BRIDGE AND APPROACHES COUNTY ROAD (EW-119): OVER UNNAMED CREEK, 3.7 MILES WEST OF THE SH-27 JUNCTION. PROJECT LENGTH = 0.198 MILES

Let date
Thursday, August 18, 2011
Contract
110352
J/P numbers
21775(04)
District
Division 3
County
Hughes
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-119): OVER UNNAMED CREEK, 3.7 MILES WEST OF THE SH-27 JUNCTION. PROJECT LENGTH = 0.198 MILES
Project number
BRF-132C(076)CI

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 BRIDGECO CONTRACTORS, INC. Low bidder $250,530
2 SEWELL BROS., INC. $258,191 +3.1%
3 K & R BUILDERS, INC. $260,320 +3.9%
4 Cimarron Construction Company, LLC $275,583 +10.0%
5 B & B BRIDGE COMPANY, LLC $281,125 +12.2%
6 C-GAWF CONSTRUCTION, INC. $292,405 +16.7%
7 Treas Construction Inc $292,648 +16.8%

Bid tab: unit prices 28 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 BRIDGECO CONTRA…#2 SEWELL BROS., I…#3 K & R BUILDERS,…#4 Cimarron Constr…#5 B & B BRIDGE CO…#6 C-GAWF CONSTRUC…#7 Treas Construct…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $4,000.00 $4,000.00 $4,500.00 $5,750.00 $5,000.00 $2,500.00 $5,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION2,051CY $7.00 $6.30 $5.00 $4.85 $5.20 $3.50 $10.00 $7.00
3202(D) 0184 UNCLASSIFIED BORROW6,041CY $10.00 $5.50 $7.00 $5.90 $6.65 $5.00 $8.00 $7.00
4221(C) 2801 TEMPORARY SILT FENCE2,100LF $2.10 $1.50 $1.50 $1.10 $2.00 $1.55 $1.95 $1.30
5221(F) 0100 TEMPORARY SILT DIKE240LF $10.00 $8.00 $8.00 $6.65 $6.00 $7.00 $5.00 $6.95
6230(A) 2806 SOLID SLAB SODDING7,976SY $1.30 $1.65 $1.55 $1.57 $1.65 $1.49 $1.75 $1.40
7233(A) 2817 VEGETATIVE MULCHING4AC $300.00 $450.00 $550.00 $150.00 $400.00 $500.00 $750.00 $450.00
8402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,146TON $25.00 $23.00 $26.00 $23.77 $22.00 $26.50 $23.00 $31.60
9509(D) 0325 CLASS C CONCRETE10CY $300.00 $200.00 $300.00 $225.00 $300.00 $250.00 $175.00 $360.00
10613(B) 4528 28" X 20" CORR. GALV. STEEL PIPE ARCH46LF $25.00 $24.35 $27.00 $23.00 $33.00 $24.50 $40.00 $28.25
11613(L) 4516 28" X 20" PREFAB. CULVERT END SECTION, ARCH2EA $300.00 $175.00 $140.00 $222.50 $297.00 $300.00 $475.00 $225.00
12501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON60CY $8.00 $8.00 $7.00 $7.92 $6.00 $26.75 $15.00 $10.00
13501(D) 6353 UNCLASSIFIED BACKFILL40CY $8.00 $10.00 $10.00 $15.50 $12.00 $70.00 $15.00 $10.00
14503(B) 6144 PRESTRESSED CONCRETE DOUBLE TEE194LF $200.00 $199.00 $218.00 $210.00 $212.00 $220.00 $200.00 $239.00
15504(D) 6239 CONCRETE RAIL (TR3)145LF $65.00 $55.00 $55.00 $71.00 $55.00 $65.00 $70.00 $60.00
16509(A) 1326 CLASS AA CONCRETE35CY $600.00 $425.00 $500.00 $524.00 $700.00 $625.00 $550.00 $510.00
17509(B) 1328 CLASS A CONCRETE28.2CY $600.00 $425.00 $500.00 $559.00 $600.00 $625.00 $550.00 $510.00
18511(A) 1332 REINFORCING STEEL10,424LB $0.7500 $0.9500 $0.9000 $0.8800 $0.7500 $1.00 $1.10 $1.07
19514(A) 6010 PILES, FURNISHED (HP 10X42)330LF $20.00 $25.73 $24.00 $27.65 $32.00 $28.00 $42.00 $28.50
20514(B) 6292 PILES, DRIVEN (HP 10X42)330LF $10.00 $15.00 $11.00 $11.85 $17.00 $15.00 $5.00 $10.00
21601(B) 1353 TYPE I-A PLAIN RIPRAP500TON $30.00 $31.00 $37.00 $31.31 $35.00 $45.00 $25.00 $33.20
22601(C) 1355 TYPE I-A FILTER BLANKET90TON $25.00 $29.00 $29.00 $30.46 $28.00 $37.25 $27.00 $35.00
23619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $6,000.00 $5,000.00 $3,000.00 $3,820.00 $5,400.00 $5,000.00 $5,000.00 $6,000.00
24623(F) 6033 GUARDRAIL ANCHOR UNIT (TYPE II)4EA $2,000.00 $2,050.00 $2,150.00 $2,237.50 $2,100.00 $2,000.00 $2,250.00 $2,000.00
25880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $3,000.00 $3,000.00 $2,420.00 $2,400.00 $2,300.00 $2,200.00 $2,550.00 $2,550.00
26642(A) 0095 CONSTRUCTION STAKING LEVEL I1LSUM $3,000.00 $4,750.00 $3,950.00 $4,000.00 $3,800.00 $5,000.00 $2,500.00 $4,620.00
27220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $4,000.00 $1,800.00 $1,000.00 $2,000.00 $5,500.00 $2,000.00 $4,750.00 $2,500.00
28641 1399 MOBILIZATION1LSUM $17,018.35 $12,000.00 $4,000.00 $14,200.00 $7,500.00 $16,650.00 $17,000.00 $16,500.00