BRIDGE AND APPROACHES COUNTY ROAD (NS-175): OVER CAMP HOLLOW CREEK , 4.0 MILES NORTH OF SH -47. PROJECT LENGTH = 0.101 MILES
- Let date
- Thursday, August 18, 2011
- Contract
- 110389
- J/P numbers
- 28023(04)
- District
- Division 5
- County
- Roger Mills
- Highway
- Limits
- BRIDGE AND APPROACHES COUNTY ROAD (NS-175): OVER CAMP HOLLOW CREEK , 4.0 MILES NORTH OF SH -47. PROJECT LENGTH = 0.101 MILES
- Project number
- BRO-165D(118)CI
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | SEWELL BROS., INC. Low bidder | $184,804 | ||
| 2 | K & R BUILDERS, INC. | $198,834 | +7.6% | |
| 3 | KLAVER CONSTRUCTION COMPANY, INC. | $212,074 | +14.8% | |
| 4 | WITTWER CONSTRUCTION CO., INC. | $214,147 | +15.9% | |
| 5 | Cimarron Construction Company, LLC | $242,590 | +31.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SEWELL BROS., I… | #2 K & R BUILDERS,… | #3 KLAVER CONSTRUC… | #4 WITTWER CONSTRU… | #5 Cimarron Constr… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $20,000.00 | $7,500.00 | $15,840.00 | $20,000.00 | $20,000.00 | $25,000.00 |
| 2 | 221(C) 2801 | TEMPORARY SILT FENCE | 1,300 | LF | $2.00 | $2.00 | $1.20 | $1.80 | $1.49 | $2.00 |
| 3 | 230(A) 2806 | SOLID SLAB SODDING | 4,600 | SY | $1.75 | $1.25 | $1.34 | $1.15 | $1.39 | $1.25 |
| 4 | 233(A) 2817 | VEGETATIVE MULCHING | 0.95 | AC | $500.00 | $440.00 | $200.00 | $400.00 | $463.50 | $400.00 |
| 5 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 221 | TON | $28.00 | $29.00 | $35.25 | $28.00 | $28.00 | $33.00 |
| 6 | 509(D) 0325 | CLASS C CONCRETE | 45.3 | CY | $275.00 | $300.00 | $320.00 | $300.00 | $225.00 | $300.00 |
| 7 | 202(A) 1301 | UNCLASSIFIED EXCAVATION | 1,280 | CY | $15.00 | $5.00 | $5.15 | $8.00 | $6.00 | $6.00 |
| 8 | 501(A) 1306 | STRUCTURAL EXCAVATION UNCLASSIFIED | 96 | CY | $15.00 | $7.00 | $10.70 | $10.00 | $12.00 | $10.00 |
| 9 | 509(B) 1328 | CLASS A CONCRETE | 209.1 | CY | $525.00 | $400.00 | $375.00 | $483.00 | $400.00 | $525.00 |
| 10 | 511(A) 1332 | REINFORCING STEEL | 39,305 | LB | $0.9500 | $0.9000 | $0.8600 | $0.9000 | $1.00 | $0.9500 |
| 11 | 601(B) 1353 | TYPE I-A PLAIN RIPRAP | 180 | TON | $40.00 | $40.00 | $47.90 | $40.00 | $45.00 | $53.00 |
| 12 | 601(C) 1355 | TYPE I-A FILTER BLANKET | 60 | TON | $32.00 | $40.00 | $40.30 | $32.00 | $42.00 | $53.00 |
| 13 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $2,050.00 | $2,420.00 | $1,950.00 | $2,008.50 | $2,500.00 |
| 14 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $7,500.00 | $3,300.00 | $3,400.00 | $1,500.00 | $3,090.00 | $3,000.00 |
| 15 | 220 2800 | SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM | $7,500.00 | $1,000.00 | $1,900.00 | $1,500.00 | $1,500.00 | $5,000.00 |
| 16 | 641 1399 | MOBILIZATION | 1 | LSUM | $15,000.00 | $6,500.00 | $14,200.00 | $2,646.00 | $20,000.00 | $9,000.00 |