| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$4,000.00 |
$4,000.00 |
$4,500.00 |
$5,750.00 |
$5,000.00 |
$2,500.00 |
$5,000.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 2,051 | CY |
$7.00 |
$6.30 |
$5.00 |
$4.85 |
$5.20 |
$3.50 |
$10.00 |
$7.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 6,041 | CY |
$10.00 |
$5.50 |
$7.00 |
$5.90 |
$6.65 |
$5.00 |
$8.00 |
$7.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 2,100 | LF |
$2.10 |
$1.50 |
$1.50 |
$1.10 |
$2.00 |
$1.55 |
$1.95 |
$1.30 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 240 | LF |
$10.00 |
$8.00 |
$8.00 |
$6.65 |
$6.00 |
$7.00 |
$5.00 |
$6.95 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 7,976 | SY |
$1.30 |
$1.65 |
$1.55 |
$1.57 |
$1.65 |
$1.49 |
$1.75 |
$1.40 |
| 7 | 233(A) 2817 |
VEGETATIVE MULCHING | 4 | AC |
$300.00 |
$450.00 |
$550.00 |
$150.00 |
$400.00 |
$500.00 |
$750.00 |
$450.00 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,146 | TON |
$25.00 |
$23.00 |
$26.00 |
$23.77 |
$22.00 |
$26.50 |
$23.00 |
$31.60 |
| 9 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$300.00 |
$200.00 |
$300.00 |
$225.00 |
$300.00 |
$250.00 |
$175.00 |
$360.00 |
| 10 | 613(B) 4528 |
28" X 20" CORR. GALV. STEEL PIPE ARCH | 46 | LF |
$25.00 |
$24.35 |
$27.00 |
$23.00 |
$33.00 |
$24.50 |
$40.00 |
$28.25 |
| 11 | 613(L) 4516 |
28" X 20" PREFAB. CULVERT END SECTION, ARCH | 2 | EA |
$300.00 |
$175.00 |
$140.00 |
$222.50 |
$297.00 |
$300.00 |
$475.00 |
$225.00 |
| 12 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 60 | CY |
$8.00 |
$8.00 |
$7.00 |
$7.92 |
$6.00 |
$26.75 |
$15.00 |
$10.00 |
| 13 | 501(D) 6353 |
UNCLASSIFIED BACKFILL | 40 | CY |
$8.00 |
$10.00 |
$10.00 |
$15.50 |
$12.00 |
$70.00 |
$15.00 |
$10.00 |
| 14 | 503(B) 6144 |
PRESTRESSED CONCRETE DOUBLE TEE | 194 | LF |
$200.00 |
$199.00 |
$218.00 |
$210.00 |
$212.00 |
$220.00 |
$200.00 |
$239.00 |
| 15 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 145 | LF |
$65.00 |
$55.00 |
$55.00 |
$71.00 |
$55.00 |
$65.00 |
$70.00 |
$60.00 |
| 16 | 509(A) 1326 |
CLASS AA CONCRETE | 35 | CY |
$600.00 |
$425.00 |
$500.00 |
$524.00 |
$700.00 |
$625.00 |
$550.00 |
$510.00 |
| 17 | 509(B) 1328 |
CLASS A CONCRETE | 28.2 | CY |
$600.00 |
$425.00 |
$500.00 |
$559.00 |
$600.00 |
$625.00 |
$550.00 |
$510.00 |
| 18 | 511(A) 1332 |
REINFORCING STEEL | 10,424 | LB |
$0.7500 |
$0.9500 |
$0.9000 |
$0.8800 |
$0.7500 |
$1.00 |
$1.10 |
$1.07 |
| 19 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 330 | LF |
$20.00 |
$25.73 |
$24.00 |
$27.65 |
$32.00 |
$28.00 |
$42.00 |
$28.50 |
| 20 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 330 | LF |
$10.00 |
$15.00 |
$11.00 |
$11.85 |
$17.00 |
$15.00 |
$5.00 |
$10.00 |
| 21 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 500 | TON |
$30.00 |
$31.00 |
$37.00 |
$31.31 |
$35.00 |
$45.00 |
$25.00 |
$33.20 |
| 22 | 601(C) 1355 |
TYPE I-A FILTER BLANKET | 90 | TON |
$25.00 |
$29.00 |
$29.00 |
$30.46 |
$28.00 |
$37.25 |
$27.00 |
$35.00 |
| 23 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$6,000.00 |
$5,000.00 |
$3,000.00 |
$3,820.00 |
$5,400.00 |
$5,000.00 |
$5,000.00 |
$6,000.00 |
| 24 | 623(F) 6033 |
GUARDRAIL ANCHOR UNIT (TYPE II) | 4 | EA |
$2,000.00 |
$2,050.00 |
$2,150.00 |
$2,237.50 |
$2,100.00 |
$2,000.00 |
$2,250.00 |
$2,000.00 |
| 25 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$3,000.00 |
$3,000.00 |
$2,420.00 |
$2,400.00 |
$2,300.00 |
$2,200.00 |
$2,550.00 |
$2,550.00 |
| 26 | 642(A) 0095 |
CONSTRUCTION STAKING LEVEL I | 1 | LSUM |
$3,000.00 |
$4,750.00 |
$3,950.00 |
$4,000.00 |
$3,800.00 |
$5,000.00 |
$2,500.00 |
$4,620.00 |
| 27 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$4,000.00 |
$1,800.00 |
$1,000.00 |
$2,000.00 |
$5,500.00 |
$2,000.00 |
$4,750.00 |
$2,500.00 |
| 28 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$17,018.35 |
$12,000.00 |
$4,000.00 |
$14,200.00 |
$7,500.00 |
$16,650.00 |
$17,000.00 |
$16,500.00 |