BRIDGE AND APPROACHES COUNTY ROAD (MEMORIAL RD ): OVER SMITH CREEK, 8.5 MILE EAST OF I-44. PROJECT LENGTH = 0.170 MILES

Let date
Thursday, March 20, 2014
Contract
140130
J/P numbers
26984(04)
District
Division 4
County
Oklahoma
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (MEMORIAL RD ): OVER SMITH CREEK, 8.5 MILE EAST OF I-44. PROJECT LENGTH = 0.170 MILES
Project number
STP-155C(749)AG

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$617,952
1 HASKELL LEMON CONSTRUCTION CO. Low bidder $619,646 +0.3%
2 KLAVER CONSTRUCTION COMPANY, INC. $622,374 +0.7% +0.4%
3 Cimarron Construction Company, LLC $643,936 +4.2% +3.9%
4 Allen Contracting, Inc. $646,643 +4.6% +4.4%
5 OBC, INC. $718,915 +16.3% +16.0%
6 MANHATTAN ROAD & BRIDGE COMPANY, LLC $771,758 +24.9% +24.5%

Bid tab: unit prices 36 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 HASKELL LEMON C…#2 KLAVER CONSTRUC…#3 Cimarron Constr…#4 Allen Contracti…#5 OBC, INC.#6 MANHATTAN ROAD …
1201(A) 0102 CLEARING AND GRUBBING1LSUM $18,185.00 $11,220.00 $20,491.21 $12,000.00 $5,000.00 $22,000.00 $45,000.00
2202(F) 0110 EMBANKMENTS2,909.4CY $15.00 $21.80 $16.34 $14.00 $14.00 $17.60 $20.00
3205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $10,000.00 $21,900.00 $14,085.24 $12,000.00 $4,000.00 $9,350.00 $2,000.00
4221(C) 2801 TEMPORARY SILT FENCE719.9LF $2.00 $2.35 $1.46 $4.00 $5.28 $1.43 $1.35
5221(F) 0100 TEMPORARY SILT DIKE251LF $7.20 $13.50 $7.96 $9.00 $11.89 $7.77 $7.45
6230(A) 2806 SOLID SLAB SODDING2,403.2SY $2.65 $2.75 $2.48 $2.50 $2.97 $2.42 $2.35
7233(A) 2817 VEGETATIVE MULCHING0.5AC $700.00 $1,650.00 $394.39 $2,000.00 $2,641.66 $385.00 $360.00
8241 2832 MOWING0.5AC $120.00 $198.00 $169.02 $250.00 $330.20 $165.00 $155.00
9307(D) 4230 LIME61TON $170.00 $199.00 $185.92 $175.00 $155.00 $172.70 $191.00
10307(H) 4270 LIME STABILIZED SUBGRADE3,385.9SY $3.60 $6.55 $4.28 $6.50 $3.25 $6.60 $7.00
11402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E621.7TON $33.56 $49.60 $42.82 $40.45 $42.00 $47.30 $40.00
12411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)753TON $89.00 $85.50 $91.89 $97.00 $88.50 $88.33 $84.00
13411(C) 5955 SUPERPAVE, TYPE S4(PG 70-28 OK)251TON $101.00 $99.50 $106.98 $110.00 $103.02 $99.55 $98.00
14509(D) 0325 CLASS C CONCRETE10CY $350.00 $334.00 $563.41 $265.00 $600.00 $443.28 $300.00
15613(B) 0690 24" CORR. GALV. STEEL PIPE235.2LF $35.00 $32.80 $39.44 $34.00 $39.00 $29.37 $35.00
16613(M) 7187 TYPE B4 CULVERT END TREATMENT10EA $1,039.00 $1,395.00 $1,170.77 $1,000.00 $1,100.00 $1,389.25 $985.00
17619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $14,431.00 $8,140.00 $16,261.13 $17,000.00 $15,000.00 $22,000.00 $7,000.00
18619(B) 4728 REMOVAL OF ASPHALT PAVEMENT2,241SY $4.00 $4.45 $4.51 $6.00 $5.94 $4.54 $8.50
19619(B) 4780 REMOVAL OF GUARDRAIL164.4LF $3.70 $3.85 $3.95 $5.00 $4.70 $4.40 $6.00
20619(B) 5918 REMOVAL OF EXISTING PIPE104.2LF $13.59 $11.00 $15.31 $17.00 $5.00 $13.20 $16.00
21619(C) 0924 SAWING PAVEMENT50LF $13.60 $11.00 $15.33 $3.00 $6.00 $8.80 $7.00
22623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE412.5LF $5.80 $17.50 $17.86 $18.00 $21.24 $17.44 $23.00
23629(A) 4958 MAILBOX INSTALLATION-SINGLE2EA $17.00 $93.50 $95.78 $100.00 $113.93 $93.50 $132.00
24629(C) 4960 MAILBOX2EA $79.00 $27.50 $28.17 $28.00 $33.51 $27.50 $80.00
25629(D) 4961 REMOVAL OF MAILBOX INSTALLATION2EA $32.00 $55.00 $169.02 $70.00 $52.84 $33.00 $80.00
26501(A) 1306 STRUCTURAL EXCAVATION UNCLASSIFIED218CY $14.00 $15.50 $5.00 $16.00 $15.00 $16.50 $45.00
27509(A) 1326 CLASS AA CONCRETE408.8CY $450.00 $415.00 $396.68 $535.00 $550.00 $501.86 $655.00
28511(A) 1332 REINFORCING STEEL37,617LB $1.00 $1.10 $0.9000 $1.00 $1.10 $1.12 $1.00
29619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $75,000.00 $28,000.00 $50,706.86 $32,000.00 $19,755.00 $71,500.00 $46,207.00
30623(G) 8580 GUARDRAIL END TREATMENT (SRT)4EA $1,800.00 $2,420.00 $2,524.07 $2,675.00 $3,002.18 $2,464.00 $1,985.00
31854(A) 8800 TRAFFIC STRIPE(PAINT)(4" WIDE)1,800LF $0.2000 $0.2900 $0.3000 $0.3500 $0.3600 $0.3000 $0.6300
32880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $1,600.00 $1,656.42 $2,900.00 $1,970.19 $1,617.00 $2,600.00
33642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $15,000.00 $8,000.00 $8,732.85 $14,000.00 $10,236.39 $8,525.00 $8,000.00
34220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $3,000.00 $5,070.68 $7,000.00 $2,124.16 $2,750.00 $1,850.00
35641 1399 MOBILIZATION1LSUM $15,000.00 $34,750.00 $37,563.53 $16,000.00 $57,000.00 $57,077.08 $63,500.00
36624(C) 4459 FENCE-STYLE SWF (5 BARBED WIRE)250LF $9.00 $12.00 $28.17 $15.00 $15.85 $13.20 $12.50