30Let jobs
$23,634,055Total low bids
$21,842,175Total estimates
+8.2%Low bids vs estimates
Aug 2011 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 18, 2011 | 110382CIRB-146C(085)RB | Mcintosh Division 1 |
BRIDGE REHABILITATION AND APPROACHES COUNTY ROAD (TEXANNA ROAD ): OVER DUCHESS CREEK, 3.0 MILES WEST OF THE MUSKOGEE COUNTY LINE AT LAKE EUFAULA . PROJECT LENGTH = 0.331 MILES · | $3,119,637 | $3,480,844 | JENSEN CONSTRUCTION COMPANY | +11.6% | 3 |
| Aug 18, 2011 | 110380STP-136D(117)CI | Kay Division 4 |
GRADE, DRAIN, AND SURFACE CITY STREETS : ON HUBBARD RD IN PONCA CITY , FROM WAVERLY RD EXTEND EAST. ON WAVERLY RD , FROM HUBBARD RD, EXTEND SOUTH. PROJECT LENGTH = 0.175 MILES · | $3,288,822 | $3,181,697 | Evans & Associates Construction Co., Inc. | -3.3% | 2 |
| Aug 18, 2011 | 110374IMG-0040-4(434)120TR | Nhg-011n(088)tr |
CANADIAN SAFETY IMPROVEMENT (CABLE BARRIER) I-40: FROM 9.0 MILES WEST OF THE US -81 JCT, EXTEND EAST. US-81: FROM 5.0 MILES SOUTH OF THE SH -66 JCT, EXTEND NORTH . PROJECT LENGTH = 14.15 MILES · | $2,523,564 | $2,574,390 | JLT Contracting, LLC | +2.0% | 2 |
| Aug 18, 2011 | 110395NHY-018N(057) | Craig Division 8 |
BRIDGE AND APPROACHES US -60: OVER SL & SF RAILROAD, 0.60 MILES NORTHWEST OF THE SH-66 JUNCTION. PROJECT LENGTH = 0.364 MILES · | $2,850,605 | $2,284,074 | OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) | -19.9% | 3 |
| Aug 18, 2011 | 110371NHG-013N(144)TR | Nhg-013n(145)tr |
BRYAN SAFETY IMPROVEMENT (CABLE BARRIER AND GUARDRAIL ) US-69: FROM THE OKLAHOMA /TEXAS STATE LINE, EXTEND NORTH . · | $1,928,504 | $2,001,223 | Midstate Traffic Control, Inc. | +3.8% | 4 |
| Aug 18, 2011 | 110295NHY-009N(097)SS | Kiowa Division 5 |
GRADE, DRAIN, AND BRIDGE US-183: FROM 1.8 MILES NORTH OF THE SH -9 WEST JUNCTION , EXTEND NORTH . PROJECT LENGTH = 2.268 MILES · | — | $1,081,603 | CORNELL CONSTRUCTION COMPANY, INC. | 6 | |
| Aug 18, 2011 | 110377BRFY-119C(102) | Creek Division 8 |
BRIDGE AND APPROACHES SH -16: OVER ROCK CREEK, 2.2 MILES EAST OF THE SH -48 JUNCTION. PROJECT LENGTH = 0.099 MILES · | $1,166,250 | $955,790 | OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) | -18.0% | 6 |
| Aug 18, 2011 | 110383CIRB-146C(100)RB | Mcintosh Division 1 |
BRIDGE REHABILITATION COUNTY ROAD (EW-122): OVER LAKE EUFAULA , 3.0 MILES SOUTH OF SH-9 IN VIVIAN AND 6.5 MILES WEST OF US -69. PROJECT LENGTH = 0.965 MILES · | $977,012 | $948,053 | C-GAWF CONSTRUCTION, INC. | -3.0% | 2 |
| Aug 18, 2011 | 110306MC-155D(836) | Oklahoma Division 4 |
PAVEMENT REHABILITATION (P. C. CONCRETE) CITY STREETS (NE 23RD STREET): FROM WALNUT STREET, EXTEND EAST. PROJECT LENGTH = 0.50 MILES · | $565,110 | $824,622 | RUDY CONSTRUCTION CO. | +45.9% | 3 |
| Aug 18, 2011 | 110381BRO-145D(129)CI | Mccurtain Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-206.5): OVER LUKFATA CREEK , 3.0 MILES WEST OF THE US-259 JUNCTION. PROJECT LENGTH = 0.150 MILES · | — | $667,332 | HUB Construction, Inc. | 1 | |
| Aug 18, 2011 | 110386BRO-157D(094)CO | Osage Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-365): OVER CLEAR CREEK, 1.0 MILE SOUTH OF THE US-60 JUNCTION. PROJECT LENGTH = 0.204 MILES · | $704,762 | $643,520 | BELK BRIDGE, INC. | -8.7% | 7 |
| Aug 18, 2011 | 110318MC-136A(208) | Kay Division 4 |
RESURFACE (ASPHALT ) US-60B: FROM ASH STREET , EXTEND EAST IN PONCA CITY . PROJECT LENGTH = 1.21 MILES · | $524,496 | $597,432 | Evans & Associates Construction Co., Inc. | +13.9% | 2 |
| Aug 18, 2011 | 110394NHG-013N(143)TR | Wagoner Division 1 |
SAFETY IMPROVEMENT (CABLE BARRIER) US-69: FROM 3.6 MILES SOUTH OF THE MAYES COUNTY LINE, EXTEND NORTH . · | $562,561 | $538,478 | Midstate Traffic Control, Inc. | -4.3% | 3 |
| Aug 18, 2011 | 110370BRF-107C(069)CI | Bryan Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-366): OVER NEWBERRY CREEK , 1.1 MILES NORTH OF THE US -70 JUNCTION. PROJECT LENGTH = 0.217 MILES · | $550,800 | $515,085 | Treas Construction Inc | -6.5% | 5 |
| Aug 18, 2011 | 110392BRO-166D(139)CI | Rogers Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-50): OVER PANTHER CREEK , 3.2 MILES EAST OF I-44. PROJECT LENGTH = 0.198 MILES · | $520,771 | $456,120 | B & B BRIDGE COMPANY, LLC | -12.4% | 6 |
| Aug 18, 2011 | 110375BRFY-NBIP(446)3B | Comanche Division 7 |
BRIDGE PAINTING I-44: 1.7 MILES NORTH OF US-62. · | $467,850 | $410,599 | K.V.K. CONTRACTING, INC. | -12.2% | 8 |
| Aug 18, 2011 | 110373BRF-108C(277)CI | Caddo Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-261): OVER CEDAR CREEK, 6.0 MILES SOUTH OF THE SH-8/SH-152 JUNCTION IN BINGER. PROJECT LENGTH = 0.160 MILES · | — | $339,056 | SEWELL BROS., INC. | 3 | |
| Aug 18, 2011 | 110391BRFY-165C(122)3B | Custer, Roger Mills |
JOINT SEAL/REPAIR I-40BUS/SH-47: AT VARIOUS LOCATIONS IN DIVISION V. · | $413,658 | $292,921 | PBX Corporation | -29.2% | 8 |
| Aug 18, 2011 | 110387BRFY-NBIP(441)3B | Leflore, Mccurtain, Pushmataha |
BRIDGE PAINTING US-259/SH-3/SH-112: AT VARIOUS LOCATIONS IN DIVISION II. · | $318,835 | $269,944 | POSEIDON CONSTRUCTION, INC. | -15.3% | 8 |
| Aug 18, 2011 | 110352BRF-132C(076)CI | Hughes Division 3 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-119): OVER UNNAMED CREEK, 3.7 MILES WEST OF THE SH-27 JUNCTION. PROJECT LENGTH = 0.198 MILES · | — | $250,530 | BRIDGECO CONTRACTORS, INC. | 7 | |
| Aug 18, 2011 | 110388BRFY-164A(166)3B | Leflore, Mccurtain, Pushmataha |
JOINT SEAL/REPAIR US-259/SH-3/SH-98/SH-112: AT VARIOUS LOCATIONS IN DIVISION II. · | $222,646 | $215,951 | B & B CONSTRUCTION SERVICE J.T., INC. | -3.0% | 5 |
| Aug 18, 2011 | 110384BRFY-NBIP(440)3B | Muskogee Division 1 |
BRIDGE PAINTING I-40: OVER COUNTY ROAD, 2.8 MILES EAST OF THE MCINTOSH COUNTY LINE. · | $281,970 | $196,715 | TARPON INDUSTRIAL, INC. | -30.2% | 7 |
| Aug 18, 2011 | 110389BRO-165D(118)CI | Roger Mills Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-175): OVER CAMP HOLLOW CREEK , 4.0 MILES NORTH OF SH -47. PROJECT LENGTH = 0.101 MILES · | — | $184,804 | SEWELL BROS., INC. | 5 | |
| Aug 18, 2011 | 110325STP-114B(276)AG | Cleveland Division 3 |
PEDESTRIAN IMPROVEMENT CITY STREET (12TH STREET): FROM SANTA FE AVE , EXTEND EAST TO JANEWAY AVE IN THE CITY OF MOORE. PROJECT LENGTH = 0.52 MILES · | $186,492 | $158,342 | RUDY CONSTRUCTION CO. | -15.1% | 6 |
| Aug 18, 2011 | 110393HSIPG-172B(524)TR | Tulsa Division 8 |
SAFETY IMPROVEMENT (GUARDRAIL AND CHEVRON ) SH-51/SH-151: AT MULTIPLE RAMP LOCATIONS AT THE INTERCHANGE OF SH -51 AND SH-151. · | $169,333 | $135,370 | Midstate Traffic Control, Inc. | -20.1% | 2 |
| Aug 18, 2011 | 110231STPY-107C(174)RW | Bryan Division 2 |
RIGHT-OF-WAY CLEARANCE SH-78: FROM 0.25 MILES NORTH OF THE US -69 JUNCTION, EXTEND NORTH . · | $130,000 | $118,700 | SCHIRALLI CONSTRUCTION CORP. | -8.7% | 4 |
| Aug 18, 2011 | 110369HSIPG-105C(201)TR | Beckham, Blaine, Roger Mills, Washita |
SAFETY IMPROVEMENT (RUMBLE STRIP) SH-6/SH-44/SH-51A/SH-152: AT VARIOUS LOCATIONS IN DIVISION V. · | $167,190 | $93,900 | SURFACE PREPARATION TECHNOLOGIES, LLC | -43.8% | 5 |
| Aug 18, 2011 | 110385BRFY-151N(239)3B | Muskogee Division 1 |
JOINT SEAL/REPAIR I-40: OVER COUNTY ROAD, 2.8 MILES EAST OF THE MCINTOSH COUNTY LINE. · | $127,922 | $85,439 | PBX Corporation | -33.2% | 7 |
| Aug 18, 2011 | 110390BRFY-NBIP(444)3B | Roger Mills Division 5 |
BRIDGE PAINTING SH -47: OVER THE EAST CROTEN CREEK , 7.2 MILES EAST OF THE SH -30 JUNCTION. · | $73,388 | $72,705 | TARPON INDUSTRIAL, INC. | -0.9% | 8 |
| Aug 18, 2011 | 110333BRFY-147C(170) | Cimarron, Ellis, Major, Woods |
BRIDGE WATER PROOF SEAL US -64/US-283/US-287/SH-8/SH-58: AT VARIOUS LOCATIONS IN DIVISION VI. · | — | $58,818 | GARY A. CRAIN, INC. | 2 |
1–30 of 30
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.