ODOT Bid Results

Jun 2015 · 29 let jobs Sign up free
29Let jobs
$54,748,871Total low bids
$52,509,925Total estimates
+4.3%Low bids vs estimates

Jun 2015 results

Bid tabs (Excel) ExcelCSV
Let dateContractCounty / DistrictProject EstimateLow bidLow bidder% vs est.Bidders
Jun 18, 2015 150214STP-164C(116)SS Pushmataha
Division 2
GRADE, DRAIN, AND SURFACE - DIVISION II SH-93: FROM THE CHOCTAW COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 2.791 MILES · $7,690,811 $8,957,820 THE CUMMINS CONSTRUCTION CO., INC. +16.5% 2
Jun 18, 2015 150219SBR-272N(114)SB Ssp-272n(123)ss
TULSA, WASHINGTON PAVEMENT AND BRIDGE REHABILITATION - DIVISION VIII US-75: FROM SH-20, EXTEND NORTH NEAR COLLINSVILLE. PROJECT LENGTH = 2.881 MILES · $7,600,840 $7,094,096 SHERWOOD CONSTRUCTION CO., INC. -6.7% 2
Jun 18, 2015 150213PLHD-261N(013)DC Pittsburg
Division 2
INTERCHANGE - DIVISION II CITY STREET (C-TREE ROAD): AT THE US-69 INTERCHANGE, IN SAVANNA . PROJECT LENGTH = 0.255 MILE · $6,815,054 $6,324,153 L & N BRIDGE, LLC -7.2% 5
Jun 18, 2015 150163CIRB-126C(131)RB Grady
Division 7
GRADE, DRAIN, AND SURFACE - DIVISION VII COUNTY ROAD (SARA ROAD ): FROM 0.50 MILES NORTH OF I -44 NEAR NEWCASTLE, EXTEND NORTH . PROJECT LENGTH = 4.042 MILES · $4,430,278 $4,393,434 SHELL CONSTRUCTION CO., INC/MARKWELL PAVING CO., INC (JV) -0.8% 2
Jun 18, 2015 150197CIRB-133C(095)RB Jackson
Division 5
GRADE, DRAIN, SURFACE , AND BRIDGE - DIVISION V COUNTY ROAD (NS-210): FROM SH-5, EXTEND NORTH NEAR ALTUS . PROJECT LENGTH = 4.013 MILES · $3,947,571 $4,150,099 KLAVER CONSTRUCTION COMPANY, INC. +5.1% 1
Jun 18, 2015 150184SBR-249N(022)SB Mayes
Division 8
BRIDGE REHABILITATION - DIVISION VIII US-69: OVER THE UNION PACIFIC RAILROAD , 4.9 MILES NORTH OF SH -20. PROJECT LENGTH = 0.167 MILE · $2,549,486 $3,171,500 BECCO CONTRACTORS, INC. +24.4% 4
Jun 18, 2015 150199NHPP-234N(015)SS Jefferson
BRIDGE AND APPROACHES - DIVISION VII US-81: OVER FLAT CREEK , 7.88 MILES NORTH OF THE TEXAS STATE LINE . PROJECT LENGTH = 0.208 MILE · $2,378,793 $2,516,113 OBC, INC. +5.8% 3
Jun 18, 2015 150207STP-249C(023)CI Mayes
Division 8
RESURFACE (P.C. CONCRETE) - DIVISION VIII COUNTY ROAD (NS-435/TRUE ROAD): FROM NE 1ST STREET (EW-49) IN PRYOR CREEK , EXTEND NORTH . PROJECT LENGTH = 5.038 MILES · $2,754,077 $2,230,907 DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV -19.0% 5
Jun 18, 2015 150223STP-158B(122)SS Ottawa
Division 8
BRIDGE AND APPROACHES US -59: OVER LITTLE HORSE CREEK, 4.5 MILES NORTHWEST OF THE DELAWARE COUNTY LINE NEAR AFTON . PROJECT LENGTH = 0.207 MILE · $2,046,642 $2,039,440 Crossland Construction Company, Inc. -0.4% 2
Jun 18, 2015 150190NHPP-219N(036)SS Creek
Division 8
BRIDGE REHABILITATION - DIVISION VIII US-75A: OVER ROCK CREEK, 0.30 MILES SOUTH OF THE SH-117 JUNCTION IN SAPULPA. PROJECT LENGTH = 0.064 MILE · $1,925,723 $1,875,234 M.J. HUGHES CONSTRUCTION, INC. -2.6% 4
Jun 18, 2015 150196SSR-227C(017)SR Grant
Division 4
RESURFACE (ASPHALT ) - DIVISION IV SH-132: FROM 0.10 MILES SOUTH OF THE GARFIELD COUNTY LINE , EXTEND NORTH NEAR PRAIRIE . PROJECT LENGTH = 5.190 MILES · $1,376,900 $1,459,500 Venture Corporation dba VCO Paving +6.0% 2
Jun 18, 2015 150208HSIPIG-3500(010)TR Carter, Murray
SAFETY IMPROVEMENT (CABLE BARRIER) - DIVISION VII I-35: FROM MILE MARKER 44, EXTEND NORTH NEAR TURNER FALLS . PROJECT LENGTH = 7.08 MILES · $1,464,358 $1,386,375 ACTION SAFETY SUPPLY CO., LLC -5.3% 4
Jun 18, 2015 150212SSR-255A(344)SR Ssr-255a(345)sr
OKLAHOMA RESURFACE (ASPHALT ) - DIVISION IV US-62: FROM THE I -35 JCT NEAR FOREST PARK , EXTEND EAST, AND FROM 0.05 MI WEST OF HIWASSEE ROAD , EXTEND EAST IN CHOCTAW . PROJECT LENGTH = 3.480 MILES · $1,328,750 $1,326,000 HASKELL LEMON CONSTRUCTION CO. -0.2% 2
Jun 18, 2015 150202SBR-238N(029)SB Kiowa
Division 5
BRIDGE REHABILITATION - DIVISION V US-183: OVER US-62, 2.1 MILES EAST OF THE TILLMAN COUNTY LINE . PROJECT LENGTH = 0.083 MILE · $1,337,716 $1,041,349 HASKELL LEMON CONSTRUCTION CO. -22.2% 3
Jun 18, 2015 150192SBR-220C(027)SB Custer
Division 5
BRIDGE REHABILITATION - DIVISION V SH-44: OVER OAK CREEK, 4.7 MILES NORTH OF THE I -40 JUNCTION. PROJECT LENGTH = 0.175 MILE · — $997,305 HASKELL LEMON CONSTRUCTION CO. 3
Jun 18, 2015 150193NHPP-221N(020)SS Delaware
Division 8
WIDEN AND RESURFACE - DIVISION VIII US-412: FROM THE ARKANSAS STATE LINE , EXTEND WEST. PROJECT LENGTH = 0.065 MILE · $817,264 $978,879 Paragon Contractors, LLC +19.8% 3
Jun 18, 2015 150198STP-234D(022)CI Jefferson
BRIDGE AND APPROACHES - DIVISION VII COUNTY ROAD (NS-296): OVER WEST MUD CREEK , 4.0 MILES NORTH OF SH -32 NEAR CORNISH. PROJECT LENGTH = 0.207 MILE · $616,285 $739,029 RRY SERVICES LLC +19.9% 3
Jun 18, 2015 150200SSR-236C(027)SR Kay
Division 4
RESURFACE (UTBWC) - DIVISION IV US-177: FROM I-35, EXTEND NORTHWEST TO THE KANSAS STATE LINE. PROJECT LENGTH = 5.310 MILES · $662,070 $679,607 Evans & Associates Construction Co., Inc. +2.6% 2
Jun 18, 2015 150221SBR-146N(134)SB Mcintosh
Division 1
BRIDGE REHABILITATION - DIVISION I I-40: OVER PIERCE ROAD, 9.31 MILES EAST OF THE OKMULGEE COUNTY LINE . · $613,009 $625,649 PBX Corporation +2.1% 4
Jun 18, 2015 150195STP-227C(016)CI Grant
Division 4
BRIDGE AND APPROACHES - DIVISION IV COUNTY ROAD (NS-296): OVER UNNAMED CREEK, 6.5 MILES NORTH OF SH -11 IN MEDFORD. PROJECT LENGTH = 0.236 MILE · $533,331 $574,754 L & M Contractors, Inc. +7.8% 5
Jun 18, 2015 150194CIRB-222D(020)RB Dewey
Division 5
BRIDGE AND APPROACHES - DIVISION V COUNTY ROAD (EW-62): OVER KIZER CREEK, 7.9 MILES EAST AND 2.0 MILES SOUTH OF VICI. PROJECT LENGTH = 0.132 MILE · $404,605 $530,316 K & R BUILDERS, INC. +31.1% 3
Jun 18, 2015 150187CIRB-205D(037)RB Beckham
Division 5
BRIDGE AND APPROACHES - DIVISION V COUNTY ROAD (EW-120): OVER INDIAN CREEK, 0.50 MILES WEST OF THE SH -34 JUNCTION. PROJECT LENGTH = 0.161 MILE · $335,368 $422,169 RRY SERVICES LLC +25.9% 2
Jun 18, 2015 150186NHPP-201N(014)RW Adair
Division 1
RIGHT-OF-WAY CLEARANCE - DIVISION I US-59: FROM 6.95 MILES NORTH OF WESTVILLE , EXTEND NORTH . PROJECT LENGTH = 3.314 MILES PRE-QUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · — $352,500 J.E. DIRT WURX, LLC 6
Jun 18, 2015 150201SSR-237N(025)SR Kingfisher
Division 4
RESURFACE (UTBWC) - DIVISION IV US-81: FROM 0.54 MILES NORTH OF THE CANADIAN COUNTY LINE, EXTEND NORTH . PROJECT LENGTH = 3.220 MILES · $317,550 $336,699 HASKELL LEMON CONSTRUCTION CO. +6.0% 1
Jun 18, 2015 150206HSIPIG-3500(007) Mcclain
Division 3
SAFETY IMPROVEMENT (CABLE BARRIER) - DIVISION III I-35: FROM MILE MARKER 98.5 TO MILE MARKER 99.5, AND FROM MILE MARKER 104.5 TO MILE MARKER 105.5 IN GOLDSBY. · $225,702 $234,479 ACTION SAFETY SUPPLY CO., LLC +3.9% 4
Jun 18, 2015 150216HSIP-272B(087)TR Tulsa
Division 8
TRAFFIC SIGNALS - DIVISION VIII US-75: AT THE SH-117 JUNCTION IN GLENPOOL. · — $139,366 Midstate Traffic Control, Inc. 3
Jun 18, 2015 150222STPY-255F(296)DC Mayes
Division 8
HIGH FRICTION SURFACE COURSE - DIVISION VIII SH-20: AT NS-442 NEAR SALINA. PROJECT LENGTH = 0.100 MILE · $60,864 $69,114 ACTION SAFETY SUPPLY CO., LLC +13.6% 2
Jun 18, 2015 150209NHPPI-3500(012)RW Oklahoma
Division 4
RIGHT-OF-WAY CLEARANCE - DIVISION IV I-240: AT THE I-35 INTERCHANGE IN OKLAHOMA CITY . PROJECT LENGTH = 0.944 MILE PRE-QUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · $244,311 $56,750 MIDWEST WRECKING, INC. -76.8% 3
Jun 18, 2015 150218HSIPG-277F(027)TR Jackson, Woodward
TRAFFIC SIGNAL BACKPLATE - DIVISION V AND VI US -183/US-283/US-412/SH-15/SH-34/CITY STREETS: AT MULTIPLE LOCATIONS IN DIVISION V AND VI. · $32,568 $46,235 Midstate Traffic Control, Inc. +42.0% 3
1–29 of 29