
| 22 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 547 | LF |
$5.00 |
$3.00 |
$3.00 |
$4.50 |
| 23 | 619(C) 0924 |
SAWING PAVEMENT | 72 | LF |
$7.00 |
$20.00 |
$20.00 |
$7.00 |
| 24 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 962 | LF |
$16.00 |
$16.50 |
$16.00 |
$21.00 |
| 25 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$2,700.00 |
$2,200.00 |
$1,895.00 |
$2,650.00 |
| 26 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$2,500.00 |
$1,675.00 |
$1,390.00 |
$2,000.00 |
| 27 | 624(C) 4458 |
FENCE-STYLE SWF (4 BARBED WIRE) | 600 | LF |
$8.00 |
$5.40 |
$9.50 |
$7.69 |
| 28 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 380 | LF |
$10.00 |
$5.70 |
$10.00 |
$7.50 |
| 29 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 250 | CY |
$22.00 |
$100.00 |
$25.00 |
$28.00 |
| 30 | 501(G) 6309 |
CLSM BACKFILL | 288 | CY |
$125.00 |
$375.00 |
$140.00 |
$105.00 |
| 31 | 503(A) 1313 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 1,345 | LF |
$225.00 |
$200.00 |
$275.00 |
$250.00 |
| 32 | 504(A) 1304 |
APPROACH SLAB | 381.4 | SY |
$173.44 |
$75.00 |
$200.00 |
$180.00 |
| 33 | 504(B) 1305 |
SAW-CUT GROOVING | 1,579.9 | SY |
$4.22 |
$4.05 |
$4.05 |
$4.50 |
| 34 | 504(C) 6250 |
SEALED EXPANSION JOINT | 48.9 | LF |
$254.49 |
$50.00 |
$205.00 |
$300.00 |
| 35 | 504(D) 6245 |
CONCRETE RAIL (TR4) | 711 | LF |
$100.00 |
$50.00 |
$90.00 |
$100.00 |
| 36 | 506(A) 1322 |
STRUCTURAL STEEL | 1,575 | LB |
$5.00 |
$1.00 |
$3.00 |
$1.75 |
| 37 | 507(A) 6170 |
STAINLESS STEEL FIXED BEARING ASSEMBLY | 10 | EA |
$2,500.00 |
$2,500.00 |
$1,000.00 |
$1,650.00 |
| 38 | 507(B) 6174 |
STAINLESS STEEL EXPANSION BEARING ASSEMBLY | 20 | EA |
$2,500.00 |
$2,500.00 |
$1,000.00 |
$1,750.00 |
| 39 | 509(A) 1326 |
CLASS AA CONCRETE | 331.8 | CY |
$600.00 |
$200.00 |
$625.00 |
$700.00 |
| 40 | 509(B) 1328 |
CLASS A CONCRETE | 206.9 | CY |
$650.00 |
$600.00 |
$625.00 |
$700.00 |
| 41 | 509(D) 1331 |
CLASS C CONCRETE | 12 | CY |
$511.76 |
$500.00 |
$300.00 |
$325.00 |
| 42 | 511(B) 6010 |
EPOXY COATED REINFORCING STEEL | 124,270 | LB |
$1.05 |
$0.7000 |
$0.9000 |
$1.00 |
| 43 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 84 | LF |
$40.00 |
$21.00 |
$30.00 |
$25.00 |
| 44 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 378 | LF |
$40.80 |
$28.00 |
$35.00 |
$31.00 |
| 45 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 84 | LF |
$13.30 |
$3.00 |
$15.00 |
$95.00 |
| 46 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 378 | LF |
$30.00 |
$3.00 |
$15.00 |
$61.00 |
| 47 | 514(K) 6260 |
(PL)PILOT HOLES | 330 | LF |
$192.71 |
$140.00 |
$225.00 |
$220.00 |
| 48 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 49 | 515(A) 6013 |
WATER REPELLENT (VISUALLY INSPECTED) | 1,301 | SY |
$5.00 |
$3.65 |
$3.65 |
$4.00 |
| 50 | 516(A) 6094 |
DRILLED SHAFTS 48" DIAMETER | 82 | LF |
$800.00 |
$1,000.00 |
$1,600.00 |
$900.00 |
| 51 | 516(C) 6200 |
CROSSHOLE SONIC LOGGING | 1 | EA |
$3,000.00 |
$2,000.00 |
$10,000.00 |
$1,500.00 |
| 52 | 523(A) 6550 |
SEALER CRACK PREPARATION | 46.5 | LF |
$4.35 |
$5.00 |
$5.00 |
$6.00 |
| 53 | 523(B) 6560 |
SEALER RESIN | 0.6 | GAL |
$129.57 |
$200.00 |
$200.00 |
$225.00 |
| 54 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 1,550 | TON |
$34.16 |
$33.14 |
$37.00 |
$38.00 |
| 55 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 295 | TON |
$35.00 |
$24.72 |
$30.00 |
$30.00 |
| 56 | 613(H) 6204 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 96 | LF |
$25.22 |
$75.00 |
$40.00 |
$27.00 |
| 57 | 613(I) 6207 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 60 | LF |
$25.94 |
$65.00 |
$40.00 |
$21.00 |
| 58 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$40,000.00 |
$50,000.00 |
$100,000.00 |
$97,000.00 |
| 59 | 805(A) 8724 |
(PL)REMOVAL OF EXISTING SIGNS | 4 | EA |
$50.00 |
$50.00 |
$50.00 |
$56.00 |
| 60 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 32 | SF |
$30.00 |
$20.00 |
$15.00 |
$22.50 |
| 61 | 851(C) 8330 |
2 1/2" SQUARE TUBE POST | 32 | LF |
$7.00 |
$8.00 |
$10.00 |
$9.00 |
| 62 | 853 9069 |
GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 24 | EA |
$11.00 |
$10.00 |
$12.50 |
$12.00 |
| 63 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 5,200 | LF |
$1.00 |
$1.00 |
$1.00 |
$1.15 |
| 64 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 8,640 | SD |
$0.8000 |
$0.5000 |
$0.3500 |
$0.7000 |
| 65 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 2,160 | SD |
$1.35 |
$1.00 |
$1.00 |
$3.40 |
| 66 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 2,160 | SD |
$5.00 |
$1.00 |
$1.00 |
$1.15 |
| 67 | 880(F) 8878 |
DRUMS | 960 | SD |
$0.5000 |
$0.5000 |
$0.4500 |
$0.5000 |
| 68 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 120 | SD |
$10.00 |
$20.00 |
$15.00 |
$22.50 |
| 69 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$8,000.00 |
$6,600.00 |
$6,200.00 |
$18,000.00 |
| 70 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$1,000.00 |
$2,500.00 |
$2,000.00 |
| 71 | 640(A) 1398 |
FIELD OFFICE | 1 | EA |
$10,000.00 |
$1,000.00 |
$5,000.00 |
$5,500.00 |
| 72 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$118,953.26 |
$65,000.00 |
$130,450.00 |
$110,000.00 |