| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$15,000.00 |
$11,000.00 |
$20,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 10,186 | CY |
$4.75 |
$4.95 |
$5.35 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 1,000 | CY |
$6.50 |
$6.60 |
$8.35 |
| 4 | 205(A) 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$10,520.00 |
$10,450.00 |
$11,500.00 |
| 5 | 221(C) 2801 |
TEMPORARY SILT FENCE | 933 | LF |
$3.00 |
$2.20 |
$1.60 |
| 6 | 221(G) 0150 |
TEMPORARY ROCK FILTER DAM TYPE 1 | 9 | CY |
$100.00 |
$110.00 |
$150.00 |
| 7 | 229 4318 |
DITCH LINER PROTECTION | 171 | LF |
$1.75 |
$1.10 |
$1.70 |
| 8 | 230(A) 2806 |
SOLID SLAB SODDING | 9,456 | SY |
$1.40 |
$1.98 |
$1.60 |
| 9 | 232(B) 2814 |
SEEDING METHOD B | 3.85 | AC |
$600.00 |
$660.00 |
$300.00 |
| 10 | 233(A) 2817 |
VEGETATIVE MULCHING | 3.85 | AC |
$775.00 |
$550.00 |
$300.00 |
| 11 | 241 2832 |
MOWING | 3.85 | AC |
$60.00 |
$55.00 |
$200.00 |
| 12 | 307(A) 4200 |
FLY ASH | 97 | TON |
$75.00 |
$107.25 |
$115.00 |
| 13 | 307(D) 4230 |
LIME | 11 | TON |
$145.00 |
$203.50 |
$220.00 |
| 14 | 307(E) 4240 |
CEMENTITIOUS STABILIZED SUBGRADE | 1,787 | SY |
$2.80 |
$7.15 |
$7.50 |
| 15 | 307(G) 4260 |
LIME PRETREATMENT | 590 | SY |
$2.50 |
$5.50 |
$5.50 |
| 16 | 317 4270 |
CEMENT TREATED BASE | 1,503 | SY |
$10.50 |
$38.50 |
$41.00 |
| 17 | 325 5271 |
SEPARATOR FABRIC | 1,787 | SY |
$1.50 |
$3.30 |
$3.50 |
| 18 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 237 | TON |
$22.00 |
$33.55 |
$36.00 |
| 19 | 407(B) 0250 |
TACK COAT | 9 | GAL |
$3.00 |
$22.00 |
$23.00 |
| 20 | 408 5774 |
PRIME COAT | 394 | GAL |
$4.50 |
$27.50 |
$29.00 |
| 21 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 25 | TON |
$200.00 |
$143.00 |
$150.00 |
| 22 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 10 | TON |
$300.00 |
$258.50 |
$270.00 |
| 23 | 414(A) 0210 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 640 | SY |
$12.50 |
$18.28 |
$25.00 |
| 24 | 414(B) 5725 |
DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 534 | SY |
$15.00 |
$21.72 |
$30.00 |
| 25 | 414(G) 5275 |
P.C. CONCRETE FOR PAVEMENT | 261 | CY |
$150.00 |
$135.71 |
$135.00 |
| 26 | 509(D) 0325 |
CLASS C CONCRETE | 32 | CY |
$275.00 |
$437.93 |
$250.00 |
| 27 | 613(B) 0689 |
18" CORR. GALV. STEEL PIPE | 44 | LF |
$24.50 |
$26.95 |
$26.00 |
| 28 | 613(H) 0450 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 150 | LF |
$10.00 |
$12.57 |
$20.00 |
| 29 | 613(I) 1096 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 50 | LF |
$8.50 |
$12.57 |
$20.00 |
| 30 | 613(M) 7186 |
TYPE A4 CULVERT END TREATMENT | 2 | EA |
$650.00 |
$1,134.15 |
$1,100.00 |
| 31 | 613(Q) 5946 |
OUTLET LATERAL HEADWALL | 1 | EA |
$500.00 |
$278.03 |
$1,200.00 |
| 32 | 613(U) 1100 |
PIPE UNDERDRAIN COVER MAT'L. | 45 | CY |
$30.00 |
$56.09 |
$66.00 |
| 33 | 613(V) 1180 |
TRENCH EXCAVATION | 60 | CY |
$10.00 |
$11.00 |
$10.00 |
| 34 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$10,000.00 |
$6,600.00 |
$10,000.00 |
| 35 | 619(B) 4727 |
REMOVAL OF CONCRETE PAVEMENT | 1,174 | SY |
$4.25 |
$4.68 |
$13.00 |
| 36 | 619(C) 0924 |
SAWING PAVEMENT | 1,088 | LF |
$3.50 |
$4.40 |
$2.25 |
| 37 | 624(C) 4459 |
FENCE-STYLE SWF (5 BARBED WIRE) | 1,686 | LF |
$5.00 |
$3.83 |
$5.50 |
| 38 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 3,660 | CY |
$6.00 |
$4.95 |
$7.00 |
| 39 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 261 | CY |
$14.00 |
$22.00 |
$15.00 |
| 40 | 509(A) 1326 |
CLASS AA CONCRETE | 726.2 | CY |
$425.00 |
$310.87 |
$480.00 |
| 41 | 511(A) 1332 |
REINFORCING STEEL | 124,220 | LB |
$0.8500 |
$0.7500 |
$0.9000 |
| 42 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$4,250.00 |
$16,060.00 |
$17,000.00 |
| 43 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 2,520 | LF |
$0.4400 |
$1.18 |
$1.27 |
| 44 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 7,200 | SD |
$0.2200 |
$0.8000 |
$0.8700 |
| 45 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 630 | SD |
$0.6300 |
$0.8000 |
$0.8700 |
| 46 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 975 | SD |
$0.8500 |
$0.8000 |
$0.8700 |
| 47 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 600 | SD |
$0.4900 |
$0.8000 |
$0.8700 |
| 48 | 880(C) 8848 |
WING BARRICADES | 300 | SD |
$0.7100 |
$0.0200 |
$0.0200 |
| 49 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 2,175 | SD |
$0.1100 |
$0.1700 |
$0.1800 |
| 50 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 150 | SD |
$13.05 |
$5.50 |
$5.95 |
| 51 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$9,260.00 |
$4,950.00 |
$6,500.00 |
| 52 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$1,500.00 |
$2,750.00 |
$5,000.00 |
| 53 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$55,000.00 |
$69,172.10 |
$38,000.00 |